- •MODERN
- •POWER STATION PRACTICE
- •PERGAMON PRESS
- •Contents
- •Foreword
- •G. A. W. Blackman, CBE, FEng
- •Preface
- •Chapters 1 and 2
- •Chapter 3
- •Contents of All Volumes
- •CHAPTER 1
- •Power station siting and site layout
- •1 Planning for new power stations
- •1.1 Introduction
- •1.2 Capacity considerations
- •1.3 Economic considerations
- •1.4 Future requirement predictions
- •1.5 System planning studies
- •1.6 Authority to build a new power station
- •2 Site selection and investigation
- •2.1 Basic site requirements
- •2.3 Detailed site investigation
- •2.4 Environmental considerations
- •2.5 Site selection
- •3 Site layout — thermal power stations
- •3.1 General
- •3.2 Foundations
- •3.3 Site and station levels
- •3.4 Main buildings and orientation
- •3.5 Ancillary buildings
- •3.6 Main access and on-site roads
- •3.7 Station operation considerations
- •3.8 Cooling water system
- •3.9 Fuel supplies and storage
- •3.10 Ash and dust disposal
- •3.11 Flue gas desulphurisation plant materials
- •3.12 Transmission requirements
- •3.13 Construction requirements
- •3.14 Amenity considerations
- •3.15 Typical site layouts
- •4 Pumped storage
- •4.1 Introduction.
- •4.2 Suitable topology
- •4.3 Ground conditions
- •4.4 Site capacity
- •4.5 System and transmission requirements
- •4.7 Heavy load access
- •4.9 Environmental impact
- •5 Gas turbines
- •5.1 Introduction
- •5.2 The role of gas turbines
- •4.7 Heavy load access
- •Station design and layout
- •1 Introduction
- •2.1 Fossil-fired stations
- •2.2 Nuclear stations
- •2.3 Hydro-electric and pumped storage stations
- •2.4 Gas turbine stations
- •3 Future development options
- •3.1 Fossil-fired plant
- •3.2 Nuclear stations
- •3.3 Combined cycle gas turbines
- •3.4 Wind power
- •3.5 Tidal power
- •3.6 Geothermal energy
- •3.7 Combined heat and power
- •4 Station design concepts
- •4.1 Basic considerations
- •4.2 Design objectives
- •5 Plant operation
- •6 Station layout
- •6.1 General
- •6.2 Main plant orientation
- •6.3 Layout conventions
- •.7 Turbine-generator systems
- •7.1 Feedheating plant
- •7.2 Condenser and auxiliary plant
- •7.3 Erection and maintenance
- •8 Boiler systems
- •8.1 Pulverised fuel system
- •8.2 Draught system
- •8.3 Oil firing system
- •8.4 Boiler fittings
- •8.5 Dust extraction plant
- •8.6 Flue gas desulphurisation plant
- •9 Main steam pipework
- •10 Low pressure pipework and valves
- •11 Water storage tanks
- •12 Cranes
- •13 Fire protection
- •13.1 Introduction
- •13.2 Prevention of fires
- •13.3 Limiting the consequences of a fire
- •13.4 Reducing the severity of fires
- •14 Electrical plant layout
- •14.1 Introduction
- •14.2 Auxiliary switchgear
- •14.3 Turbine-generator auxiliaries
- •14.4 Main connections
- •14.5 Transformers
- •14.6 Cables
- •14.7 Batteries and charging equipment
- •14.8 Control rooms
- •15 Heating, ventilation and air conditioning
- •15.1 Introduction
- •15.2 Ventilation of nuclear stations
- •15.3 Smoke and fire control
- •15.4 General layout of HVAC plant
- •16 Air services
- •17 Water treatment plant
- •18 Cooling water plant
- •18.1 General design considerations
- •18.2 Cooling water pumphouse
- •18.3 Main cooling water pumps
- •18.4 Screening plant
- •18.5 Pump discharge valves
- •18.6 Section valves
- •18.7 Discharge pipework
- •18.8 Auxiliary systems
- •19 Chlorination plant
- •20 Coal handling plant
- •20.2 Water-borne reception and discharging
- •20.3 Road-borne reception and discharging
- •20.4 Coal storage
- •20.5 Conveyance from unloading point to station bunkers or coal store
- •20.6 Plant control
- •21 Ash and dust handling plant
- •21.1 Ash handling plant
- •21.2 Dust handling plant
- •21.3 Ash and dust disposal
- •22 Auxiliary boilers
- •23 Gas generation and storage
- •23.1 Hydrogen
- •23.2 Carbon dioxide
- •23.3 Nitrogen
- •23.4 Miscellaneous gases
- •24 Pumped storage plant
