- •MODERN
- •POWER STATION PRACTICE
- •PERGAMON PRESS
- •Contents
- •Foreword
- •G. A. W. Blackman, CBE, FEng
- •Preface
- •Chapters 1 and 2
- •Chapter 3
- •Contents of All Volumes
- •CHAPTER 1
- •Power station siting and site layout
- •1 Planning for new power stations
- •1.1 Introduction
- •1.2 Capacity considerations
- •1.3 Economic considerations
- •1.4 Future requirement predictions
- •1.5 System planning studies
- •1.6 Authority to build a new power station
- •2 Site selection and investigation
- •2.1 Basic site requirements
- •2.3 Detailed site investigation
- •2.4 Environmental considerations
- •2.5 Site selection
- •3 Site layout — thermal power stations
- •3.1 General
- •3.2 Foundations
- •3.3 Site and station levels
- •3.4 Main buildings and orientation
- •3.5 Ancillary buildings
- •3.6 Main access and on-site roads
- •3.7 Station operation considerations
- •3.8 Cooling water system
- •3.9 Fuel supplies and storage
- •3.10 Ash and dust disposal
- •3.11 Flue gas desulphurisation plant materials
- •3.12 Transmission requirements
- •3.13 Construction requirements
- •3.14 Amenity considerations
- •3.15 Typical site layouts
- •4 Pumped storage
- •4.1 Introduction.
- •4.2 Suitable topology
- •4.3 Ground conditions
- •4.4 Site capacity
- •4.5 System and transmission requirements
- •4.7 Heavy load access
- •4.9 Environmental impact
- •5 Gas turbines
- •5.1 Introduction
- •5.2 The role of gas turbines
- •4.7 Heavy load access
- •Station design and layout
- •1 Introduction
- •2.1 Fossil-fired stations
- •2.2 Nuclear stations
- •2.3 Hydro-electric and pumped storage stations
- •2.4 Gas turbine stations
- •3 Future development options
- •3.1 Fossil-fired plant
- •3.2 Nuclear stations
- •3.3 Combined cycle gas turbines
- •3.4 Wind power
- •3.5 Tidal power
- •3.6 Geothermal energy
- •3.7 Combined heat and power
- •4 Station design concepts
- •4.1 Basic considerations
- •4.2 Design objectives
- •5 Plant operation
- •6 Station layout
- •6.1 General
- •6.2 Main plant orientation
- •6.3 Layout conventions
- •.7 Turbine-generator systems
- •7.1 Feedheating plant
- •7.2 Condenser and auxiliary plant
- •7.3 Erection and maintenance
- •8 Boiler systems
- •8.1 Pulverised fuel system
- •8.2 Draught system
- •8.3 Oil firing system
- •8.4 Boiler fittings
- •8.5 Dust extraction plant
- •8.6 Flue gas desulphurisation plant
- •9 Main steam pipework
- •10 Low pressure pipework and valves
- •11 Water storage tanks
- •12 Cranes
- •13 Fire protection
- •13.1 Introduction
- •13.2 Prevention of fires
- •13.3 Limiting the consequences of a fire
- •13.4 Reducing the severity of fires
- •14 Electrical plant layout
- •14.1 Introduction
- •14.2 Auxiliary switchgear
- •14.3 Turbine-generator auxiliaries
- •14.4 Main connections
- •14.5 Transformers
- •14.6 Cables
- •14.7 Batteries and charging equipment
- •14.8 Control rooms
- •15 Heating, ventilation and air conditioning
- •15.1 Introduction
- •15.2 Ventilation of nuclear stations
- •15.3 Smoke and fire control
- •15.4 General layout of HVAC plant
- •16 Air services
- •17 Water treatment plant
- •18 Cooling water plant
- •18.1 General design considerations
- •18.2 Cooling water pumphouse
- •18.3 Main cooling water pumps
- •18.4 Screening plant
- •18.5 Pump discharge valves
- •18.6 Section valves
- •18.7 Discharge pipework
- •18.8 Auxiliary systems
- •19 Chlorination plant
- •20 Coal handling plant
- •20.2 Water-borne reception and discharging
- •20.3 Road-borne reception and discharging
- •20.4 Coal storage
- •20.5 Conveyance from unloading point to station bunkers or coal store
- •20.6 Plant control
- •21 Ash and dust handling plant
