- •MODERN
- •POWER STATION PRACTICE
- •PERGAMON PRESS
- •Contents
- •Foreword
- •G. A. W. Blackman, CBE, FEng
- •Preface
- •Chapters 1 and 2
- •Chapter 3
- •Contents of All Volumes
- •CHAPTER 1
- •Power station siting and site layout
- •1 Planning for new power stations
- •1.1 Introduction
- •1.2 Capacity considerations
- •1.3 Economic considerations
- •1.4 Future requirement predictions
- •1.5 System planning studies
- •1.6 Authority to build a new power station
- •2 Site selection and investigation
- •2.1 Basic site requirements
- •2.3 Detailed site investigation
- •2.4 Environmental considerations
- •2.5 Site selection
- •3 Site layout — thermal power stations
- •3.1 General
- •3.2 Foundations
- •3.3 Site and station levels
- •3.4 Main buildings and orientation
- •3.5 Ancillary buildings
- •3.6 Main access and on-site roads
- •3.7 Station operation considerations
- •3.8 Cooling water system
- •3.9 Fuel supplies and storage
- •3.10 Ash and dust disposal
- •3.11 Flue gas desulphurisation plant materials
- •3.12 Transmission requirements
- •3.13 Construction requirements
- •3.14 Amenity considerations
- •3.15 Typical site layouts
- •4 Pumped storage
- •4.1 Introduction.
- •4.2 Suitable topology
- •4.3 Ground conditions
- •4.4 Site capacity
- •4.5 System and transmission requirements
- •4.7 Heavy load access
- •4.9 Environmental impact
- •5 Gas turbines
- •5.1 Introduction
- •5.2 The role of gas turbines
- •4.7 Heavy load access
- •Station design and layout
- •1 Introduction
- •2.1 Fossil-fired stations
- •2.2 Nuclear stations
- •2.3 Hydro-electric and pumped storage stations
- •2.4 Gas turbine stations
- •3 Future development options
- •3.1 Fossil-fired plant
- •3.2 Nuclear stations
- •3.3 Combined cycle gas turbines
- •3.4 Wind power
- •3.5 Tidal power
- •3.6 Geothermal energy
- •3.7 Combined heat and power
- •4 Station design concepts
- •4.1 Basic considerations
- •4.2 Design objectives
- •5 Plant operation
- •6 Station layout
- •6.1 General
- •6.2 Main plant orientation
- •6.3 Layout conventions
- •.7 Turbine-generator systems
- •7.1 Feedheating plant
- •7.2 Condenser and auxiliary plant
- •7.3 Erection and maintenance
- •8 Boiler systems
- •8.1 Pulverised fuel system
- •8.2 Draught system
- •8.3 Oil firing system
- •8.4 Boiler fittings
- •8.5 Dust extraction plant
- •8.6 Flue gas desulphurisation plant
- •9 Main steam pipework
- •10 Low pressure pipework and valves
- •11 Water storage tanks
- •12 Cranes
- •13 Fire protection
- •13.1 Introduction
- •13.2 Prevention of fires
- •13.3 Limiting the consequences of a fire
- •13.4 Reducing the severity of fires
- •14 Electrical plant layout
- •14.1 Introduction
- •14.2 Auxiliary switchgear
- •14.3 Turbine-generator auxiliaries
- •14.4 Main connections
- •14.5 Transformers
- •14.6 Cables
- •14.7 Batteries and charging equipment
- •14.8 Control rooms
- •15 Heating, ventilation and air conditioning
- •15.1 Introduction
- •15.2 Ventilation of nuclear stations
- •15.3 Smoke and fire control
- •15.4 General layout of HVAC plant
- •16 Air services
- •17 Water treatment plant
- •18 Cooling water plant
- •18.1 General design considerations
- •18.2 Cooling water pumphouse
- •18.3 Main cooling water pumps
- •18.4 Screening plant
- •18.5 Pump discharge valves
- •18.6 Section valves
- •18.7 Discharge pipework
- •18.8 Auxiliary systems
- •19 Chlorination plant
- •20 Coal handling plant
- •20.2 Water-borne reception and discharging
- •20.3 Road-borne reception and discharging
- •20.4 Coal storage
- •20.5 Conveyance from unloading point to station bunkers or coal store
- •20.6 Plant control
- •21 Ash and dust handling plant
- •21.1 Ash handling plant
- •21.2 Dust handling plant
