- •MODERN
- •POWER STATION PRACTICE
- •PERGAMON PRESS
- •Contents
- •Foreword
- •G. A. W. Blackman, CBE, FEng
- •Preface
- •Chapters 1 and 2
- •Chapter 3
- •Contents of All Volumes
- •CHAPTER 1
- •Power station siting and site layout
- •1 Planning for new power stations
- •1.1 Introduction
- •1.2 Capacity considerations
- •1.3 Economic considerations
- •1.4 Future requirement predictions
- •1.5 System planning studies
- •1.6 Authority to build a new power station
- •2 Site selection and investigation
- •2.1 Basic site requirements
- •2.3 Detailed site investigation
- •2.4 Environmental considerations
- •2.5 Site selection
- •3 Site layout — thermal power stations
- •3.1 General
- •3.2 Foundations
- •3.3 Site and station levels
- •3.4 Main buildings and orientation
- •3.5 Ancillary buildings
- •3.6 Main access and on-site roads
- •3.7 Station operation considerations
- •3.8 Cooling water system
- •3.9 Fuel supplies and storage
- •3.10 Ash and dust disposal
- •3.11 Flue gas desulphurisation plant materials
- •3.12 Transmission requirements
- •3.13 Construction requirements
- •3.14 Amenity considerations
- •3.15 Typical site layouts
- •4 Pumped storage
- •4.1 Introduction.
- •4.2 Suitable topology
- •4.3 Ground conditions
- •4.4 Site capacity
- •4.5 System and transmission requirements
- •4.7 Heavy load access
- •4.9 Environmental impact
- •5 Gas turbines
- •5.1 Introduction
- •5.2 The role of gas turbines
- •4.7 Heavy load access
- •Station design and layout
- •1 Introduction
- •2.1 Fossil-fired stations
- •2.2 Nuclear stations
- •2.3 Hydro-electric and pumped storage stations
- •2.4 Gas turbine stations
- •3 Future development options
- •3.1 Fossil-fired plant
- •3.2 Nuclear stations
- •3.3 Combined cycle gas turbines
- •3.4 Wind power
- •3.5 Tidal power
- •3.6 Geothermal energy
- •3.7 Combined heat and power
- •4 Station design concepts
- •4.1 Basic considerations
- •4.2 Design objectives
- •5 Plant operation
- •6 Station layout
- •6.1 General
- •6.2 Main plant orientation
- •6.3 Layout conventions
- •.7 Turbine-generator systems
- •7.1 Feedheating plant
- •7.2 Condenser and auxiliary plant
- •7.3 Erection and maintenance
- •8 Boiler systems
- •8.1 Pulverised fuel system
- •8.2 Draught system
- •8.3 Oil firing system
- •8.4 Boiler fittings
- •8.5 Dust extraction plant
- •8.6 Flue gas desulphurisation plant
- •9 Main steam pipework
- •10 Low pressure pipework and valves
- •11 Water storage tanks
- •12 Cranes
- •13 Fire protection
- •13.1 Introduction
- •13.2 Prevention of fires
- •13.3 Limiting the consequences of a fire
- •13.4 Reducing the severity of fires
- •14 Electrical plant layout
- •14.1 Introduction
- •14.2 Auxiliary switchgear
- •14.3 Turbine-generator auxiliaries
- •14.4 Main connections
- •14.5 Transformers
- •14.6 Cables
- •14.7 Batteries and charging equipment
- •14.8 Control rooms
- •15 Heating, ventilation and air conditioning
- •15.1 Introduction
- •15.2 Ventilation of nuclear stations
- •15.3 Smoke and fire control
- •15.4 General layout of HVAC plant
- •16 Air services
- •17 Water treatment plant
- •18 Cooling water plant
- •18.1 General design considerations
- •18.2 Cooling water pumphouse
- •18.3 Main cooling water pumps
- •18.4 Screening plant
- •18.5 Pump discharge valves
- •18.6 Section valves
- •18.7 Discharge pipework
- •18.8 Auxiliary systems
- •19 Chlorination plant
- •20 Coal handling plant
- •20.2 Water-borne reception and discharging
- •20.3 Road-borne reception and discharging
- •20.4 Coal storage
- •20.5 Conveyance from unloading point to station bunkers or coal store
- •20.6 Plant control
- •21 Ash and dust handling plant
- •21.1 Ash handling plant
- •21.2 Dust handling plant
- •21.3 Ash and dust disposal