- •21.1 Ash handling plant
- •21.2 Dust handling plant
- •21.3 Ash and dust disposal
- •22 Auxiliary boilers
- •23 Gas generation and storage
- •23.1 Hydrogen
- •23.2 Carbon dioxide
- •23.3 Nitrogen
- •23.4 Miscellaneous gases
- •24 Pumped storage plant
- •24.1 Hydraulic machines
- •24.2 Generator-motors
- •24.3 Main inlet valves
- •24.4 Draft tube valves
- •24.5 Gates
- •24.6 High integrity pipework
- •25 Gas turbine plant
- •25.1 Introduction
- •25.2 Operational requirements
- •25.3 Aero-engine-derivative gas turbines
- •25.4 Industrial gas turbines
- •25.5 Gas turbine power station layout
- •26 References
- •CHAPTER 3
- •Civil engineering and building works
- •Introduction
- •2 Geotechnical investigations
- •2.1 General and desk studies
- •2.2 Geophysical investigations
- •2.3 Trial excavations and boreholes
- •2.3 Trial excavations and boreholes
- •2.4 In-situ tests
- •2.5 Groundwater investigations
- •2.6 Ground description and classification
- •2.7 Laboratory tests
- •2.8 Factual reports
- •2.9 Interpretation of site investigations
- •3 Seismic hazard assessment
- •3.1 Geology
- •3.2 Earthquakes
- •3.3 Crustal dynamics
- •3.4 Ground motion hazard
- •3.5 Ground rupture hazard
- •4 Types of foundations
- •4.1 Isolated column foundations
- •4.2 Strip foundations
- •4.5 Piled foundations
- •4.5 Piled foundations
- •4.6 Caisson foundations
- •4.7 Anti-seismic foundations
- •5 Foundations design and construction
- •5.1 Concrete
- •5.2 Bearing pressures and settlement
- •5.3 Test piling
- •6 Foundations for main and secondary structures
- •6.1 Boiler house foundations
- •6.2 Turbine hall foundations
- •6.3 Turbine-generator blocks
- •6.4 Basement of ground floor
- •6.5 Track hoppers
- •6.6 Chimney foundations
- •6.7 Cooling tower foundations
- •6.8 Reactor foundations
- •7 General site works
- •7.1 Flood embankments
- •7.2 Roads
- •7.3 Drainage
- •7.4 Railways
- •7.5 Coal storage
- •7.3 Oil tank compounds
- •7.7 Ash disposal areas
- •8 Methods of construction
- •8.1 Site clearance, access roads and construction offices
- •8.2 Underground construction
- •8.3 Groundwater lowering
- •8.4 Excavating machinery
- •8.6 Formwork and reinforcement
- •8.7 Mixing and placing of concrete
- •9 Direct cooled circulating water systems
- •9.1 Civil engineering structures in direct cooling systems
- •9.2 Culverts
- •3.3 Pumphouse and screen chamber intake
- •9.4 Cooling water tunnels
- •9.5 Submersible cooling water structures
- •9.6' Maintenance considerations
- •10 Harbours and jetties
- •10.1 General
- •10.2 Types of harbours and jetties
- •10.3 Construction of harbours and jetties
- •11 Loadings
- •11.1 Definitions
- •11.2 Imposed loads due <o plant
- •11.3 Distributed imposed loads
- •II. 6 Reduced loadings in main beams and columns
- •11.4 Cranes
- •11.5 Wind and snow loads
- •12 Steel frames
- •12.1 Steelwork
- •13 Reinforced concrete
- •13.1 General
- •13.2 Formwork
- •13.3 Reinforcement
- •1^.4 Design of reinforced concrete
- •12.2 Design of members
- •12.3 Connections
- •12.4 Protection of steelwork
- •13.5 Movement joints
- •13.6 Curing
- •13.7 Precast concrete
- •14 Prestressed concrete
- •14.1 Prestressing
- •14.2 Prestressed piling
- •14.2 Prestressed piling
- •14.3 Prestressed concrete pressure vessels and containments
- •15 Brickwork and blockwork
- •15.1 General
- •15.2 Bricks
- •15.3 Mortar
- •15.4 Brickwork
- •15.5 Blocks
- •15.8 Openings
- •15.6 Blockwork
- •16 Lightweight walling systems
- •16.1 Sheeting
- •16.2 Insulation
- •16.3 Fixings
- •16.4 Durability
- •17 Roofing
- •17.1 Structural elements
