- •MODERN
- •POWER STATION PRACTICE
- •PERGAMON PRESS
- •Contents
- •Foreword
- •G. A. W. Blackman, CBE, FEng
- •Preface
- •Chapters 1 and 2
- •Chapter 3
- •Contents of All Volumes
- •CHAPTER 1
- •Power station siting and site layout
- •1 Planning for new power stations
- •1.1 Introduction
- •1.2 Capacity considerations
- •1.3 Economic considerations
- •1.4 Future requirement predictions
- •1.5 System planning studies
- •1.6 Authority to build a new power station
- •2 Site selection and investigation
- •2.1 Basic site requirements
- •2.3 Detailed site investigation
- •2.4 Environmental considerations
- •2.5 Site selection
- •3 Site layout — thermal power stations
- •3.1 General
- •3.2 Foundations
- •3.3 Site and station levels
- •3.4 Main buildings and orientation
- •3.5 Ancillary buildings
- •3.6 Main access and on-site roads
- •3.7 Station operation considerations
- •3.8 Cooling water system
- •3.9 Fuel supplies and storage
- •3.10 Ash and dust disposal
- •3.11 Flue gas desulphurisation plant materials
- •3.12 Transmission requirements
- •3.13 Construction requirements
- •3.14 Amenity considerations
- •3.15 Typical site layouts
- •4 Pumped storage
- •4.1 Introduction.
- •4.2 Suitable topology
- •4.3 Ground conditions
- •4.4 Site capacity
- •4.5 System and transmission requirements
- •4.7 Heavy load access
- •4.9 Environmental impact
- •5 Gas turbines
- •5.1 Introduction
- •5.2 The role of gas turbines
- •4.7 Heavy load access
- •Station design and layout
- •1 Introduction
- •2.1 Fossil-fired stations
- •2.2 Nuclear stations
- •2.3 Hydro-electric and pumped storage stations
- •2.4 Gas turbine stations
- •3 Future development options
- •3.1 Fossil-fired plant
- •3.2 Nuclear stations
- •3.3 Combined cycle gas turbines
- •3.4 Wind power
- •3.5 Tidal power
- •3.6 Geothermal energy
- •3.7 Combined heat and power
- •4 Station design concepts
- •4.1 Basic considerations
- •4.2 Design objectives
- •5 Plant operation
- •6 Station layout
- •6.1 General
- •6.2 Main plant orientation
- •6.3 Layout conventions
- •.7 Turbine-generator systems
- •7.1 Feedheating plant
- •7.2 Condenser and auxiliary plant
- •7.3 Erection and maintenance
- •8 Boiler systems
- •8.1 Pulverised fuel system
- •8.2 Draught system
- •8.3 Oil firing system
- •8.4 Boiler fittings
- •8.5 Dust extraction plant
- •8.6 Flue gas desulphurisation plant
- •9 Main steam pipework
- •10 Low pressure pipework and valves
- •11 Water storage tanks
- •12 Cranes
- •13 Fire protection
- •13.1 Introduction
- •13.2 Prevention of fires
- •13.3 Limiting the consequences of a fire
- •13.4 Reducing the severity of fires
- •14 Electrical plant layout
- •14.1 Introduction
- •14.2 Auxiliary switchgear
- •14.3 Turbine-generator auxiliaries
- •14.4 Main connections
- •14.5 Transformers
- •14.6 Cables
- •14.7 Batteries and charging equipment
- •14.8 Control rooms
- •15 Heating, ventilation and air conditioning
- •15.1 Introduction
- •15.2 Ventilation of nuclear stations
- •15.3 Smoke and fire control
- •15.4 General layout of HVAC plant
- •16 Air services
- •17 Water treatment plant
- •18 Cooling water plant
- •18.1 General design considerations
- •18.2 Cooling water pumphouse
- •18.3 Main cooling water pumps
- •18.4 Screening plant
- •18.5 Pump discharge valves
- •18.6 Section valves
- •18.7 Discharge pipework
- •18.8 Auxiliary systems
- •19 Chlorination plant
- •20 Coal handling plant
- •20.2 Water-borne reception and discharging
- •20.3 Road-borne reception and discharging
- •20.4 Coal storage
- •20.5 Conveyance from unloading point to station bunkers or coal store
- •20.6 Plant control
- •21 Ash and dust handling plant
- •21.1 Ash handling plant
- •21.2 Dust handling plant
- •21.3 Ash and dust disposal
- •22 Auxiliary boilers
- •23 Gas generation and storage