- •24.1 Hydraulic machines
- •24.2 Generator-motors
- •24.3 Main inlet valves
- •24.4 Draft tube valves
- •24.5 Gates
- •24.6 High integrity pipework
- •25 Gas turbine plant
- •25.1 Introduction
- •25.2 Operational requirements
- •25.3 Aero-engine-derivative gas turbines
- •25.4 Industrial gas turbines
- •25.5 Gas turbine power station layout
- •26 References
- •CHAPTER 3
- •Civil engineering and building works
- •Introduction
- •2 Geotechnical investigations
- •2.1 General and desk studies
- •2.2 Geophysical investigations
- •2.3 Trial excavations and boreholes
- •2.3 Trial excavations and boreholes
- •2.4 In-situ tests
- •2.5 Groundwater investigations
- •2.6 Ground description and classification
- •2.7 Laboratory tests
- •2.8 Factual reports
- •2.9 Interpretation of site investigations
- •3 Seismic hazard assessment
- •3.1 Geology
- •3.2 Earthquakes
- •3.3 Crustal dynamics
- •3.4 Ground motion hazard
- •3.5 Ground rupture hazard
- •4 Types of foundations
- •4.1 Isolated column foundations
- •4.2 Strip foundations
- •4.5 Piled foundations
- •4.5 Piled foundations
- •4.6 Caisson foundations
- •4.7 Anti-seismic foundations
- •5 Foundations design and construction
- •5.1 Concrete
- •5.2 Bearing pressures and settlement
- •5.3 Test piling
- •6 Foundations for main and secondary structures
- •6.1 Boiler house foundations
- •6.2 Turbine hall foundations
- •6.3 Turbine-generator blocks
- •6.4 Basement of ground floor
- •6.5 Track hoppers
- •6.6 Chimney foundations
- •6.7 Cooling tower foundations
- •6.8 Reactor foundations
- •7 General site works
- •7.1 Flood embankments
- •7.2 Roads
- •7.3 Drainage
- •7.4 Railways
- •7.5 Coal storage
- •7.3 Oil tank compounds
- •7.7 Ash disposal areas
- •8 Methods of construction
- •8.1 Site clearance, access roads and construction offices
- •8.2 Underground construction
- •8.3 Groundwater lowering
- •8.4 Excavating machinery
- •8.6 Formwork and reinforcement
- •8.7 Mixing and placing of concrete
- •9 Direct cooled circulating water systems
- •9.1 Civil engineering structures in direct cooling systems
- •9.2 Culverts
- •3.3 Pumphouse and screen chamber intake
- •9.4 Cooling water tunnels
- •9.5 Submersible cooling water structures
- •9.6' Maintenance considerations
- •10 Harbours and jetties
- •10.1 General
- •10.2 Types of harbours and jetties
- •10.3 Construction of harbours and jetties
- •11 Loadings
- •11.1 Definitions
- •11.2 Imposed loads due <o plant
- •11.3 Distributed imposed loads
- •II. 6 Reduced loadings in main beams and columns
- •11.4 Cranes
- •11.5 Wind and snow loads
- •12 Steel frames
- •12.1 Steelwork
- •13 Reinforced concrete
- •13.1 General
- •13.2 Formwork
- •13.3 Reinforcement
- •1^.4 Design of reinforced concrete
- •12.2 Design of members
- •12.3 Connections
- •12.4 Protection of steelwork
- •13.5 Movement joints
- •13.6 Curing
- •13.7 Precast concrete
- •14 Prestressed concrete
- •14.1 Prestressing
- •14.2 Prestressed piling
- •14.2 Prestressed piling
- •14.3 Prestressed concrete pressure vessels and containments
- •15 Brickwork and blockwork
- •15.1 General
- •15.2 Bricks
- •15.3 Mortar
- •15.4 Brickwork
- •15.5 Blocks
- •15.8 Openings
- •15.6 Blockwork
- •16 Lightweight walling systems
- •16.1 Sheeting
- •16.2 Insulation
- •16.3 Fixings
- •16.4 Durability
- •17 Roofing
- •17.1 Structural elements
- •17.2 Insulation and weatherproofing layers
- •17.3 Application to power stations
- •17.4 Durability
- •17.5 Rainwater disposal
- •18 Finishes
- •18.1 Floor finish considerations
- •18.2 Types of floor finish
- •18.3 Finishes to walls and ceilings
- •18.4 Wall tiling and other special finishes
- •18.5 Internal painting
- •18^6 External painting
- •19 Turbine hall and boiler house construction
- •19.1 General
- •19.2 Structural considerations
- •19.3 Erection of steelwork
- •19.4 ''Cladding
- •19.5 Ventilation
- •19.6 Floor and wall finishes