- •22 Auxiliary boilers
- •23 Gas generation and storage
- •23.1 Hydrogen
- •23.2 Carbon dioxide
- •23.3 Nitrogen
- •23.4 Miscellaneous gases
- •24 Pumped storage plant
- •24.1 Hydraulic machines
- •24.2 Generator-motors
- •24.3 Main inlet valves
- •24.4 Draft tube valves
- •24.5 Gates
- •24.6 High integrity pipework
- •25 Gas turbine plant
- •25.1 Introduction
- •25.2 Operational requirements
- •25.3 Aero-engine-derivative gas turbines
- •25.4 Industrial gas turbines
- •25.5 Gas turbine power station layout
- •26 References
- •CHAPTER 3
- •Civil engineering and building works
- •Introduction
- •2 Geotechnical investigations
- •2.1 General and desk studies
- •2.2 Geophysical investigations
- •2.3 Trial excavations and boreholes
- •2.3 Trial excavations and boreholes
- •2.4 In-situ tests
- •2.5 Groundwater investigations
- •2.6 Ground description and classification
- •2.7 Laboratory tests
- •2.8 Factual reports
- •2.9 Interpretation of site investigations
- •3 Seismic hazard assessment
- •3.1 Geology
- •3.2 Earthquakes
- •3.3 Crustal dynamics
- •3.4 Ground motion hazard
- •3.5 Ground rupture hazard
- •4 Types of foundations
- •4.1 Isolated column foundations
- •4.2 Strip foundations
- •4.5 Piled foundations
- •4.5 Piled foundations
- •4.6 Caisson foundations
- •4.7 Anti-seismic foundations
- •5 Foundations design and construction
- •5.1 Concrete
- •5.2 Bearing pressures and settlement
- •5.3 Test piling
- •6 Foundations for main and secondary structures
- •6.1 Boiler house foundations
- •6.2 Turbine hall foundations
- •6.3 Turbine-generator blocks
- •6.4 Basement of ground floor
- •6.5 Track hoppers
- •6.6 Chimney foundations
- •6.7 Cooling tower foundations
- •6.8 Reactor foundations
- •7 General site works
- •7.1 Flood embankments
- •7.2 Roads
- •7.3 Drainage
- •7.4 Railways
- •7.5 Coal storage
- •7.3 Oil tank compounds
- •7.7 Ash disposal areas
- •8 Methods of construction
- •8.1 Site clearance, access roads and construction offices
- •8.2 Underground construction
- •8.3 Groundwater lowering
- •8.4 Excavating machinery
- •8.6 Formwork and reinforcement
- •8.7 Mixing and placing of concrete
- •9 Direct cooled circulating water systems
- •9.1 Civil engineering structures in direct cooling systems
- •9.2 Culverts
- •3.3 Pumphouse and screen chamber intake
- •9.4 Cooling water tunnels
- •9.5 Submersible cooling water structures
- •9.6' Maintenance considerations
- •10 Harbours and jetties
- •10.1 General
- •10.2 Types of harbours and jetties
- •10.3 Construction of harbours and jetties
- •11 Loadings
- •11.1 Definitions
- •11.2 Imposed loads due <o plant
- •11.3 Distributed imposed loads
- •II. 6 Reduced loadings in main beams and columns
- •11.4 Cranes
- •11.5 Wind and snow loads
- •12 Steel frames
- •12.1 Steelwork
- •13 Reinforced concrete
- •13.1 General
- •13.2 Formwork
- •13.3 Reinforcement
- •1^.4 Design of reinforced concrete
- •12.2 Design of members
- •12.3 Connections
- •12.4 Protection of steelwork
- •13.5 Movement joints
- •13.6 Curing
- •13.7 Precast concrete
- •14 Prestressed concrete
- •14.1 Prestressing
- •14.2 Prestressed piling
- •14.2 Prestressed piling
- •14.3 Prestressed concrete pressure vessels and containments
- •15 Brickwork and blockwork
- •15.1 General
- •15.2 Bricks
- •15.3 Mortar
- •15.4 Brickwork
- •15.5 Blocks
- •15.8 Openings
- •15.6 Blockwork
- •16 Lightweight walling systems
- •16.1 Sheeting
- •16.2 Insulation
- •16.3 Fixings
- •16.4 Durability
- •17 Roofing
- •17.1 Structural elements
- •17.2 Insulation and weatherproofing layers
- •17.3 Application to power stations
- •17.4 Durability
- •17.5 Rainwater disposal
- •18 Finishes
- •18.1 Floor finish considerations
- •18.2 Types of floor finish