- •17.2 Insulation and weatherproofing layers
- •17.3 Application to power stations
- •17.4 Durability
- •17.5 Rainwater disposal
- •18 Finishes
- •18.1 Floor finish considerations
- •18.2 Types of floor finish
- •18.3 Finishes to walls and ceilings
- •18.4 Wall tiling and other special finishes
- •18.5 Internal painting
- •18^6 External painting
- •19 Turbine hall and boiler house construction
- •19.1 General
- •19.2 Structural considerations
- •19.3 Erection of steelwork
- •19.4 ''Cladding
- •19.5 Ventilation
- •19.6 Floor and wall finishes
- •20 Reactor construction
- •20.1 Reactors
- •20.2 Reactor buildings
- •21.2 Control room building
- •21.3 Gas turbine house
- •21.4 CW pumphouse
- •21.6 Workshops and stores
- •21.7 Offices, welfare blocks, laboratories and similar buildings
- •22 Chimneys, cooling towers and precipitators
- •22.1 Chimneys
- •22.2 Cooling towers
- •22.3 Precipitators
- •23 Architecture and landscape
- •23.1 General power station architecture
- •23.2 Landscape considerations
- •23.3 Preparatory works
- •23.4 Landscape layout
- •24 Regulations
- •24.1 Government instruments
- •24.2 Factories Act
- •24.4 Building regulations
- •24.5 Nuclear station licensing
- •25 Civil engineering contracts
- •25.2 Forms of contract
- •25.3 Contract strategy
- •25.4 Contract placing
- •25.5 Contract administration
- •25.6 Budgetary approval and control
- •26 References
- •Appendix A
- •SUBJECT INDEX
Main steam pipework
Fig. 2.33 Site plan showing location of the regenerative FGD plant
is connected to the unit plant by means of a pipe bridge and cable trench.
The plant is serviced by many external facilities such as rail sidings, water services, electrical services, etc.
The location of FGD plant on a greenfield site would need to be considered as part of the overall site layout exercise.
See Volume B, Chapter 4 for detailed descriptions of FGD processes.
9 Main steam pipework
The main concern in developing the layout for main steam pipework is to provide for flexibility and to
minimise loadings at the terminal points of the boiler and turbine. In practice, because of the high cost of this pipework, a minimum total piping run is preferred and often the layout adopted will be a compromise based on economic as well as technical factors.
The thermal expansion and contraction of the pipe work needs to be accommodated by the inherent flexi bility designed into the system, and by the use of cold pull-ups and constraints which are applied to the pipe work where needed. Cold pull-up is the term used to describe the prestressing of a pipework system in the cold condition, such that it is in a neutral state after expanding to the hot operating condition.
Flexibility is a major concern during the layout process, and it is advisable for continuous reviews of
97
layout and design Station 2 Chapter _______________________ ___________ ____________ ___
Fig. 2.34 Perspective arrangement of the limestone-gypsum FGD plant
Low pressure pipework and valves
pipework design to be undertaken as station layout development proceeds.
The thrusts and turning moments at the terminal points can be difficult to calculate manually, but modern computing methods based on mathematical analysis allows rapid reviews and layout to move forward with the knowledge that design changes can be readily assessed.
The position of the turbine relative to the boiler can have significant influence on both the overall flexibility and cost of the pipework system. Transverse turbine layouts located on the boiler centreline generally allow for short symmetrical pipe routes to be adopted as shown in Fig 2.35.