- •20 Reactor construction
- •20.1 Reactors
- •20.2 Reactor buildings
- •21.2 Control room building
- •21.3 Gas turbine house
- •21.4 CW pumphouse
- •21.6 Workshops and stores
- •21.7 Offices, welfare blocks, laboratories and similar buildings
- •22 Chimneys, cooling towers and precipitators
- •22.1 Chimneys
- •22.2 Cooling towers
- •22.3 Precipitators
- •23 Architecture and landscape
- •23.1 General power station architecture
- •23.2 Landscape considerations
- •23.3 Preparatory works
- •23.4 Landscape layout
- •24 Regulations
- •24.1 Government instruments
- •24.2 Factories Act
- •24.4 Building regulations
- •24.5 Nuclear station licensing
- •25 Civil engineering contracts
- •25.2 Forms of contract
- •25.3 Contract strategy
- •25.4 Contract placing
- •25.5 Contract administration
- •25.6 Budgetary approval and control
- •26 References
- •Appendix A
- •SUBJECT INDEX
Chapter 3
attentuation of the seismic waves propagated |
from |
attention is paid in the on-site geological investigation |
||||||||||||||||||||||||||||||||||||
them to the site. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(see Section 2 of this chapter) in order to understand as |
||||||||||||||||||||||
Variabilities in model source parameters arc incor |
fully as possible the geometry, relationships and dale of |
|||||||||||||||||||||||||||||||||||||
porated, in a Bayesian sense, by the assignment of |
last movement of any faults which are encountered. If |
|||||||||||||||||||||||||||||||||||||
appropriate weights to discrete value representations of |
any are found which cannot categorically be shown by |
|||||||||||||||||||||||||||||||||||||
these parameters, the weights being determined by a |
geological evidence to be effectively extinct, it may be |
|||||||||||||||||||||||||||||||||||||
consensus of expert opinion. The weighted parameter |
necessary either to abandon the site or to compute the |
|||||||||||||||||||||||||||||||||||||
functions are attached to branches of a computational |
ground rupture hazard (using methods comparable to |
|||||||||||||||||||||||||||||||||||||
logic tree for calculating hazard on which the prob |
those for the ground motion hazard) in terms of prob |
|||||||||||||||||||||||||||||||||||||
abilities at each ihkIc |
arc |
disjoint and |
exhaustive |
of |
ability levels for the exceedance of various displace |
|||||||||||||||||||||||||||||||||
all possible choices. On the logic tree there are main |
ments, and then demonstrate the acceptability of the |
|||||||||||||||||||||||||||||||||||||
branches for each area and fault source on which indivi |
Resulting hazard at the lowest levels of probability. This |
|||||||||||||||||||||||||||||||||||||
dual probability distributions for geometry, earthquake |
latter route is best avoided or at least ameliorated by |
|||||||||||||||||||||||||||||||||||||
recurrence, and strong motion attenuation are defined. |
|
|
adjustment to the layout of safety related plant. |
|
|
|||||||||||||||||||||||||||||||||
The |
boundaries |
of |
area |
sources |
are |
adjusted |
to |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||||||||||||
reflect tectonic understanding of the region but remain |
4 |
Types of foundations |
|
|
|
|
|
|||||||||||||||||||||||||||||||
conservative |
with |
regard |
to |
their |
hazard implications |
|
|
|
|
|
||||||||||||||||||||||||||||
for the site. Boundaries between the area sources are |
4.1 |
Isolated column foundations |
|
|
|
|||||||||||||||||||||||||||||||||
tested for statistical significance. |
|
|
|
|
|
|
|
|
|
|
|
|||||||||||||||||||||||||||
Having |
statistically |
tested |
that the |
Set |
L |
seismicities |
Any |
columns |
may be |
founded |
on a |
pad |
foundation, |
|||||||||||||||||||||||||
of area |
sources |
can |
each |
be |
represented |
by |
Poisson |
|||||||||||||||||||||||||||||||
provided |
that |
the |
size |
