- •MODERN
- •POWER STATION PRACTICE
- •PERGAMON PRESS
- •Contents
- •Foreword
- •G. A. W. Blackman, CBE, FEng
- •Preface
- •Chapters 1 and 2
- •Chapter 3
- •Contents of All Volumes
- •CHAPTER 1
- •Power station siting and site layout
- •1 Planning for new power stations
- •1.1 Introduction
- •1.2 Capacity considerations
- •1.3 Economic considerations
- •1.4 Future requirement predictions
- •1.5 System planning studies
- •1.6 Authority to build a new power station
- •2 Site selection and investigation
- •2.1 Basic site requirements
- •2.3 Detailed site investigation
- •2.4 Environmental considerations
- •2.5 Site selection
- •3 Site layout — thermal power stations
- •3.1 General
- •3.2 Foundations
- •3.3 Site and station levels
- •3.4 Main buildings and orientation
- •3.5 Ancillary buildings
- •3.6 Main access and on-site roads
- •3.7 Station operation considerations
- •3.8 Cooling water system
- •3.9 Fuel supplies and storage
- •3.10 Ash and dust disposal
- •3.11 Flue gas desulphurisation plant materials
- •3.12 Transmission requirements
- •3.13 Construction requirements
- •3.14 Amenity considerations
- •3.15 Typical site layouts
- •4 Pumped storage
- •4.1 Introduction.
- •4.2 Suitable topology
- •4.3 Ground conditions
- •4.4 Site capacity
- •4.5 System and transmission requirements
- •4.7 Heavy load access
- •4.9 Environmental impact
- •5 Gas turbines
- •5.1 Introduction
- •5.2 The role of gas turbines
- •4.7 Heavy load access
- •Station design and layout
- •1 Introduction
- •2.1 Fossil-fired stations
- •2.2 Nuclear stations
- •2.3 Hydro-electric and pumped storage stations
- •2.4 Gas turbine stations
- •3 Future development options
- •3.1 Fossil-fired plant
- •3.2 Nuclear stations
- •3.3 Combined cycle gas turbines
- •3.4 Wind power
- •3.5 Tidal power
- •3.6 Geothermal energy
- •3.7 Combined heat and power
- •4 Station design concepts
- •4.1 Basic considerations
- •4.2 Design objectives
- •5 Plant operation
- •6 Station layout
- •6.1 General
- •6.2 Main plant orientation
- •6.3 Layout conventions
- •.7 Turbine-generator systems
- •7.1 Feedheating plant
- •7.2 Condenser and auxiliary plant
- •7.3 Erection and maintenance
- •8 Boiler systems
- •8.1 Pulverised fuel system
- •8.2 Draught system
- •8.3 Oil firing system
- •8.4 Boiler fittings
- •8.5 Dust extraction plant
- •8.6 Flue gas desulphurisation plant
- •9 Main steam pipework
- •10 Low pressure pipework and valves
- •11 Water storage tanks
- •12 Cranes
- •13 Fire protection
- •13.1 Introduction
- •13.2 Prevention of fires
- •13.3 Limiting the consequences of a fire
- •13.4 Reducing the severity of fires
- •14 Electrical plant layout
- •14.1 Introduction
- •14.2 Auxiliary switchgear
- •14.3 Turbine-generator auxiliaries
- •14.4 Main connections
- •14.5 Transformers
- •14.6 Cables
- •14.7 Batteries and charging equipment
- •14.8 Control rooms
- •15 Heating, ventilation and air conditioning
- •15.1 Introduction
- •15.2 Ventilation of nuclear stations
- •15.3 Smoke and fire control
- •15.4 General layout of HVAC plant
- •16 Air services
- •17 Water treatment plant
- •18 Cooling water plant
- •18.1 General design considerations
- •18.2 Cooling water pumphouse
- •18.3 Main cooling water pumps
- •18.4 Screening plant
- •18.5 Pump discharge valves
- •18.6 Section valves
- •18.7 Discharge pipework
- •18.8 Auxiliary systems
- •19 Chlorination plant
- •20 Coal handling plant
- •20.2 Water-borne reception and discharging
- •20.3 Road-borne reception and discharging
- •20.4 Coal storage
- •20.5 Conveyance from unloading point to station bunkers or coal store
- •20.6 Plant control
- •21 Ash and dust handling plant
