- •MODERN
- •POWER STATION PRACTICE
- •PERGAMON PRESS
- •Contents
- •Foreword
- •G. A. W. Blackman, CBE, FEng
- •Preface
- •Chapters 1 and 2
- •Chapter 3
- •Contents of All Volumes
- •CHAPTER 1
- •Power station siting and site layout
- •1 Planning for new power stations
- •1.1 Introduction
- •1.2 Capacity considerations
- •1.3 Economic considerations
- •1.4 Future requirement predictions
- •1.5 System planning studies
- •1.6 Authority to build a new power station
- •2 Site selection and investigation
- •2.1 Basic site requirements
- •2.3 Detailed site investigation
- •2.4 Environmental considerations
- •2.5 Site selection
- •3 Site layout — thermal power stations
- •3.1 General
- •3.2 Foundations
- •3.3 Site and station levels
- •3.4 Main buildings and orientation
- •3.5 Ancillary buildings
- •3.6 Main access and on-site roads
- •3.7 Station operation considerations
- •3.8 Cooling water system
- •3.9 Fuel supplies and storage
- •3.10 Ash and dust disposal
- •3.11 Flue gas desulphurisation plant materials
- •3.12 Transmission requirements
- •3.13 Construction requirements
- •3.14 Amenity considerations
- •3.15 Typical site layouts
- •4 Pumped storage
- •4.1 Introduction.
- •4.2 Suitable topology
- •4.3 Ground conditions
- •4.4 Site capacity
- •4.5 System and transmission requirements
- •4.7 Heavy load access
- •4.9 Environmental impact
- •5 Gas turbines
- •5.1 Introduction
- •5.2 The role of gas turbines
- •4.7 Heavy load access
- •Station design and layout
- •1 Introduction
- •2.1 Fossil-fired stations
- •2.2 Nuclear stations
- •2.3 Hydro-electric and pumped storage stations
- •2.4 Gas turbine stations
- •3 Future development options
- •3.1 Fossil-fired plant
- •3.2 Nuclear stations
- •3.3 Combined cycle gas turbines
- •3.4 Wind power
- •3.5 Tidal power
- •3.6 Geothermal energy
- •3.7 Combined heat and power
- •4 Station design concepts
- •4.1 Basic considerations
- •4.2 Design objectives
- •5 Plant operation
- •6 Station layout
- •6.1 General
- •6.2 Main plant orientation
- •6.3 Layout conventions
- •.7 Turbine-generator systems
- •7.1 Feedheating plant
- •7.2 Condenser and auxiliary plant
- •7.3 Erection and maintenance
- •8 Boiler systems
- •8.1 Pulverised fuel system
- •8.2 Draught system
- •8.3 Oil firing system
- •8.4 Boiler fittings
- •8.5 Dust extraction plant
- •8.6 Flue gas desulphurisation plant
- •9 Main steam pipework
- •10 Low pressure pipework and valves
- •11 Water storage tanks
- •12 Cranes
- •13 Fire protection
- •13.1 Introduction
- •13.2 Prevention of fires
- •13.3 Limiting the consequences of a fire
- •13.4 Reducing the severity of fires
- •14 Electrical plant layout
- •14.1 Introduction
- •14.2 Auxiliary switchgear
- •14.3 Turbine-generator auxiliaries
- •14.4 Main connections
- •14.5 Transformers
- •14.6 Cables
- •14.7 Batteries and charging equipment
- •14.8 Control rooms
- •15 Heating, ventilation and air conditioning
- •15.1 Introduction
- •15.2 Ventilation of nuclear stations
- •15.3 Smoke and fire control
- •15.4 General layout of HVAC plant
- •16 Air services
- •17 Water treatment plant
- •18 Cooling water plant
- •18.1 General design considerations
- •18.2 Cooling water pumphouse
- •18.3 Main cooling water pumps
- •18.4 Screening plant
- •18.5 Pump discharge valves
- •18.6 Section valves
- •18.7 Discharge pipework
- •18.8 Auxiliary systems
- •19 Chlorination plant
- •20 Coal handling plant
- •20.2 Water-borne reception and discharging
- •20.3 Road-borne reception and discharging
- •20.4 Coal storage
- •20.5 Conveyance from unloading point to station bunkers or coal store
- •20.6 Plant control
- •21 Ash and dust handling plant
- •21.1 Ash handling plant
- •21.2 Dust handling plant
- •21.3 Ash and dust disposal
- •22 Auxiliary boilers
- •23 Gas generation and storage
- •23.1 Hydrogen
- •23.2 Carbon dioxide
- •23.3 Nitrogen
- •23.4 Miscellaneous gases
- •24 Pumped storage plant
- •24.1 Hydraulic machines
- •24.2 Generator-motors
- •24.3 Main inlet valves
- •24.4 Draft tube valves
- •24.5 Gates
- •24.6 High integrity pipework
- •25 Gas turbine plant
- •25.1 Introduction
- •25.2 Operational requirements
- •25.3 Aero-engine-derivative gas turbines
- •25.4 Industrial gas turbines
- •25.5 Gas turbine power station layout
- •26 References
- •CHAPTER 3
- •Civil engineering and building works
- •Introduction
- •2 Geotechnical investigations
- •2.1 General and desk studies
- •2.2 Geophysical investigations