of pad |
required to |
spread |
the |
|||||||||||||||||||||||||||||||
processes, |
the |
next |
step |
is |
the |
derivation |
of |
their |
||||||||||||||||||||||||||||||
concentrated |
|
column loading |
is compatible |
with |
the |
|||||||||||||||||||||||||||||||||
respective |
activity |
rate, b-value, focal |
depth |
and |
maxi |
|
||||||||||||||||||||||||||||||||
allowable |
bearing |
pressure |
|
under |
that |
foundation. |
||||||||||||||||||||||||||||||||
mum |
magnitude distributions. Because of their |
impact |
|
|||||||||||||||||||||||||||||||||||
However, pads are only used where they are shown to |
||||||||||||||||||||||||||||||||||||||
on the |
hazard assessment, |
these assignments |
integrate |
|||||||||||||||||||||||||||||||||||
be |
economical in excavation |
and construction, such |
as |
|||||||||||||||||||||||||||||||||||
the |
available |
information |
from |
different |
historical |
|||||||||||||||||||||||||||||||||
where rock occurs near ground level. |
|
|
|
|
|
|||||||||||||||||||||||||||||||||
periods into overall distributions which are weighted by |
|
|
|
|
|
|||||||||||||||||||||||||||||||||
|
With |
other |
soils |
and |
rocks |
the use |
of |
such |
founda |
|||||||||||||||||||||||||||||
a consensus of expert opinion. |
|
|
|
|
|
|
|
|
|
|
|
|||||||||||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
tions |
may also require |
consideration |
of |
the |
accept |
|||||||||||||||||||||||
Of the many faults found in the region, very few will |
||||||||||||||||||||||||||||||||||||||
ability of |
the |
settlement which |
may |
occur |
under |
the |
||||||||||||||||||||||||||||||||
be significant by meeting the criteria for modelling as a |
stipulated |
loadings. In general |
the recommendations |
of |
||||||||||||||||||||||||||||||||||
discrete seismic source and by virtue of their proximity |
||||||||||||||||||||||||||||||||||||||
BS8004 [2] for shallow foundations should be followed |
||||||||||||||||||||||||||||||||||||||
to the |
site. These |
faults |
are |
modelled with |
appropriate |
|||||||||||||||||||||||||||||||||
in design. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|||||||||||||||||||||||||
geometries with respect to the site and with parameters |
|
|
|
|
|
|
|
|
|
|
|
|
|
|||||||||||||||||||||||||
|
Low |
rise |
structures with |
light frames |
arc |
normally |
||||||||||||||||||||||||||||||||
that |
are |
consistent |
with |
the |
available evidence. Com |
|
||||||||||||||||||||||||||||||||
founded |
on |
unrcinforced or |
nominally |
reinforced con |
||||||||||||||||||||||||||||||||||
pensatory adjustment is |
made to the activity rate of an |
|||||||||||||||||||||||||||||||||||||
crete |
pad |
footings. Here the |
|
footing supporting |
the |
|||||||||||||||||||||||||||||||||
area |
source |
which surrounds |
any |
particular |
modelled |
|
||||||||||||||||||||||||||||||||
frame should be so proportioned that the angle of load |
||||||||||||||||||||||||||||||||||||||
fault. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
spread from |
the pier or |
baseplate to the |
outer edge of |
||||||||||||||||
The |
final |
computational |
model, |
therefore, |
consists |
of |
||||||||||||||||||||||||||||||||
the ground bearing does not exceed 45°, hence minimi |
||||||||||||||||||||||||||||||||||||||
a combination |
of |
nearby |
area sources |
and, |
perhaps, |
|||||||||||||||||||||||||||||||||
sing tensile stresses within the footing. |
|
|
|
|
|
|||||||||||||||||||||||||||||||||
specific |
fault sources |
surrounded |
by |
a zone |
which |
is |
|
|
|
|
|
|||||||||||||||||||||||||||
|
Buildings |
with |
heavier column loadings |
should |
be |
|||||||||||||||||||||||||||||||||
assumed |
|
to |
be |
subject |
to |
average |
British |
seismicity. |
|
|||||||||||||||||||||||||||||
|
designed |
to |
the requirements |
of BS8110 |
[3] |
for rein |