- •21.1 Ash handling plant
- •21.2 Dust handling plant
- •21.3 Ash and dust disposal
- •22 Auxiliary boilers
- •23 Gas generation and storage
- •23.1 Hydrogen
- •23.2 Carbon dioxide
- •23.3 Nitrogen
- •23.4 Miscellaneous gases
- •24 Pumped storage plant
- •24.1 Hydraulic machines
- •24.2 Generator-motors
- •24.3 Main inlet valves
- •24.4 Draft tube valves
- •24.5 Gates
- •24.6 High integrity pipework
- •25 Gas turbine plant
- •25.1 Introduction
- •25.2 Operational requirements
- •25.3 Aero-engine-derivative gas turbines
- •25.4 Industrial gas turbines
- •25.5 Gas turbine power station layout
- •26 References
- •CHAPTER 3
- •Civil engineering and building works
- •Introduction
- •2 Geotechnical investigations
- •2.1 General and desk studies
- •2.2 Geophysical investigations
- •2.3 Trial excavations and boreholes
- •2.3 Trial excavations and boreholes
- •2.4 In-situ tests
- •2.5 Groundwater investigations
- •2.6 Ground description and classification
- •2.7 Laboratory tests
- •2.8 Factual reports
- •2.9 Interpretation of site investigations
- •3 Seismic hazard assessment
- •3.1 Geology
- •3.2 Earthquakes
- •3.3 Crustal dynamics
- •3.4 Ground motion hazard
- •3.5 Ground rupture hazard
- •4 Types of foundations
- •4.1 Isolated column foundations
- •4.2 Strip foundations
- •4.5 Piled foundations
- •4.5 Piled foundations
- •4.6 Caisson foundations
- •4.7 Anti-seismic foundations
- •5 Foundations design and construction
- •5.1 Concrete
- •5.2 Bearing pressures and settlement
- •5.3 Test piling
- •6 Foundations for main and secondary structures
- •6.1 Boiler house foundations
- •6.2 Turbine hall foundations
- •6.3 Turbine-generator blocks
- •6.4 Basement of ground floor
- •6.5 Track hoppers
- •6.6 Chimney foundations
- •6.7 Cooling tower foundations
- •6.8 Reactor foundations
- •7 General site works
- •7.1 Flood embankments
- •7.2 Roads
- •7.3 Drainage
- •7.4 Railways
- •7.5 Coal storage
- •7.3 Oil tank compounds
- •7.7 Ash disposal areas
- •8 Methods of construction
- •8.1 Site clearance, access roads and construction offices
- •8.2 Underground construction
- •8.3 Groundwater lowering
- •8.4 Excavating machinery
- •8.6 Formwork and reinforcement
- •8.7 Mixing and placing of concrete
- •9 Direct cooled circulating water systems
- •9.1 Civil engineering structures in direct cooling systems
- •9.2 Culverts
- •3.3 Pumphouse and screen chamber intake
- •9.4 Cooling water tunnels
- •9.5 Submersible cooling water structures
- •9.6' Maintenance considerations
- •10 Harbours and jetties
- •10.1 General
- •10.2 Types of harbours and jetties
- •10.3 Construction of harbours and jetties
- •11 Loadings
- •11.1 Definitions
- •11.2 Imposed loads due <o plant
- •11.3 Distributed imposed loads
- •II. 6 Reduced loadings in main beams and columns
- •11.4 Cranes
- •11.5 Wind and snow loads
- •12 Steel frames
- •12.1 Steelwork
- •13 Reinforced concrete
- •13.1 General
- •13.2 Formwork
- •13.3 Reinforcement
- •1^.4 Design of reinforced concrete
- •12.2 Design of members
- •12.3 Connections
- •12.4 Protection of steelwork
- •13.5 Movement joints
- •13.6 Curing
- •13.7 Precast concrete
- •14 Prestressed concrete
- •14.1 Prestressing
- •14.2 Prestressed piling
- •14.2 Prestressed piling
- •14.3 Prestressed concrete pressure vessels and containments
- •15 Brickwork and blockwork
- •15.1 General
- •15.2 Bricks
- •15.3 Mortar
- •15.4 Brickwork
- •15.5 Blocks
- •15.8 Openings
- •15.6 Blockwork
- •16 Lightweight walling systems
- •16.1 Sheeting
- •16.2 Insulation
- •16.3 Fixings
- •16.4 Durability
- •17 Roofing
- •17.1 Structural elements
- •17.2 Insulation and weatherproofing layers