- •21.3 Ash and dust disposal
- •22 Auxiliary boilers
- •23 Gas generation and storage
- •23.1 Hydrogen
- •23.2 Carbon dioxide
- •23.3 Nitrogen
- •23.4 Miscellaneous gases
- •24 Pumped storage plant
- •24.1 Hydraulic machines
- •24.2 Generator-motors
- •24.3 Main inlet valves
- •24.4 Draft tube valves
- •24.5 Gates
- •24.6 High integrity pipework
- •25 Gas turbine plant
- •25.1 Introduction
- •25.2 Operational requirements
- •25.3 Aero-engine-derivative gas turbines
- •25.4 Industrial gas turbines
- •25.5 Gas turbine power station layout
- •26 References
- •CHAPTER 3
- •Civil engineering and building works
- •Introduction
- •2 Geotechnical investigations
- •2.1 General and desk studies
- •2.2 Geophysical investigations
- •2.3 Trial excavations and boreholes
- •2.3 Trial excavations and boreholes
- •2.4 In-situ tests
- •2.5 Groundwater investigations
- •2.6 Ground description and classification
- •2.7 Laboratory tests
- •2.8 Factual reports
- •2.9 Interpretation of site investigations
- •3 Seismic hazard assessment
- •3.1 Geology
- •3.2 Earthquakes
- •3.3 Crustal dynamics
- •3.4 Ground motion hazard
- •3.5 Ground rupture hazard
- •4 Types of foundations
- •4.1 Isolated column foundations
- •4.2 Strip foundations
- •4.5 Piled foundations
- •4.5 Piled foundations
- •4.6 Caisson foundations
- •4.7 Anti-seismic foundations
- •5 Foundations design and construction
- •5.1 Concrete
- •5.2 Bearing pressures and settlement
- •5.3 Test piling
- •6 Foundations for main and secondary structures
- •6.1 Boiler house foundations
- •6.2 Turbine hall foundations
- •6.3 Turbine-generator blocks
- •6.4 Basement of ground floor
- •6.5 Track hoppers
- •6.6 Chimney foundations
- •6.7 Cooling tower foundations
- •6.8 Reactor foundations
- •7 General site works
- •7.1 Flood embankments
- •7.2 Roads
- •7.3 Drainage
- •7.4 Railways
- •7.5 Coal storage
- •7.3 Oil tank compounds
- •7.7 Ash disposal areas
- •8 Methods of construction
- •8.1 Site clearance, access roads and construction offices
- •8.2 Underground construction
- •8.3 Groundwater lowering
- •8.4 Excavating machinery
- •8.6 Formwork and reinforcement
- •8.7 Mixing and placing of concrete
- •9 Direct cooled circulating water systems
- •9.1 Civil engineering structures in direct cooling systems
- •9.2 Culverts
- •3.3 Pumphouse and screen chamber intake
- •9.4 Cooling water tunnels
- •9.5 Submersible cooling water structures
- •9.6' Maintenance considerations
- •10 Harbours and jetties
- •10.1 General
- •10.2 Types of harbours and jetties
- •10.3 Construction of harbours and jetties
- •11 Loadings
- •11.1 Definitions
- •11.2 Imposed loads due <o plant
- •11.3 Distributed imposed loads
- •II. 6 Reduced loadings in main beams and columns
- •11.4 Cranes
- •11.5 Wind and snow loads
- •12 Steel frames
- •12.1 Steelwork
- •13 Reinforced concrete
- •13.1 General
- •13.2 Formwork
- •13.3 Reinforcement
- •1^.4 Design of reinforced concrete
- •12.2 Design of members
- •12.3 Connections
- •12.4 Protection of steelwork
- •13.5 Movement joints
- •13.6 Curing
- •13.7 Precast concrete
- •14 Prestressed concrete
- •14.1 Prestressing
- •14.2 Prestressed piling
- •14.2 Prestressed piling
- •14.3 Prestressed concrete pressure vessels and containments
- •15 Brickwork and blockwork
- •15.1 General
- •15.2 Bricks
- •15.3 Mortar
- •15.4 Brickwork
- •15.5 Blocks
- •15.8 Openings
- •15.6 Blockwork
- •16 Lightweight walling systems
- •16.1 Sheeting
- •16.2 Insulation
- •16.3 Fixings
- •16.4 Durability
- •17 Roofing
- •17.1 Structural elements
- •17.2 Insulation and weatherproofing layers
- •17.3 Application to power stations
- •17.4 Durability
- •17.5 Rainwater disposal
- •18 Finishes