- •18.3 Finishes to walls and ceilings
- •18.4 Wall tiling and other special finishes
- •18.5 Internal painting
- •18^6 External painting
- •19 Turbine hall and boiler house construction
- •19.1 General
- •19.2 Structural considerations
- •19.3 Erection of steelwork
- •19.4 ''Cladding
- •19.5 Ventilation
- •19.6 Floor and wall finishes
- •20 Reactor construction
- •20.1 Reactors
- •20.2 Reactor buildings
- •21.2 Control room building
- •21.3 Gas turbine house
- •21.4 CW pumphouse
- •21.6 Workshops and stores
- •21.7 Offices, welfare blocks, laboratories and similar buildings
- •22 Chimneys, cooling towers and precipitators
- •22.1 Chimneys
- •22.2 Cooling towers
- •22.3 Precipitators
- •23 Architecture and landscape
- •23.1 General power station architecture
- •23.2 Landscape considerations
- •23.3 Preparatory works
- •23.4 Landscape layout
- •24 Regulations
- •24.1 Government instruments
- •24.2 Factories Act
- •24.4 Building regulations
- •24.5 Nuclear station licensing
- •25 Civil engineering contracts
- •25.2 Forms of contract
- •25.3 Contract strategy
- •25.4 Contract placing
- •25.5 Contract administration
- •25.6 Budgetary approval and control
- •26 References
- •Appendix A
- •SUBJECT INDEX
Civil engineering and building works |
Chapter 3 |
Fig. 3.18 Section through main buildings
In addition to these readings some blocks have been fitted with a large number of remote reading instru ments buried at strategic points as construction pro ceeded. Strain gauges, thermocouples and moisture cells have been used in combination for this, and give some indication of the behaviour of the block under the influence of changing load and long term heating from the turbine-generator itself.
6.4 Basement of ground floor
The choice of level for the basement of operating floor is dependent on various influences, some of which, e.g., hydraulics and layout, are discussed elsewhere in this book. The civil engineer's aim is to provide a suit able foundation for the main plant at the least capital cost, situated not so low as to involve expensive dewatering and not so high as to require imported fill. A cost balance can be arrived at for any given site, which is fine for producing capital estimates for the civil elements. However, other disciplines with a vested interest in station levels show more substantial revenue costs or savings, such as pumping costs and main tenance access. Hence the optimal level to minimise
lifetime costs needs to be calculated from a range of levels through progressive iterations.
Building and landscape architects have an. input which may also call for planning decisions before the final cost optimisation is done. The final choice from this wide parametric study is unlikely to coincide with the civil engineer’s preference and extra costs will inevitably be incurred.
The designer therefore has to accept the layout and levelsjlecided by a range of interests and must tailor his structural design to suit the engineering ground condi tions and the construction programme within these external constraints.
Boiler house and turbine hall foundations have been covered in the preceding sections, but the depth of basement will affect the choice of foundation from the range of buoyant, semi-buoyant, raft, piled, cylinders and contact types. For the main foundations it is not easy, or usual, to combine more than two of these methods in similar ground.
If a basement is proposed, the design must take into account the temporary stages when the excavation will heave at the bottom due to being unloaded and later when the whole basement may tend to float. Pressure relief, semi-permanent ground dewatering or ground anchors may have to be introduced.
