Добавил:
Upload Опубликованный материал нарушает ваши авторские права? Сообщите нам.
Вуз: Предмет: Файл:
Экология ВИЭ / СЭС / Final Programmatic Environmental Impact Statement for Solar Energy Development.pdf
Скачиваний:
17
Добавлен:
31.03.2015
Размер:
9.69 Mб
Скачать

1

The scope of the cumulative impact analysis in this section and in the Draft Solar PEIS

2

assumes solar energy development at the level projected in the RFDS (the RFDS is presented in

3

Section 2.4 of this Final Solar PEIS). Potential differences in cumulative impacts between

4

alternatives are highlighted as appropriate. In applying the RFDS to all alternatives,

5

the following caveats must be considered.

6

 

7As discussed in Section 6.2, there is the possibility that the total level of development

8 could be curtailed under the SEZ alternative, at least in some states, because this alternative may

9not make enough lands available for ROW application. The extent to which this might occur

10cannot be quantified, at least in part because the BLM is likely to identify additional SEZs in the

11future to make more land available. Furthermore, because the RFDS is based on the state-

12specific RPSs, which are mandatory in each of the six states except Utah, it was assumed that

13development in that state that would not occur on BLM-administered lands would be made up

14for by development on non-BLM-administered lands.

15

16As discussed in Section 6.3, the no action alternative would make ample lands available

17for ROW application to support the projected RFDS development levels on BLM-administered

18lands. Although this alternative would not likely enhance the pace of utility-scale development

19over the next 20 years (see Section 6.3.1), the extent to which development would occur on

20BLM-administered lands cannot be quantified. Solar development that did not occur on BLM-

21administered lands would be assumed to be made up for by development on non-BLM-

22administered lands. This programmatic cumulative impact assessment assumes that solar

23development will occur up to the level of the total RFDS (i.e., approximately 32,000 MW on

24both BLM-administered and other lands), regardless of the portion of that development that

25occurs on BLM-administered lands.

26

27By restricting and/or prioritizing development in the SEZs under the two action

28alternatives, cumulative impacts may be more concentrated and/or severe within individual SEZs

29than described in this section. On the other hand, the concentration of development in the SEZs

30may also allow for the consolidation of related infrastructure (e.g., roads and transmission lines)

31and less total land disturbance. Cumulative impacts analyses for individual SEZs are presented in

32Chapters 8 through 13.

33

34An updated overview of ongoing and reasonably foreseeable activities in the six-state

35study area is presented in Section 6.5.1, including energy production and distribution

36(Section 6.5.1.1), and other activities such as recreation, mineral production, military operations,

37grazing and rangeland management, fire management, forestry, transportation, and industrial

38development (Section 6.5.1.2.1). An update for general trends in population growth, energy

39demand, water availability, and climate change is provided in Section 6.5.1.2.2. An updated

40discussion of cumulative impacts for the resource areas is provided in Section 6.5.2.

41

42

43 6.5.1 Overview of Activities in the Six-State Study Area

44

45Activities in the six-state study area considered in the cumulative impact analysis

46described in the Draft Solar PEIS remain valid overall, but some information has been updated

Final Solar PEIS

6-37

July 2012

1since the Draft was issued based on the availability of newer data or in response to public

2comments on the Draft Solar PEIS. Tables presented in Draft Solar PEIS are updated in the

3following sections. For tables in the Draft that are affected, either a revised table is presented or a

4description of changes is provided. Tables with no changes are also identified.

5

6Tables 6.5-1 and 6.5-2 in the Draft Solar PEIS present the types of future actions and

7trends that have been identified in the study area as part of the cumulative impact analysis. These

8table are not repeated here. In Table 6.5-1, under Type of Action – Transportation, the following

9associated activity should be added: “Aircraft operations (i.e., commercial and general

10aviation).” No changes are required for Table 6.5-2.

11

12Updated programmatic-level actions on federal lands are presented in Table 6.5-3 of this

13Final Solar PEIS.

14

 

15

6.5.1.1 Energy Production and Distribution

16

17

 

18

6.5.1.1.1 Oil and Gas Production

19

20

 

21Table 6.5-4 has been updated to compare oil production in the study area between 2000

22and 2010 and gas production between 2000 and 2009. Table 6.5-5 has been updated from fiscal

23year (FY) 2009 to show sales of oil and gas from BLM-administered lands in the six-state study

24area for FY 2010 (BLM 2011a).