||||||||||||||||||||||||||||||||
The |
expected ground |
motion |
hazard |
at the |
site |
is |
then |
|||||||||||||||||||||||||||||||
forced concrete. |
|
|
|
|
|
|
|
|
|
|
||||||||||||||||||||||||||||
calculated |
|
using |
an |
appropriate |
computer |
program. |
|
|
|
|
|
|
|
|
|
|
||||||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|||||||||||||||||||||
The results are tabulated and plotted for a wide range |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|||||||||||||||||||||
of |
probabilities |
together |
with |
their |
corresponding |
4.2 |
Strip foundations |
|
|
|
|
|
|
|
||||||||||||||||||||||||
curves at various levels of confidence. Sensitivity |
|
|
|
|
|
|
|
|||||||||||||||||||||||||||||||
studies are carried out to allow the evaluation of the |
The basic requirements for a strip foundation are |
|||||||||||||||||||||||||||||||||||||
effects |
|
of |
any |
remaining |
uncertainties |
in |
the |
final |
similar to those which apply to an isolated pad founda |
|||||||||||||||||||||||||||||
mood. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
tion. It is the most suitable form of foundation for both |
||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
interior and exterior walls of all low rise buildings on |
|||||||||||||||||
3.5 |
|
Ground rupture hazard |
|
|
|
|
|
|
reasonable ground. |
|
|
|
|
|
|
|
|
|
|
|||||||||||||||||||
|
|
|
|
|
|
|
|
On sloping sites strip footings should be on a |
||||||||||||||||||||||||||||||
Earthquake ‘ground rupture’ describes the pheno |
horizontal bearing stepped where necessary to maintain |
|||||||||||||||||||||||||||||||||||||
menon of displacement at rockhead or at ground level. adequate depth. |
|
|
|
|
|
|
|
|
|
|
||||||||||||||||||||||||||||
,If it occurs at all, it is very localised. |
|
|
|
|
|
|
|
For heavy column loads on weaker soils the size of |
The emphasis in the assessment of the hazard it posesadjacent isolated footings may be such as to make them
at any site is therefore on the present and active status |
touch. In such cases some economy may be achieved in |
|
of known faults at or very close to the site. Great |
excavation costs by providing a strip foundation and |
|
194 |
. |
|
|j<». 3.9 Cellular fouudaliuns
The designer must check that a cellular foundation
.constructed in water-bearing ground will not float due to the hydrostatic head exceeding the imposed loading at any stage of construction or usage. This danger may prevail in the case of over-cornpensated foundations, such as empty submerged storage tanks, where loadings vary due to operational demands. In a similar manner the effect of ground heave when sucfxfoundations are supported on cohesive soils is an equally vital design condition requiring careful study.
4.5 Piled foundations
When a stratum sufficiently strong to support the imposed loading does not exist fairly near the surface, piled foundations may be used. A pile is a ‘column’ in the ground which is used to transfer the load to a stronger and deeper stratum.
Piles may be of timber, hollow steel section, prestressed or reinforced concrete; the last named being the most used for foundations of buildings. The load carried by a pile can vary from 300 to 10 000 kN depending on the size, type and ground conditions. The load is trans mitted from the pile to the ground either by end bear ing of the pile toe on a hard strata underlaying soft ground, or by ‘skin friction’ between the surface area of the pile and the surrounding soil, or by a combination of both.
♦ There is no one pile type which is best in all condi tions and all types have their advantages according to circumstances. Piles can be sub-divided into two main types — displacement piles and replacement piles.
4.5.1Displacement piles
Displacement piles are sub-divided into preformed (precast, in the case of concrete) piles and in-situ piles.