- •17.3 Application to power stations
- •17.4 Durability
- •17.5 Rainwater disposal
- •18 Finishes
- •18.1 Floor finish considerations
- •18.2 Types of floor finish
- •18.3 Finishes to walls and ceilings
- •18.4 Wall tiling and other special finishes
- •18.5 Internal painting
- •18^6 External painting
- •19 Turbine hall and boiler house construction
- •19.1 General
- •19.2 Structural considerations
- •19.3 Erection of steelwork
- •19.4 ''Cladding
- •19.5 Ventilation
- •19.6 Floor and wall finishes
- •20 Reactor construction
- •20.1 Reactors
- •20.2 Reactor buildings
- •21.2 Control room building
- •21.3 Gas turbine house
- •21.4 CW pumphouse
- •21.6 Workshops and stores
- •21.7 Offices, welfare blocks, laboratories and similar buildings
- •22 Chimneys, cooling towers and precipitators
- •22.1 Chimneys
- •22.2 Cooling towers
- •22.3 Precipitators
- •23 Architecture and landscape
- •23.1 General power station architecture
- •23.2 Landscape considerations
- •23.3 Preparatory works
- •23.4 Landscape layout
- •24 Regulations
- •24.1 Government instruments
- •24.2 Factories Act
- •24.4 Building regulations
- •24.5 Nuclear station licensing
- •25 Civil engineering contracts
- •25.2 Forms of contract
- •25.3 Contract strategy
- •25.4 Contract placing
- •25.5 Contract administration
- •25.6 Budgetary approval and control
- •26 References
- •Appendix A
- •SUBJECT INDEX
ability of materials and the relative costs based on the capital and running costs. The connections from the pumphouse to the turbine hall should then be kept as short and as straight as possible to minimise costs and pressure losses in the system.
Care should be taken in routing the culverts or pipes so as to avoid the crossing of culverts or obstacles that could create air pockets in the system.
The syphonic weir and seal pit should be located as close as possible to the turbine hall to limit the extent of the more expensive pressurised cooling water culverts. The outlet culverts from the seal pit can be designed to a lower pressure. Care should be taken when routing culverts to ensure that satisfactory clearances exist to other services and structures to enable their satisfactory construction.
3.8.2 Closed cooling tower water system
A closed cooling tower water system, or indirect system, is used when the water supply available is inadequate for direct cooling, and the condensers operate on a closed circuit. A typical arrangement is shown in Fig 1.2S. The essential elements of the system include a cooling water pumphouse and forebay, intake and outlet culverts, cooling towers and return culverts to the lorebay. A make-up and purge system is provided to control the salts concentrated in the system due to continuous recirculation and to replace the amount lost by evaporation from the cooling towers.
The location of the cooling water pumphouse (see Fig 1.29) is again dictated by construction aspects and the need to minimise the pressurised cooling water culvert lengths.
The principles previously explained in Section 3.8.1 relevant to culvert routing equally apply to indirectcooled systems. The major impact on layout of a closed cooling tower water system is without doubt the cooling towers. At Drax power station (41XX) MW), which was the most recent to be built by the CEGB using cooling towers, there are a total of twelve cooling towers, each being approximately 115 m high and 93 m diameter at the pond cill levels. It may be appreciated therefore that the towers, together with the open return culverts to the pumphouse forebay, require a considerable area of land.