- •2.3 Trial excavations and boreholes
- •2.3 Trial excavations and boreholes
- •2.4 In-situ tests
- •2.5 Groundwater investigations
- •2.6 Ground description and classification
- •2.7 Laboratory tests
- •2.8 Factual reports
- •2.9 Interpretation of site investigations
- •3 Seismic hazard assessment
- •3.1 Geology
- •3.2 Earthquakes
- •3.3 Crustal dynamics
- •3.4 Ground motion hazard
- •3.5 Ground rupture hazard
- •4 Types of foundations
- •4.1 Isolated column foundations
- •4.2 Strip foundations
- •4.5 Piled foundations
- •4.5 Piled foundations
- •4.6 Caisson foundations
- •4.7 Anti-seismic foundations
- •5 Foundations design and construction
- •5.1 Concrete
- •5.2 Bearing pressures and settlement
- •5.3 Test piling
- •6 Foundations for main and secondary structures
- •6.1 Boiler house foundations
- •6.2 Turbine hall foundations
- •6.3 Turbine-generator blocks
- •6.4 Basement of ground floor
- •6.5 Track hoppers
- •6.6 Chimney foundations
- •6.7 Cooling tower foundations
- •6.8 Reactor foundations
- •7 General site works
- •7.1 Flood embankments
- •7.2 Roads
- •7.3 Drainage
- •7.4 Railways
- •7.5 Coal storage
- •7.3 Oil tank compounds
- •7.7 Ash disposal areas
- •8 Methods of construction
- •8.1 Site clearance, access roads and construction offices
- •8.2 Underground construction
- •8.3 Groundwater lowering
- •8.4 Excavating machinery
- •8.6 Formwork and reinforcement
- •8.7 Mixing and placing of concrete
- •9 Direct cooled circulating water systems
- •9.1 Civil engineering structures in direct cooling systems
- •9.2 Culverts
- •3.3 Pumphouse and screen chamber intake
- •9.4 Cooling water tunnels
- •9.5 Submersible cooling water structures
- •9.6' Maintenance considerations
- •10 Harbours and jetties
- •10.1 General
- •10.2 Types of harbours and jetties
- •10.3 Construction of harbours and jetties
- •11 Loadings
- •11.1 Definitions
- •11.2 Imposed loads due <o plant
- •11.3 Distributed imposed loads
- •II. 6 Reduced loadings in main beams and columns
- •11.4 Cranes
- •11.5 Wind and snow loads
- •12 Steel frames
- •12.1 Steelwork
- •13 Reinforced concrete
- •13.1 General
- •13.2 Formwork
- •13.3 Reinforcement
- •1^.4 Design of reinforced concrete
- •12.2 Design of members
- •12.3 Connections
- •12.4 Protection of steelwork
- •13.5 Movement joints
- •13.6 Curing
- •13.7 Precast concrete
- •14 Prestressed concrete
- •14.1 Prestressing
- •14.2 Prestressed piling
- •14.2 Prestressed piling
- •14.3 Prestressed concrete pressure vessels and containments
- •15 Brickwork and blockwork
- •15.1 General
- •15.2 Bricks
- •15.3 Mortar
- •15.4 Brickwork
- •15.5 Blocks
- •15.8 Openings
- •15.6 Blockwork
- •16 Lightweight walling systems
- •16.1 Sheeting
- •16.2 Insulation
- •16.3 Fixings
- •16.4 Durability
- •17 Roofing
- •17.1 Structural elements
- •17.2 Insulation and weatherproofing layers
- •17.3 Application to power stations
- •17.4 Durability
- •17.5 Rainwater disposal
- •18 Finishes
- •18.1 Floor finish considerations
- •18.2 Types of floor finish
- •18.3 Finishes to walls and ceilings
- •18.4 Wall tiling and other special finishes
- •18.5 Internal painting
- •18^6 External painting
- •19 Turbine hall and boiler house construction
- •19.1 General
- •19.2 Structural considerations
- •19.3 Erection of steelwork
- •19.4 ''Cladding
- •19.5 Ventilation
- •19.6 Floor and wall finishes
- •20 Reactor construction
- •20.1 Reactors
- •20.2 Reactor buildings
- •21.2 Control room building
- •21.3 Gas turbine house
- •21.4 CW pumphouse
- •21.6 Workshops and stores
- •21.7 Offices, welfare blocks, laboratories and similar buildings
- •22 Chimneys, cooling towers and precipitators
- •22.1 Chimneys
- •22.2 Cooling towers
- •22.3 Precipitators
- •23 Architecture and landscape
- •23.1 General power station architecture
- •23.2 Landscape considerations
- •23.3 Preparatory works
- •23.4 Landscape layout
- •24 Regulations
- •24.1 Government instruments
- •24.2 Factories Act
- •24.4 Building regulations
- •24.5 Nuclear station licensing
- •25 Civil engineering contracts
- •25.2 Forms of contract
- •25.3 Contract strategy
- •25.4 Contract placing
- •25.5 Contract administration
- •25.6 Budgetary approval and control
- •26 References
- •Appendix A
- •SUBJECT INDEX
arrangement conceals the pipe and reduces the chance of damage by water due to a stopped pipe bursting at a joint. Cast iron, aluminium, and rigid plastic pipes are used for rainwater dispersal.