- •18.1 Floor finish considerations
- •18.2 Types of floor finish
- •18.3 Finishes to walls and ceilings
- •18.4 Wall tiling and other special finishes
- •18.5 Internal painting
- •18^6 External painting
- •19 Turbine hall and boiler house construction
- •19.1 General
- •19.2 Structural considerations
- •19.3 Erection of steelwork
- •19.4 ''Cladding
- •19.5 Ventilation
- •19.6 Floor and wall finishes
- •20 Reactor construction
- •20.1 Reactors
- •20.2 Reactor buildings
- •21.2 Control room building
- •21.3 Gas turbine house
- •21.4 CW pumphouse
- •21.6 Workshops and stores
- •21.7 Offices, welfare blocks, laboratories and similar buildings
- •22 Chimneys, cooling towers and precipitators
- •22.1 Chimneys
- •22.2 Cooling towers
- •22.3 Precipitators
- •23 Architecture and landscape
- •23.1 General power station architecture
- •23.2 Landscape considerations
- •23.3 Preparatory works
- •23.4 Landscape layout
- •24 Regulations
- •24.1 Government instruments
- •24.2 Factories Act
- •24.4 Building regulations
- •24.5 Nuclear station licensing
- •25 Civil engineering contracts
- •25.2 Forms of contract
- •25.3 Contract strategy
- •25.4 Contract placing
- •25.5 Contract administration
- •25.6 Budgetary approval and control
- •26 References
- •Appendix A
- •SUBJECT INDEX
: Station design and layout |
Chapter 2 |
IiftTuTURBINE 7 CONDENSER | | TURBINEtin8 CONDENSER |
£ □□□ £
Fig. 2.58 CW system mimic panel
15 Heating, ventilation and air conditioning
15.1 Introduction
The objectives of a heating, ventilation and air con ditioning (HVAC) plant on a power station can be considered to include one or more of the following:
• To comply with Statutory Regulations such as the Health and Safety at Work Act and the Nuclear Installations Act.
•To comply with CEGB Policies and Safety Rules.
•To maintain specified environmental conditions for plant and personnel.
•To remove toxic and hazardous materials present in the atmosphere.
•To remove heat .or moisture generated by equip ment.
•To assist in the containment of radioactive material and to minimise discharges to the environment.
•To assist in controlling the spread of smoke and fire in order to support the escape of personnel and the protection of plant.
To ensure that the identified design objectives are met it is essential that the HVAC requirements are con sidered as early as possible. HVAC equipment such as fans, ducts and filters require a lot of space and plant rooms and duct routes must be identified at an early stage In the layout of the station.
During the design phase each area of the station is studied in turn. Maximum and minimum temperature limits will be determined from equipment specifications and personnel requirements. Humidity levels will be determined and the need for specialist ventilation to dissipate toxic gases or control smoke and hot gases will be also determined. From these detailed requirements for each area, and with a knowledge of the building fabric, the solar gain to the buildings and the maximum and minimum external design conditions, estimates can be made of the heating, cooling and ventilation loads for each area. With this information a decision can be made concerning the type of system to be adopted for each area and preliminary plant sizes can be estimated enabling plant rooms and duct routes to be drawn up. As the design of the main plant progresses and more information regarding plant heating and cooling loads becomes available, then the preliminary estimates will need to be checked. As soon as a reasonable degree of confidence in the cooling and heating loads is available then final sizing and ordering of equipment can take place.