25

26

27 6.5.1.1.2 Coal Production

28

29Table 6.5-6 updates the comparison of coal production in the four producing states within

30the six-state study area from between 2002 and 2008 to between 2002 and 2010.

31

 

32

6.5.1.1.3 Nuclear Electricity Generation

33

34

 

35

There are no updates to this section.

36

 

37

6.5.1.1.4 Renewable Energy Development

38

39

 

40

 

41Solar Energy. In 2009, solar energy accounted for about 1% of renewable electricity

42generation and about 0.10% of the total U.S. electricity supply (EIA 2012). As listed in

43Appendix B, as of May 31, 2012, there were 78 open pending applications for utility-scale solar

44power–generating facilities on BLM-administered public lands, with a total estimated capacity of

45approximately 33,000 MW. However, not all of the pending applications will result in ROW

46authorizations; applications are often terminated either because the developer decides to drop the

Final Solar PEIS

6-38

July 2012

1TABLE 6.5-3 Programmatic-Level Actions on Federal Landa

 

Responsible

 

Primary

Description

Agency

Status

Impact Location

Oil shale and tar sands

BLM

Record of Decision for

Colorado, Utah, and Wyoming

development

 

initial PEIS published

 

 

 

Nov. 19, 2008; Notice

 

 

 

of Availability of draft

 

 

 

2012 PEIS published

 

 

 

February 3, 2012, and

 

 

 

Record of Decision is

 

 

 

expected by Dec. 2012

 

Wind energy development

BLM

Notice of Availability of

Arizona, California, Colorado,

 

 

Record of Decision

Idaho, Montana, Nevada,

 

 

published Jan. 11, 2006

New Mexico, Oregon, Utah,

 

 

 

Washington, and Wyoming

West-wide energy

DOE, BLM, FS

Notice of Availability of

Arizona, California, Colorado,

corridors

 

Final PEIS published

Idaho, Montana, Nevada,

 

 

Nov. 28, 2008, and

New Mexico, Oregon, Utah,

 

 

Record of Decision

Washington, and Wyoming

 

 

published Jan. 14, 2009

 

Vegetation management

BLM

Notice of Availability

Alaska, Arizona, California,

 

 

of Record of Decision

Colorado, Idaho, Montana,

 

 

published Oct. 5, 2007

Nebraska, New Mexico, Nevada,

 

 

 

North Dakota, South Dakota,

 

 

 

Oklahoma, Oregon, Texas, Utah,

 

 

 

Washington, and Wyoming

Geothermal energy

BLM, FS

Notice of Availability of

Alaska, Arizona, California,

development

 

Final PEIS published

Colorado, Idaho, Montana,

 

 

Oct. 24, 2008, and

New Mexico, Nevada, Oregon,

 

 

Record of Decision

Utah, Washington, and Wyoming

 

 

published Dec. 17, 2008

 

aUpdated programmatic-level actions are shown in bold text.

2

3

4

Final Solar PEIS

6-39

July 2012

1TABLE 6.5-4 Trends in Oil and Gas Production in the Six-State Study Area

 

Oil Production (tbbl)a

 

Gas Production (mcf)b

 

 

 

Percentage

 

 

 

Percentage

State

2000

2011

Change

2000

2010

Change

Arizona

59

37

–37.3

368

183

–50.2

California

271,132

195,718

–27.8

418,865

286,841

–31.5

Colorado

18,481

32,305

74.8

760,213

1,578,379

107.6

Nevada

621

408

–34.3

7

4

–42.9

New Mexico

67,198

70,764

-5.3

1,820,516

1,292,185

–29.0

Utah

15,636

26,276

68.0

281,117

432,045

53.7

Total

373,127

325,508

–12.8

3,281,086

3,589,637

9.4

atbbl = thousand barrels. To convert bbl to L, multiply by 159.

b mcf = million cubic feet. To convert cf to m3, multiply by 0.02832.

Sources: EIA (2001, 2011a,b).

2

3

4TABLE 6.5-5 Oil and Gas Activities on Public Lands of the United States in

5FY 2010

 

Producible

 

Acresa in

Oil Sales

Gas Sales

 

and Service

Producing

Producing

Volume

Volume

State

Holes

Leases

Status

(bbl)b

(mcf)c

Arizona

2

0

0

31,560

119,885

California

7,845

322

81,315

3,576,882

8,419,421

Colorado

6,482

2,174

1,467,839

3,968,467

311,724,278

Nevada

93

26

23,637

415,426

d

New Mexico

34,018

6,556

3,688,759

31,056,750

594,608,604

Utah

7,542

1,460

1,107,185

17,229,310

275,515,303

Total

55,980

10,538

6,368,735

56,278,395

1,190,387,491

aTo convert acres to km2, multiply by 0.004047.

bbbl = barrels. To convert bbl to L, multiply by 159.

cmcf = million cubic feet. To convert cf to m3, multiply by 0.02832.

d A dash indicates no activity.