The precast piles in general use on power station sites are made either as reinforced or prestressed concrete usually of square or near-square section. Reinforce ment consists of heavy longitudinal bars with square links or helical binders. Prestressed piles are most usually pretensioned. In both types, the spacing of links and binders is decreased at the toe and the head to resist driving stresses; the longitudinal icinl'otcciisenI or prestress provided is greatly in excess of that required to take the structural load, but is needed to resist the stresses of lifting, handling and driving. The toe may be strengthened with a pointed cast-iron shoe, although this may not be necessary when driving in clay.
The casting, storing, transporting and driving of the precast piles for a major contract, which may call for some 20 (MX) piles, is a considerable undertaking. A large area of the site has to be set aside and levelled and accurately paved with concrete to provide a casting bed, and further areas are required for storage. Travel ling derricks are required for casting the piles and lifting and handling them, a batching plant is needed to produce the large quantity of concrete required, and a light railway system to transport the piles to the driving frames.
Piles precast in this manner have the advantage that they can be inspected before driving, and good control of the quality of concrete can be maintained. They are driven only after sufficient time has been allowed for the concrete to mature, and are thus resistant to attack from harmful substances in the soil.
196
Civil engineering and building works |
Chapter 3 |
PLAN
Fig. 3.9 Cellular foundations
The designer must check that a cellular foundation constructed in water-bearing ground will not float due to the hydrostatic head exceeding the imposed loading at any stage of construction or usage. This danger may prevail in the case of over-compensated foundations, such as empty submerged storage tanks, where loadings vary due to operational demands. In a similar manner *thefoundationseffect of areground heave when such
supported on cohesive soils is an equally vita) design condition requiring careful stifdy.
4.5 Piled foundations
When a stratum sufficiently strong to support the imposed loading does not exist fairly near the surface, piled foundations may be used. A pile is a ‘column’ in the ground which is used to transfer the load to a stronger and deeper stratum.
Piles may be of timber, hollow steel section, prestressed or reinforced concrete; the last named being the most used for foundations of buildings. The load carried by a pile can vary from 300 to 10 000 kN depending on the size, type and ground conditions. The load is trans mitted from the pile to the ground either by end bear ing of the pile toe on a hard strata underlaying soft ground, or by ‘skin friction’ between the surface area of
. the pile and the surrounding soil, or by a combination of both.
« There is no one pile type which is best in all condi tions and all types have their advantages according to circumstances. Piles can be sub-divided into two main types — displacement piles and replacement piles.
4.5.1Displacement piles
Displacement piles are sub-divided into preformed (precast, in the case of concrete) piles and in-situ piles.
The precast piles in general use on power station sites are made either as reinforced or prestressed concrete usually of square or near-square section. Reinforce ment consists of heavy longitudinal bars with square links or helical binders. Prestressed piles are most usually pretensioned. In both types, the spacing of links, and binders is decreased at the toe and the head to resist driving stresses; Ihe longitudinal reinforcemcnl or prestress provided is greatly in excess of that required to take the structural load, but is needed to resist the stresses of lifting, handling and driving. The toe may be strengthened with a pointed cast-iron shoe, although this may not be necessary when driving in clay.
The casting, storing, transporting and driving of the precast piles for a major contract, which may call for some 20 (XX) piles, is a considerable undertaking. A large area of the site has to be set aside and levelled and accurately paved with concrete to provide a casting bed, and further areas are required for storage. Travel ling derricks are required for casting the piles and lifting and handling them, a batching plant is needed to produce the large quantity of concrete required, and a light railway system to transport the piles to the driving frames.
Piles precast in this manner have the advantage that they can be inspected before driving, and good control of the quality of concrete can be maintained. They are driven only after sufficient time has been allowed for the concrete to mature, and are thus resistant to attack from harmful substances in the soil.
196
Some wastage of concrete is necessary as the tops of the piles have to be cut away to expose the pile rein forcement for inclusion in the foundations. An accurate
knowledge |
of the |
level |
of the bearing stratum is |
required to |
avoid |
further |
wastage through excessive |
cut-off. It is possible to drive piles below ground level using a wooden ‘dolly’ as a temporary extension to the pile. Permanent extension of the pile and subsequent redriving is a tedious business as the head has to be stripped away, a new length of pile cast on in-xitu and left to mature before redriving can be undertaken.