Fig. 2.35 Main steam pipework arrangement for transverse turbine
The longitudinal turbine arrangement often results in a longer asymmetrical piping layout as shown in Fig 2.36, unless the ideal layout can be adopted by off-setting the turbine-generator unit from the boiler centreline. In an overall station layout context, whilst off-setting of the turbine hall relative to the boiler house may be viable in a technical sense, the overall effect on the station’s visual appearance may need to be considered. Additionally, if an asymmetrical piping layout is adopted than a review of steam pressure and temperature variations should be undertaken to ensure that the steam conditions at the turbine inlets are within acceptable tolerance levels.
To permit the monitoring and recording of pipework expansions and creep, a measurement system has been introduced on more recent stations within the CEGB. These measurements are taken following completion of construction at regular intervals in the life of the station. Suitable access facilities should therefore be provided in the layout for this activity.
Fig. 2.36 Main steam pipework arrangement for longitudinal turbine
10 Low pressure pipework and valves
Low pressure pipework and valves are usually asso ciated with the following services systems within the power station:
•Town water.
•River water.
•Treated (demineralised) water.
•Chlorine solution dosing.
•Reserve feedwater.
•Blowdown water recovery.
•Fire hydrant system.
•Fixed water spray protection.
•Ash sluicing supplies.
•Nitrogen supplies.
•Potable water supplies (fit for drinking).
•Compressed air supplies.
Many of these services lend themselves to trunk main routing throughout the length of the station with branch supplies out to each unit. Ample space for the routing of the pipework must be reserved, for example in the heater bay between the sets and the boilers, or below the operating floor walkways.
In the early stages of design it is essential that diagrams arc prepared for all low pressure services and a pattern established of valve and pipework require ments. The diagrams are then constantly developed as
99
Station design and layout
the requirements of the main plant items services become known. Low pressure pipework system design and layout must be responsive to the osciall main plant layout. As with all pipework design, the route and pressure drop must be optimised to give best overall efficiency.
Pipework should not be run in trenches or small ducts out of sight. It should be visible and accessible for maintenance together with its associated valves. There, must be correct drainage falls with air release valves fitted where necessary. Pipework should be wellsupported and secured. Pipe joints are usually the weakest links in a pipework system and demand the highest standards of materials and workmanship. The number of joints should be minimised by the use of welding.
11 Water storage tanks
Water storage represents a large space requirement and could, for instance, be in excess of 9090 nr’ of town water to cover station requirements for 24 hours. Reserve feedwater should be available for at least
Chapter 2
24 hours maximum continuous rating (MCR) supply lor each boiler.
Storage facilities lor town water are normally located externally to the main building, perhaps adjacent to the water treatment plant, but certainly with consideration being given to other uses and needs on this particular commodity, i.e., specific reserve for fire fighting pur pose, FGD requirements, etc.
The design of the storage facility is dependent on site space availability and various forms can be considered, e.g., low profile pressed steel tanks, concrete reservoirs of vertical cylindrical tanks. The vertical cylindrical type of tank is most common for reserve feedwater
storage |
use, the shape naturally allowing optimisation |
|
of |
base |
diameter to height ratio to cover such aspects |
as available space and ground load bearing capability. |
||
|
These |
large quantities of water arc not now stored |
at |
high |
level in the boiler house or turbine hall, as it |
is uneconomical in terms of steelwork to support the load. In addition, a disaster situation would arise if a tank weld or interconnecting pipe connection failed. Figure 2.37 shows a typical town water and raw waler system for an oil-fired station.
PUMPS SHUTDOWN
FIRST TRANSFER PUMP STARTS SECOND TRANSFER PUMP STARTS THIRD TRANSFER PUMP STARTS LOW LEVEL ALARM
EXTREME LOW LEVEL ALARM
STATION HIGH LEVEL BREAK TANKS
PLANT
—r~ |
TO WHEEL |
“T —T“ |
— |
TO SITE SERVICES MAIN |
TO SITE |
TO SITE TO MAIN |
TO SITE |
AND ANCILLARY BUILDINGS |
|
STORAGE AREA |
!SITEI |
|||
SERVICES WASHING BAY |
OFFICES BUILDINGS |
SERVICES |
|
|
|
|
|
BUILDING |
|
Fig. 2.37 Typical town water and raw water system
100