18Finishes
18.1Floor finish considerations
The following basic factors should be considered in choosing a suitable floor finish to a given area:
•Durability — the floor finish must have the ability to withstand the traffic. Maintenance appropriate to its location is essential for longevity.
•Appearance — which may be of prime importance or of little consequence depending upon location.
•Cost — capital, maintenance and the expected lifetime are the key interdependent parameters of total economic choice.
•Surface finish — highly polished surfaces will show
variations in surface levelling; anti-slip properties may be important, particularly in areas of spillage, e.g., kitchens, laboratories, etc.
•Acoustic properties — sound absorption may be
required in certain areas, e.g., control rooms, offices, conference rooms, corridors, etc.
•Fire resistance — in areas of high fife risk, low flame spread and low smoke emission materials may be of particular importance.
•Access to services — specially raised access floors may be required in computer rooms, cable areas,
,etc.
•Special requirements — floors used in conjunction with under-floor heating, or in areas of potential
chemical or radiation contamination will require special materials..
• Thermal movement — suitable expansion and con traction joints may be required where differential expansion characteristics of sub-floor and floor finish may be experienced.
18.2 Types of floor finish
Having assessed the requirements of a floor finish in a particular location a selection can be made and some of the more common types available are as follows:
Trowelled concrete This is a means of obtaining a cheap, reasonable finish to a concrete slab. The con crete is trowelled smooth by hand or by machine (power floating) and the surface can be. treated with a proprietary anti-dust silicate sealant. This method can provide a suitable surface for the application of other sheet or liquid resin floor finishes. Its tendency to dust
Finishes
under traffic can be resisted by the application of cheap penetrative sealants.
Granolithic finish This finish is applied to concrete floors and consists of a layer of concrete made from fine granite chippings and cement. The granite aggregate is graded in size from chippings down to dust. It gives a superior finish to concrete, being harder and less absorbent. This finish can be applied to set concrete, but is not recommended due to inherent problems of adhesion. It is better laid on ‘green’ concrete, or integrally with the concrete, to ensure a good bond and to avoid differential shrinkage of the floor and finish. The thickness laid varies from 50 mm to 75 mm and depends upon the location on the floor. The thickness can be reduced if it is laid monolithic with the concrete, which will also ensure the most positive bond with the base concrete.
Terrazzo This is an expensive finish consisting of marble chippings set in white cement. The surface is ground and polished to a flat surface after the cement has hardened. It can be laid in-situ or as tiles. This finish is very impermeable and hygienic but is so brittle that cracking occurs very easily. Expansion and con traction joints must be very carefully located. Specialist armoured terrazzo tiles are manufactured which are quite suitable for turbine hall floors and other heavy duty areas, albeit expensive.
Quarry and other vitreous tiles These are made from burnt clay and have good acid-resisting properties. Tiles can be obtained in a variety of colours with rough or smooth surfaces. Purpose-made tiles can be obtained to form coves, skirtings and other similar features. They can be set and jointed in cement or, alternatively, in a proprietary jointing compound which remains slightly plastic after setting and thus prevents failure by differential movement of the finish and slab. The fullyvitrified tiles are impermeable and are suitable for areas subject to contamination in reactor buildings.