A mobile pile frame — a tall steel structure on rails fitted with diesel-driven lifting gear — is employed to drive the piles. This hoists the pile into position, holds it and supports the pile hammer during driving, which continues until sufficient resistance is encountered, A variety of pile hammers are in use. Drop hammers varying in weight up to some 4 tonnes, dependent on the weight of pile, are still used, but diesel-driven hammers, which are much quicker in operation, are nowadays more common. The pile head is protected during driving with a steel helmet lined with a wooden or hard plastic packer.
Some of the problems related to uncertainty concern ing pile length can be addressed by jointed reinforced concrete piles which are offered as proprietary systems by some specialist contractors. Such piles can be pre cast in appropriate lengths (up to 10 in) and combina-’ tions. It is not desirable to have a joint just below
ground level when the |
pile is being |
hardest driven to |
its set. |
|
|
Hollow steel piles, |
generally of |
hexagonal shape |
and with pointed toes, are frequently used to support jetties, especially where long pile lengths are required. Although more expensive than concrete piles, they are much lighter and do not require such careful handling. Lengthening, when required, is a simple matter of trimming the head and welding on a further section. A protective external coating of bituminous compound, or protective paint is required before driving. Once driven, the piles are sometimes filled with concrete or with inert water.
A number of systems for forming in-situ displace ment piles are used, each specialist firm having its own method. A heavy steel tube fitted with a detachable cast iron or concrete shoe, or a concrete tube formed of hollow precast sections and fitted with a concrete shoe, is driven using a special piling frame usually mounted on a crawler-tracked excavator. A cage of reinforce ment is lowered into the tube and the void concreted. The precast concrete shells are left in position and have the advantage that the outer skin of mature concrete is resistant to chemical attack. Where steel tubes are employed, these are withdrawn as concreting proceeds (great care must be taken to ensure that voids are not created by pulling sections of concrete with the tube). Piles of this type need be only lightly reinforced to take
the |
structural loads, and can be accurately finished to |
the |
required level, thus avoiding wastage of concrete. |
i ypes or rounoanons
They are less certain in quality than the precast pile, particularly where a steel outer casing is used, as the ground pressure may cause the pile to close up after the casing is removed. A few systems employ a lighter steel permanent casing which is internally supported during driving by a mandrel in a similar way to the precast concrete shell type.
The greatest part of the loading on power station foundations is vertical, but some horizontal forces due to wind and operation loads have to be resisted. These forces are resisted by driving some piles at a rake of up to about 1 in 3. Raking piles are commonly used on such structures as jetties, cooling towers, chimneys, coal-handling structures and transmission .towers.
The very high column loadings now experienced in power station work cause the spacing of piles to be reduced to a point where the increase in ground pressure and consequential ‘heave’ caused by dis placement piles can become a serious problem. Great care has to be taken if ground movement is not to occur, and piles be displaced. Pre-boring at the location of each pile is sometimes undertaken to solve this problem. This procedure is also adopted to enable driven piles to penetrate thin hard layers of soil overlaying softer material.
4.5.2Replacement piles
Replacement piles arc constructed by specialist con tractors, with various methods of boring. It is rare for a single pile to be used on its own; piles are normally driven in groups at a spacing of 2.5 to 3 times their diameter and their heads incorporated into a thick capping of reinforced concrete designed to transmit the column load evenly to the piles. An arrangement of precast piles to support a column load of about 2000 kN is shown in Fig 3.10 and one to support about 30 000 kN from a major column using large diameter bored piles is shown in Fig 3.11.
If the piles are too close together, there will be considerable overlap of stress from adjacent piles in the soil or rock on which they rely for end bearing. Interaction is a particularly important consideration between piles which rely on skin friction. The bearing capacity of a group of piles is therefore, often less than the capacity of one pile multiplied by the number of piles in the group. This reduction in capacity is greatest for piles in cohesive soils, and in large groups can be as much as one third.
4.6Caisson foundations
For larger concentrated loads it may be necessary to use large diameter caissons either singly or in groups. The concrete shell of a cylinder is built from a steel cut ting edge at ground level, and supported vertically by temporary guides. The walls are in the order of 150 mm thick. Precast sections are used for cylinders between
197