210
6.5 Track hoppers
Coal-fired stations requiring some 20 000 t of coal per day need extensive bulk handling facilities for delivery, storage and retrieval of fuel. Track hoppers, into which a train can discharge its load whilst moving, form the biggest single foundation in the fuel handling system, followed by those for the boom stacker and reclaim track.
Figure 3.19 shows typical reinforced concrete hoppers which are about 70 m long and have a through put of over 1000 t per hour. Coal is removed from the hopper onto conveyors by paddle feeders which can travel the length of the hopper.
The track hopper extends rather more than 10 m below ground level and has to withstand considerable earth pressure. Also, if the ground water level is high, precautions have to be taken to prevent the empty hopper’s tendency to float. This may be done by increasing the dead weight of the whole construction. Another way is to extend the width of the base slab, as shown dotted in Fig 3.19(a), and use the weight of soil above the projections to counteract the tendency.
The beams supporting the track over the hopper should be as narrow as practicable so that the discharge of coal from the railway wagons is not impeded. A smooth tile or cast glass lining to the hopper face assists coal flow.
The design of hopper shown in Fig 3.19(b) provides improved handling of coals which have poor flow qualities.
6.6 Chimney foundations
The adoption of tall, multi-flue chimneys in the mid 1960s to reduce ground level concentrations of sulphur dioxide from the main boilers has resulted in structures of 200 m to 260 m in height and weighing 20 000 t to 30 000 t.
Foundations have taken several forms but generally comprise a thick reinforced concrete slab suppprted in some of the following ways:
• On driven or bored pattern piling with both vertical and raking members.
• On large diameter concrete foundation cylinders. These arc adopted when conventional pile driving might require impractically-close pile pitch or deep multiple piling where the as-built geometry would prove extremely difficult to meet the design.
•The slab is replaced by a cellular foundation where only low bearing pressures can be tolerated. The hollow cellular form allows some pre-loading of the sub-base before chimney building commences.
•As a reinforced concrete contact foundation where high bearing pressures are tolerable, such as on a high rockhead site.
Foundations for main and secondary structures
Modern design methods require that the dynamic response of tall chimneys to cross wind effects should be established, calling for study of the interaction of the chimney superstructure, the foundation and the under lying soils. Hence the initial choice of foundation scantlings or even forms based on static wind loadings and sized to be within allowable ground bearing pressures, may require modification in the secondary stage of design when the dynamic response is being estimated.
Two types of modem multi-flue chimney foundation are illustrated in Figs 3.20 and 3.21.
6.7Cooling tower foundations
The foundations for a cooling tower have to be considered in the light of the various components which constitute an operating tower.
Since the intensity of loading will vary in both form and magnitude from component to component, suit able isolation in the form of expansion joints must be provided between them to allow for differential move ment and settlement.
6.7.1 The cooling tower shell and shell support columns
The shell and its support columns can be carried on a discrete pier at each lower node point, i.e., the junction of each column pair at their base. Alternatively the columns can be carried on a continuous circular foun- • dation ring beam. The need for piling in either case will
depend upon |
the proximity |
of a |
suitable |
bearing |
stratum to ground level. |
|
|
|
|
To achieve |
acceptable load |
paths |
from the |
shell to |
the foundations, the support columns follow the basic geometry of the lower ring. As such they are raked both radially and circumferentially and the traditional X or W form results from this geometry of structure.
The need to allow in the design for the lateral thrust component of the force in these raking columns will, by analogy, necessitate raking piles where piling is con sidered suitable or will require a means of tying discrete footings together in the case of contact foundations (see Fig 3.22).
6.7.2The packing support structure
Since this normally comprises a square grid of columns at 6 m to 9 m centres, it is generally adequate to provide a single pile or isolated footing at the location of each column. Largely shielded by the shell from wind loadings, these foundations are virtually unin fluenced by horizontal loadings.
6.7.3The pond floor
This generally supports a head of water not exceeding 3 m depth and unless supported on very poor ground
211
Civil engineering and building works |
Chapter 3 |
A
B
Fig. 3.19 Reinforced concrete coal plant track hopper designs
212
rounuduuns top main ana seconaary structures
213
Civil engineering and building works |
Chapter 3 |
|
PLAN
Fig. 3.21 Chimney foundations — cellular
214