- •23.1 Hydrogen
- •23.2 Carbon dioxide
- •23.3 Nitrogen
- •23.4 Miscellaneous gases
- •24 Pumped storage plant
- •24.1 Hydraulic machines
- •24.2 Generator-motors
- •24.3 Main inlet valves
- •24.4 Draft tube valves
- •24.5 Gates
- •24.6 High integrity pipework
- •25 Gas turbine plant
- •25.1 Introduction
- •25.2 Operational requirements
- •25.3 Aero-engine-derivative gas turbines
- •25.4 Industrial gas turbines
- •25.5 Gas turbine power station layout
- •26 References
- •CHAPTER 3
- •Civil engineering and building works
- •Introduction
- •2 Geotechnical investigations
- •2.1 General and desk studies
- •2.2 Geophysical investigations
- •2.3 Trial excavations and boreholes
- •2.3 Trial excavations and boreholes
- •2.4 In-situ tests
- •2.5 Groundwater investigations
- •2.6 Ground description and classification
- •2.7 Laboratory tests
- •2.8 Factual reports
- •2.9 Interpretation of site investigations
- •3 Seismic hazard assessment
- •3.1 Geology
- •3.2 Earthquakes
- •3.3 Crustal dynamics
- •3.4 Ground motion hazard
- •3.5 Ground rupture hazard
- •4 Types of foundations
- •4.1 Isolated column foundations
- •4.2 Strip foundations
- •4.5 Piled foundations
- •4.5 Piled foundations
- •4.6 Caisson foundations
- •4.7 Anti-seismic foundations
- •5 Foundations design and construction
- •5.1 Concrete
- •5.2 Bearing pressures and settlement
- •5.3 Test piling
- •6 Foundations for main and secondary structures
- •6.1 Boiler house foundations
- •6.2 Turbine hall foundations
- •6.3 Turbine-generator blocks
- •6.4 Basement of ground floor
- •6.5 Track hoppers
- •6.6 Chimney foundations
- •6.7 Cooling tower foundations
- •6.8 Reactor foundations
- •7 General site works
- •7.1 Flood embankments
- •7.2 Roads
- •7.3 Drainage
- •7.4 Railways
- •7.5 Coal storage
- •7.3 Oil tank compounds
- •7.7 Ash disposal areas
- •8 Methods of construction
- •8.1 Site clearance, access roads and construction offices
- •8.2 Underground construction
- •8.3 Groundwater lowering
- •8.4 Excavating machinery
- •8.6 Formwork and reinforcement
- •8.7 Mixing and placing of concrete
- •9 Direct cooled circulating water systems
- •9.1 Civil engineering structures in direct cooling systems
- •9.2 Culverts
- •3.3 Pumphouse and screen chamber intake
- •9.4 Cooling water tunnels
- •9.5 Submersible cooling water structures
- •9.6' Maintenance considerations
- •10 Harbours and jetties
- •10.1 General
- •10.2 Types of harbours and jetties
- •10.3 Construction of harbours and jetties
- •11 Loadings
- •11.1 Definitions
- •11.2 Imposed loads due <o plant
- •11.3 Distributed imposed loads
- •II. 6 Reduced loadings in main beams and columns
- •11.4 Cranes
- •11.5 Wind and snow loads
- •12 Steel frames
- •12.1 Steelwork
- •13 Reinforced concrete
- •13.1 General
- •13.2 Formwork
- •13.3 Reinforcement
- •1^.4 Design of reinforced concrete
- •12.2 Design of members
- •12.3 Connections
- •12.4 Protection of steelwork
- •13.5 Movement joints
- •13.6 Curing
- •13.7 Precast concrete
- •14 Prestressed concrete
- •14.1 Prestressing
- •14.2 Prestressed piling
- •14.2 Prestressed piling
- •14.3 Prestressed concrete pressure vessels and containments
- •15 Brickwork and blockwork
- •15.1 General
- •15.2 Bricks
- •15.3 Mortar
- •15.4 Brickwork
- •15.5 Blocks
- •15.8 Openings
- •15.6 Blockwork
- •16 Lightweight walling systems
- •16.1 Sheeting
- •16.2 Insulation
- •16.3 Fixings
- •16.4 Durability
- •17 Roofing
- •17.1 Structural elements
- •17.2 Insulation and weatherproofing layers
- •17.3 Application to power stations
- •17.4 Durability
- •17.5 Rainwater disposal
- •18 Finishes
- •18.1 Floor finish considerations
- •18.2 Types of floor finish
- •18.3 Finishes to walls and ceilings
- •18.4 Wall tiling and other special finishes
- •18.5 Internal painting
- •18^6 External painting