Wood Hardwood boards or blocks are the timbers usually used for floor finishes in power stations, although softwood boards are sometimes used to pro vide a base for a further covering. Timbers vary and although good results can be obtained from the best hardwoods such as maple boards or oak blocks, other types of wood flqors are not suitable for heavy traffic. Wood blocks laid with their grain vertical make an excellent floor finish for workshops and similar loca tions. The end grain gives good wearing characteristics and the nature of the surfaces means that there is a smaller chance of damage to castings and similar items placed on or moved across the floor. These blocks are often set in pitch and should not be used where the risk of fire is high.
Wood fibre blocks These are made from recon structed timber and are very similar to wood blocks.
Sheet floorings These include linoleum, rubber and PVC. They are usually Secured to a timber or cement
265
Civil engineering and building works
scored base by means of a suitable adhesive. They give a good impervious hygienic finish which is not difficult to keep clean but they are not suitable lor areas of heavy traffic.
Plastjc tiles These are similar to sheet floors but in tileform. They are more easily laid, but hase the disadvantage of many joints which are vulnerable to moisture spillage and consequent loss of adhesion, together with an inherent tendency to curl in lesser quality tiles.
In-situ composition floors 'lhese include asphalt, magnesium oxychloride, epoxide resins and many other types of finish. The quality and type of finish can be varied to resist acids, alkalis and other contaminants. Such special materials normally fall outside the architect’s or civil engineer’s experience and specialist advice is sought before adoption.
18.3 Finishes to walls and ceilings
For many power station buildings of brick and concrete construction a fair finish and flush pointing to the brick work together with a good finish to the concrete is adequate. Plastering, rendering and similar treatments to walls and ceilings are called wet processes. Although •satisfactory results are usually obtained, the time taken by application of these finishes together with the drying out periods which must be allowed before decoration can commence have led to the development of dry finishes. These include ceilings constructed by plastic sheet, insulation board, hardboard, metal trays and other materials which can be supported by hangers from the roof to provide a space above the ceiling for ducts and services. Insulation boards on the inside of sheet cladding and unit partitions in office blocks tire typical examples of this type of finish. Many such panels can be supplied ready decorated if required.
Special finishes such as vermiculite spray can be applied in thicknesses usually between 25 mm and 50 mm to concrete, steelwork or other surfaces. Although occasionally used for insulation, the main function of these finishes is the protection of steelwork against fire.
18.4 Wall tiling and other special finishes
In kitchens, toilets, medical centres or similar locations where walls are subject to contamination by grease, dirt or corrosive substances and a high degree of hygiene is necessary, the conditions and frequent washings re quire the use of a better surface than is obtainable with a paint finish. In these circumstances glazed or unglazed
. wall tiles, in-situ terrazzo or terrazzo tiles, plastics or similar materials are used for the finish to wall surfaces. Particular attention to such decontaminabie finishes is paid in the design of those areas of nuclear stations vulnerable to radioactive contamination.
Chapter 3
18.5 Internal painting
Apart from protecting the steelwork, internal painting is used mainly for decorative reasons and is usually carried out in accordance with schemes prepared by the architects. For painting on timber, concrete, brick work, plaster, metal or similar surfaces, the basic system is usually as follows:
(a)Cleaning down and surface preparation Before painting, all loose material should be removed and
■all surfaces thoroughly cleaned. A vacuum plain should be provided lor the removal of dust. Clean liness of the base prior to application of any protective coating is of paramount importance.
(b)Priming coat This seals and prepares the surface and also provides a key for subsequent coats of
paint. It can also be used to protect a material during the constructional stages before the final coatings are applied near to station completion. Aluminium or conventional wood primers are normally used for timber, and alkali-resisting primers for the surfaces of new plaster, concrete, brickwork and similar surfaces. For ferrous metals a zinc phosphate or other approved rust inhibiting primer is suitable, and for galvanised surfaces an etch primer followed by a zinc phosphate primer should be used.
(c)Undercoats One or two coats of paint is the usual specification for undercoats, using a paint which is compatible with the primer and finishing coat.
(d)Finishing coats These arc normally alkyd-based resin paints or similar materials which give a hard durable finish. They can be supplied to give a matt, semi-gloss or high gloss finish.
(e)Other paints A more economic but less durable finish can be obtained on brickwork, plaster, concrete and similar surfaces by the use of emul sion paints.
18^6 External painting
Although the decorative aspect of external painting must receive some consideration especially on the main buildings, offices, welfare blocks and similar buildings, there are many locations such as precipitator steelwork, coal gantry steelwork, external plant and other similar items where protection is of prime importance and appearance of less importance. External painting is carried out using preparations and materials similar to those used for internal work with the addition of micaceous iron oxide, chlorinated rubber, polyurethene, epoxy, acrylated rubber, vinyl acrylic and glass flake systems as required, depending on the local climate and in-service environment envisaged for the protective coating.
266