15.2 Ventilation of nuclear stations
HVAC systems on nuclear stations also serve to supplement physical containment in order to prevent the escape of radioactive particles. Air patterns are arranged so that air is extracted from the areas of higher activity and supplied to the cleaner areas. The arrangement is designed to ensure that air always flows from the cleaner areas at-sufficient velocity to prevent the back-diffusion of radioactive particles. Elaborate studies are made and sufficient equipment is installed to ensure that these air flows are maintained under all conceivable operating conditions. In addition to pre venting the spread of contamination within the build ing, the ventilation system has two further important roles. By providing sufficient air changes within the ventilated space, the system also helps to minimise the build-up of activity within the space by continuously purging it with clean air; and by fitting high efficiency particulate filters to the extract system the discharge of activity to atmosphere is kept to within allowable limits. The filtration system has a collection efficiency of greater than 99.9%, and before being discharged to atmosphere the air is sampled to check for levels of
128
activity in case of accidents such as a burst filter. These filtration systems are regularly checked to ensure that the collection efficiency does not deteriorate.
The foregoing requirements inevitably place a high burden of reliability on the ventilation system. This leads generally to the requirement for standby fans and filters, which in turn results in complex control systems. The necessity for standby plant, high air volumes and large banks of filters, inevitably leads to a high require ment for space. It is therefore important that these requirements are identified at an early stage in the design. For a detailed treatment on the design of active ventilation systems, reference should be made to the Atomic Energy Code of Practice 1054 — Ventilation of Radioactive Areas.
Figure 2.59 is a simplified schematic of an AGR nuclear station central control room heating, ventila tion and air conditioning system.
15.3 Smoke and fire control
In order to prevent the spread of fire and smoke between lire compartments and to assist in search and rescue operations, smoke or lire venting facilities are usually incorporated into the design. For large single storey buildings such as a turbine hall, automaticallyinitiated fire vents are installed in the roof. These ventilators operate at a predetermined temperature, or on a signal from the fire detection system, and opcn-up allowing fire and hot gases to escape to atmosphere.
To prevent fire and hot gases spreading between compartments which share the same ventilation system, the HVAC systems are fitted with fire dampers at penetrations through the fire compartment walls. These fire dampers possess the same degree of fire resistance as the partitions they penetrate and are automatically initiated on detection of heat or from the fire detection system. In addition, it is common practice to include a facility to enable the ventilation system to be used as a vehicle for extracting smoke following a fire. This is usually accomplished by fitting a fireman’s switch to the control system, which enables the system to be switched between normal operation, smoke extract and off. These switches are usually located in an easily accessible entrance lobby.
•J
15.4 General layout of HVAC plant
15.4.1 Turbine hall and boiler house
Traditionally the main buildings of a fossil-fired station have been naturally ventilated. Advantage has been taken of the tall boiler house, the high internal heat losses and the forced draft (FD) fans to draw air in through inlet louvres located at low level around the turbine hall and boiler house. The air rises through the building and is drawn into the FD fan intake with the balance being rejected through roof vents. The advan
tages of this system are that no energy is expended in driving the system, and heat losses from the boiler and turbines are collected and passed back into the boilers; collection efficiencies greater than 60% are not uncom mon. Disadvantages, however, include problems such as high boiler house temperatures, dust and condensa tion in the turbine hall and smoke logging in the turbine hall during a fire situation. These problems are usually associated with too little inlet area at low level in the turbine hall. Increasing the area, whilst solving these problems, leads to cold weather problems, for this reason consideration is now being given to separating the buildings with a partition wall and ventilating them separately along the lines of a nuclear station turbine hall.
15.4.2Coal bunkers
This area is usually mechanically ventilated by means of an extract fan and fresh air inlet louvres. Air patterns are arranged to suppress dust levels, and sufficient air changes are provided to disperse any carbon monoxide which may be given off by a slow burning bunker fire. Consideration is being given on the latest stations to fitting filters on the extract to reduce the dust dis charged to atmosphere. This puts a heavy burden on space requirements in the area.