- •19 Turbine hall and boiler house construction
- •19.1 General
- •19.2 Structural considerations
- •19.3 Erection of steelwork
- •19.4 ''Cladding
- •19.5 Ventilation
- •19.6 Floor and wall finishes
- •20 Reactor construction
- •20.1 Reactors
- •20.2 Reactor buildings
- •21.2 Control room building
- •21.3 Gas turbine house
- •21.4 CW pumphouse
- •21.6 Workshops and stores
- •21.7 Offices, welfare blocks, laboratories and similar buildings
- •22 Chimneys, cooling towers and precipitators
- •22.1 Chimneys
- •22.2 Cooling towers
- •22.3 Precipitators
- •23 Architecture and landscape
- •23.1 General power station architecture
- •23.2 Landscape considerations
- •23.3 Preparatory works
- •23.4 Landscape layout
- •24 Regulations
- •24.1 Government instruments
- •24.2 Factories Act
- •24.4 Building regulations
- •24.5 Nuclear station licensing
- •25 Civil engineering contracts
- •25.2 Forms of contract
- •25.3 Contract strategy
- •25.4 Contract placing
- •25.5 Contract administration
- •25.6 Budgetary approval and control
- •26 References
- •Appendix A
- •SUBJECT INDEX
20Coal handling plant
20.1Rail-borne reception and discharging
The annual coal consumption of a 2000 MW station, depending on its load factor, amounts to approximately 5 million tonnes, i.c., 20 000 tonnes daily over 250 days. To achieve this delivery rate of coal, trains to large modern power station utilise hopper-bottom wagons on a permanently coupled basis. Permanently coupled working means the keeping together of the main line locomotive and its train of wagons as a single unit, from entering to leaving the site, including discharge over a track unloading hopper.
The advantages of this system are a fast turnround of the train at the power station. It is expected that trains will achieve at least 3.5 trips per week between colliery and power station, thus giving greater wagon utilisation together with capital economy in track work and associated savings in operational costs.
A design of hopper wagon has now been adopted having rapid self-discharging characteristics. This wagon is the 32 tonne capacity. 2-axle wagon with six bottom doors operated automatically by lineside equip ment. It discharges the coal whilst travelling at a speed of approximately 0.24 m/s.
^udi i idriu111 ig piam
The largest train at present envisaged by British Rail is 2070 tonnes gross load, with a payload of 1440 tonnes. The size of the train for this payload will be 45 wagons plus locomotive giving an overall length of 425 m. Accommodation in the sidings layout should
therefore be 500 |
m |
to provide |
working |
clearance. |
Where possible it |
is |
prudent to |
allow |
for greater |
lengths, if site space allows, to provide for longer trains should BR wish to introduce them at some later date. Introduction of light wagon bodies offering lower tare weights, and hence higher payload potential, is also currently being considered.
Depending on the space available and the volume of traffic to be handled, the choice lies between the merry- go-round (MGR) loop system or the run round system. The latter, although necessitating the main line loco motive running round its train, is accepted by BR as permanently coupled working. Figure 2.75 shows the merry-go-round system at a 2000 MW coal-fired station and Figure 2.76 shows the run round system at a 2000 MW coal-fired station.
The CEGB now accepts the weekly delivery of coal over 5 days. Consequently, two sevenths of the daily coal intake is put out to store for reclamation at weekends, when coal is not being delivered. Normally the stations are coaled over two shifts (i.e., 16 hours). However, BR have the right to request the CEGB to
Fig. 2.75 Plan of coal handling plant with merry-go-round system for a 2000 MW station
147