Cooling towers are usually grouped and sited so that the CW system as a whole is as compact as possible, maintaining an adequate clearance between adjacent towers, and between the towers and any object which might obstruct the air flow into them. Towers should be so positioned that any spray at the base of the tower does not blow on to public or station roads in frequent use, or onto the coal delivery rail sidings, and it is desirable to reduce the risk of coal dust and ash dust blowing into the tower ponds.
The location of the towers is also influenced by the preferences of the Consultant Architects commissioned by the CEGB for layout studies.
Site layout — thermal power stations
The layout of the make-up and purge system is dictated by the relative locations of the nearest river source and the cooling towers.
3.9 Fuel supplies and storage
3.9.1 Coal plant
The costs of coal deliveries by British Rail (BR) from British Coal arc dependent not only on the distances involved, but also on demurrage rates for locos and rolling stock and the efficient use of rail capacity by high speed permanently-coupled wagons. These costs can be minimised by providing the most rapid and efficient turnround at the power station unloading point. For this reason, the favoured arrangement for coal unloading at any power station site is the merry-go-round system, whereby bottom-opening hopper wagons unload the coal into underground hoppers, with the train runningon to leave the site without stopping. For the train to turn round and return to the loading colliery, a loop is required, with a 250 m minimum radius of track, and having the appropriate standing room for signal delays, means that a considerable area is required for such a loop arrangement. The land within the loop provides a convenient coal stock-out area.
Where insufficient area is available, or where access
. problems exist, a compromise solution can be adopted with sidings before and after the unloading track hopper and with provision for the loco to run round the train prior to exit from the site.
Figure 1.30 shows typical siding layout schematics. The track hoppers are situated as close to the boiler
house as possible to minimise conveyor lengths, but still providing sufficient distance for the rise from under ground hoppers to boiler house bunker tops to be achieved at a suitable inclination angle, allowing for junction lowers as required.
Another factor in the coal plant layout derives from the British Coal working arrangements requiring a week’s coal burn to be delivered in five working days. Thus, on average, two-sevenths of each day’s delivery must be stocked out for reclamation at the weekend. Consequently, stock-out and reclaim on a regular basis must be facilitated, and large travelling bucket wheel machines on rail tracks are often used for stocking out and reclaiming from the appropriate parts of the total fuel stocks. Longer term strategic stocks <ire held as part of the total stock, but transport to and from these more remote areas of the coal stock area is more economically achieved by bowl scraper mobile equip
ment.
The total area required for coal store, rail arrange ments and handling equipment can be up to 20 hectares for a 2000 MW station.
Similar layout considerations may apply to coastal stations with sea-borne coal deliveries and short-term stocks as a ‘buffer’ between ship arrivals and longer term strategic stocks.
- 39
DE ICING RING |
MAKE-UP |
|
|
|
|
|
ON ALL TOWERS |
MAKE-UP |
|
|
|
|
|
DOSING |
|
|
|
GENERATOR |
||
|
WATER |
|
|
|
||
|
HOUSE |
|
|
|
TRANSFORMER |
|
NORTHERN |
PUMP |
PURGE |
PURGE 1 |
|
||
|
|
|||||
COOLING TOWERS |
|
HOUSE |
■oo MIXING |
stilling i |
|
OIL COOLER |
|
|
WASTE |
450 gaLmin |
|||
|
|
|
CHAMBER |
CHAMBER■ |
||
|
|
|
PURGE |
WATER TREATMENT |
TO |
|
|
|
|
COOLER |
PLANT EFFLUENT |
STATION ACW STRAINERS |
|
|
|
|
DRAIN |
|
||
|
|
|
|
ASH PLANT EFFLUENT |
|
|
|
|
|
FUTURE |
|
|
|
|
ORA.N POINT |
|
|
|
|
|
|
|
INSTALLATION |
|
|
|
CW
PUMP HOUSE
CW SYSTEM
FILLING VALVES
TO |
|
|
CL2 |
DRAIN 5 |
|
PLANT |
||
POINTS! |
||
|
STILLING
CHAMBER
DRAIN
POINT
CONDR
DRAIN
POINTS
ASH
PUMP HOUSE
SOUTHERN
COOUNG TOWERS
’ HOM CfcNfR >ANS Oil COOLER it) MAIN AIR PUM»’
CQNU
CONOR
X MANHOLE WITH AIR RELEASE
AR AIR RELEASE VALVE
AUXILIARY CW SYSTEM
CONOR
SUPPLY TO
AIR HEATER WASHING PVMP
BO’LcR FC-E- 0.L PUMP DYNASPEED COOLER ASH HOPPED QJEnCh
AND SEAL
ASH PIT AGiTATOR DUST CONDITIONERS
CONDR
GENERAL SERVICE
COOLERS 2500 gal mtn
CONTROL
VALVE
TO STATION
DRAIN
MAIN ANO S’i-T UP
,AIR PUMPS 300 gal min 130 gal m.n 5 _
ACW DW . 2C0C <;.« '•
FEED PUL'i
Oil COOLE.