15.4.3Electrical equipment annexes
With the exception of computer suites and control rooms, which usually have their own packaged air conditioning units, most electrical annexes housing cableways, battery rooms, switchgear rooms, etc., are mechanically ventilated for cooling with duct-mounted heater batteries. Air is usually ducted from a central fan room and the temperature of the room is regulated by a room-mounted thermostat controlling a heater battery located at the duct entry to the room. Occa sionally several rooms are served by one heater battery, in which case an average of room temperatures control the temperature. On occasion when equipment is sensi tive to high humidity, humidistats are installed, which on sensing a high humidity, e.g., greater than 70%, override the heating system, increasing the room temperature, thereby dropping the humidity. The air volume allocated to each area is determined from an estimation of the maximum heat load and the maxi mum outside air.temperature. During winter conditions 90% recirculation of extract air is employed to conserve heating costs.
Figure 2.60 shows a heating and ventilation system for an essential electrical supplies building.
15.4.4Auxiliary buildings
Wherever possible, auxiliary buildings such as the cooling water (CW) pumphouse and compressor houses are naturally ventilated. Such buildings are
129
130
NR
|
|
|
|
|
|
|
|
|
|
MAIN EXTRACT |
||
|
|
|
|
|
|
|
|
|
|
FANS |
||
TO ATMOSPHERE |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
D |
|
|
|
|
NR |
|
|
|
|
||||
ACOUSTIC |
|
|
|
|
|
|
|
|
|
|
|
|
LOUVRE |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Z/1 ( HO |
NR |
|||
|
AIR |
|
- |
|
|
|
|
|
ELEC |
|
||
|
MIXING |
|
|
|
|
|
|
|
|
|
|
|
0 |
CHAMBER |
|
|
|
|
|
|
ZONE 10 |
0 |
|||
|
|
|
|
|
|
|
|
|||||
ACOUSTIC |
|
|
|
|
|
|
|
|||||
|
|
|
|
|
BRANCH SECTION |
|
||||||
LOUVRE |
|
|
|
|
|
|
||||||
|
|
|
|
|
|
|
|
|
|
|
||
|
|
|
CENTRAL CONTROL ROOM |
|
|
|
|
|||||
|
|
|
|
AIR HANDLING UNITS |
|
|
|
|
||||
|
|
|
|
. NR |
|
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
, y , |
NR |
|
|
|
|
|
|
|
|
|
|
|
HO |
||
|
MIXING |
|
|
|
|
|
|
|
_ ELEC |
|
||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
CHAMBER |
|
|
|
|
|
|
|
|
|
|
D |
ACOUSTIC |
|
|
|
|
|
|
ZONE 10 |
|
||||
|
|
|
|
|
BRANCH SECTION |
|
||||||
LOUVRE |
|
|
|
|
|
|
||||||
|
|
|
|
|
|
|
|
|
|
|
||
|
|
|
CENTRAL CONTROL ROOM |
|
|
|
|
|||||
|
|
|
|
AIR HANDUNG UNIT 2 |
|
|
|
|
||||
|
|
|
|
NR |
|
|
|
|
||||
|
|
|
|
1 |
|
>< |
|
NR |
||||
|
|
|
|
|||||||||
|
|
|
|
|
|
|
|
c/ |
|
HO |
|
|
|
|
|
|
|
|
|
|
|
|
ELEC |
|
|
8 |
|
|
|
|
|
|
|
|
|
|
|
|
ACOUSTIC |
|
|
|
|
|
|
|
|
|
|
|
|
LOUVRE |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
CENTRAL CONTROL ROOM |
|
|
|
|
|||||
|
|
|
|
AIR HANDLING UNIT 1 |
|
|
|
|
I i
|
MAIN EXTRACT FROM ALL ZONES |
|
NR |
|
|
EXTRACT FROM TOILETS AT ? |
NR |
|
|
|
LEVEL 08' TO ATMOSPHERE |
|
||
|
|
LOUVRE |
NR |
|
|
EXTRACT FROM TOILETS MESS AND S |
|
|
|
|
LOCKER ROOMS AT LEVEL |
NR |
|
|
|
07 < TO ATMOSPHERE |
|
ANCILLARY |
|
|
|
LOUVRE |
NR |
EXTRACT FANS |
|
|
|
|
|
|
|
|
NR |
|
|
EXTRACT FROM TOILETS AT |
|
|
|
|
LEVEL 06 . TO ATMOSPHERE |
|
|
|
|
|
LOUVRE |
|
|
|
SUPPLY TO ZONE 4 |
fo7 COMPUTER ROOM 2 |
|
|
0 |
PLANT VENT |
|
||
■j09 CCR HVAC PLANTROOM |
|
|||
D |
SUPPLY TO ZONE 5 |
|
||
-|07 INSTRUMENT ROOM? |
|
|||
|
|
|
||
0 |
SUPPLY TO ZONE 8 |
07 SAFETY ROOM 2 |
|
|
|
|
|
|
|
|
UNIT A-' |
07 CCR |
|
— |
|
|
l 70% SATURATED AIR TO VDU |
||
|
|
|
| DESK HOODS IN CCR |
|
SECONDARY CONDITIONING UNITS |
07 CCR |
|
|
|
CPU AMENDMENT OFFICE' |
|
|||
|
UNIT ‘S' |
|
||
|
|
08 SIMULATOR ROOM |
|
|
|
|
SUPPLY TO ZONE 1 SECONDARY AREAS |
|
|
|
SUPPLY TO ZONE 2 |
06 LEVEv 2 COMPUTER OFFICE • |
|
|
|
|
|
TOILETS |
|
SUPPLY TO ZONE 9
SUPPLY TO ZONE 3
SUPPLY TO ZONE 5
SUPPLY TO ZONE 7
OS MAIN TELECOMS AND EQUIPMENT ROOM - TELECOMS BATTERY ROOM (INFILTRATION FROM MAIN TELECOMS AND EQUIPMENT ROOM) • COMMON STATIONS SERVICES EQUIPMENT ROOM
07 COMPUTER ROOM 1
jp7 INSTRUMENT RQQmT
07 SAFETY ROOM 1
06 UNIT 7 TELECOMS • UNIT 8 TELECOMS - BATTERY ROOMS
(INFILTRATION FROM UNIT 7 AND UNIT 8 TELECOMS)
SUPPLY TO ZONE 10
07 C AND I CPU MAINTENANCE - OPERATIONS I COMMISSIONING OFFICE • DATA CENTRE • SHIFT CHARGE ENGINEER • RECORDS ■ MESS ROOM - MALE LOCKER ROOM - MALE TOILET ANO SHOWER ■ FEMALE LOCKER ROOM ■ FEMALE TOILET ANO SHOWER - SECURITY OFFICE • CORRIDORS
08 LECTURE THEATRE • OFFICE > MALE TOILETS • FEMALE TOILETS • CCR VIEWING GALLERY • LOBBIES ■ CORRIDORS
09 CORRIDOR
CHARGE HALL VIEWING GALLERY
Fig. 2.59 HVAC system for nuclear station central control room
layout^ and design Station
2 Chapter
3 x 50% DUTY EXTRACT FANS
DISCHARGE TO
ATMOSPHERE
BATTERY
ROOM
2 x 100% DUTY BATTERY ROOM EXTRACT FANS
1 / ' PRESSURE RELIEF
J -£ DAMPERS DISCHARGE TO ATMOSPHERE
EXTRACT BY
CUBICLE FANS
GAS CIRCULATOR
CONVERTER ROOM
I'ig. 2.60 Healing and ventilation system for essential electrical supplies system
rarely heated, reliance being placed on the fact that plant is working during cold spells. Buildings such as the water treatment plant, oil pumphouse, ash/slurry pumphouse, fire fighting pumphouses, etc., which have low heat loads and which are sensitive to cold weather, usually employ thermostatically controlled roof extract
fans and fresh air inlet louvres. On occasion heating is also provided, usually in the form of radiant panels or fan-coil units. In the case of the administration block and amenities buildings, these usually employ a mecha nically ventilated system with heating coils similar to that used in the electrical annexes.
131