120 9*1! rr.:-
FEED PUL |
TOR |
AIR COOL: |
|
FEED LIQUID Rt 3-20 gat -n
LUB OIL COOLERS 1800 f gal mtn <
s
layout site and siting ton
Fig. 1.28 Typical diagrammatic arrangement of a closed cooling tower water system
25-TOV.S :•••
PUMPHC-ii *.-ANE
10-TONNE AUXILIARY PUMPHOUSE crane
Fig. 1^29 Typical CW forebay and pumphouse for a closed cooling lower water system
power thermal — layout Site
w
Power station ^itingf aqi^site layout |
Chapter 1 |
(a) Closed loop system
MAIN LINE RAILWAY
LOCO RUN ROUND LOOP
1
tjRAKF VAN SPUR
TARE |
GROSS |
WEIGHBRIDGES |
WEIGHBRIDGES |
3.9.2Fuel oil plant
To date the CEGB has not located an oil-fired station where its supply of heavy fuel oil would be dependent
on road or |
rail-borne transport. Stations have been |
sited either |
close to-oil refineries where direct piped |
fuel is available, or on coasts and estuaries where deliveries from sea-going tankers can be received. Quantities stored depend on a judgement of the security of supplies according to the proximity or otherwise of the source, and factors such as whether import and export to other nearby consumers is required. At least two and possibly up to five, large storage tanks are required. Ideal situations would be close to the main buildings on the ‘fuel delivery side’, but leaving adequate distances to minimise fire hazard to the station, and from other plant and equipment to the tanks themselves. Also adequately firm ground conditions are required and a suitable area large enough for a bund to contain the contents of one tank in case of a tank fracture.
Figure 1.31 shows the fuel oil delivery and storage arrangements at the 3 x 660 MW Littlebrook D power station.
On coal-fired stations, the need for boiler lighting-up oil requires delivery and storage arrangements. The
quantities of the lighter grade of oil needed arc relatively small and so delivery is normally by road tanker. Storage is in tanks within a bund located as close to the main boiler house as other layout con siderations allow.
3.10 Ash and dust disposal
The site layout must provide means of disposal for furnace bottom ash and for the large quantities of pulverised fuel dust produced as waste products. Although purchasers can be found at times for certain quantities of these waste products in the construction industry, in concretes or simply as landfill, long term dumping provisions are required. These can be close to the site or some distance away involving the pumping of dust as slurry, for example, to local natural or artificial lagoons, or transport by rail or sea in a dry condition, or by road in a wet condition. Market opportunities vary over the life of the station; some dumping grounds may become full or otherwise unavailable and disposal economics vary. Consequently the layout is likely to require several disposal options to be kept open in the longer term, whatever the immediate or initial short term disposal may be (see Fig 1.12).
42
Site layout — thermal power stations
TO ROtlER |
AUXILIARY |
FUEL OIL RURNERS |
Fig. 1.31 Fuel oil supply and storage — Littlebrook D power station
43