Source: BLM (2011a).

6

7

Final Solar PEIS

6-40

July 2012

1

TABLE 6.5-6 Coal Production in the Producing States within the Six-State

2

Study Area in 2002 and 2010a

 

 

 

 

 

 

 

 

State

2002

2010

Percentage Change

 

(thousand short tons)

(thousand short tons)

from 2002 to 2010

 

Arizona

12,804

7,752

–39.4

 

Colorado

35,103

25,163

–28.3

 

New Mexico

28,916

20,991

–27.4

 

Utah

25,304

19,351

–23.5

 

Total

102,127

73,257

–28.3

a To convert short tons to metric tons (MT), multiply by 0.9072.

Sources: EIA (2003, 2011c).

3

4

5project or because the BLM determines that the application is not viable. In fact, several of the

6applications pending as of October 2011 have been closed (see Appendix B). The RFDS

7assumed for this PEIS estimates that solar development on BLM-administered lands over the

820-year study period will be only about 75% of that represented by the active BLM applications,

9or 24,000 MW. An additional 8,000 MW is projected to be developed on non-BLM lands in the

10study area.

11

12

13Wind Energy. In 2009, wind energy accounted for about 9% of the renewable electricity

14generation and 0.76% of the total U.S. electrical supply (EIA 2012).

15

16

17Geothermal Energy. Geothermal energy resources are the steam and hot water generated

18by heat from within the earth. In 2009, they accounted for about 5% of the renewable electricity

19generation and 0.4% of the total U.S. electricity supply (EIA 2012). Table 6.5-7 has been

20updated to compare the number and acreage of geothermal leases in FY 2002. The number of

21leases issued by the BLM in the study area nearly tripled between FY 2002 (255) and FY 2010

22(702).

23

24

25Hydroelectric Power. In 2009, hydroelectric power generation accounted for about 2.8%

26of the total U.S. electricity supply (EIA 2012).

27

28

29Biomass Resources. In 2009, biomass resources accounted for about 50% of renewable

30electricity generation and about 4.1% of the total U.S. electricity supply (EIA 2012).

31

32

33

Final Solar PEIS

6-41

July 2012

1TABLE 6.5-7 Competitive and Noncompetitive Geothermal Leases on BLM

2Public Lands in FY 2002 and FY 2010

 

 

 

 

 

 

 

 

FY 2010

 

 

 

 

 

 

 

FY 2002

 

Competitived

 

 

Noncompetitive

 

 

 

 

State

Acresa,b

Leasesc

Acres

Leases

Acres

Leases

 

 

Arizona

0

0

 

0

0

 

 

2,084

1

 

 

 

California

100,766

72

 

90,003

72

 

 

21,573

20

 

 

 

Nevada

236,601

171

 

697,094

276

 

 

477,035

270

 

 

 

New Mexico

4,581c

4e

2,941

3

 

 

640

1

 

 

 

Utah

6,906

8

 

160,461

58

 

 

1,744

1

 

 

 

Total

348,854

255

 

950,499

409

 

 

503,076

293

 

 

 

a

Number represents acreage for both competitive and noncompetitive leases.

 

 

 

 

b

To convert acres to km2, multiply by 0.004047.

 

 

 

 

 

 

 

 

c

Number represents total for both competitive and noncompetitive leases.

 

 

 

 

d

Includes both Energy Policy Act of 2005 leases and pre-act leases.

 

 

 

 

 

e

There were only competitive geothermal leases in New Mexico in FY 2002.

 

 

3

 

Sources: BLM (2003, 2011b).

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4

6.5.1.1.5 Transmission and Distribution Systems

 

 

 

 

 

 

5

 

 

 

 

 

 

6

 

 

 

 

 

 

 

 

 

 

 

 

 

7

Table 6.5-8 has been updated from FY 2009 data to show that in FY 2010, the BLM had

8

a total of 63,694 existing ROWs for oil and gas pipelines and electricity transmission lines in the

9six-state study area (BLM 2011b). This represents a 20.8% increase over the number of ROWs

10(52,724) in existence in FY 2002.The largest increase in ROWs issued between FY 2002 and

11FY 2010 occurred in California (up 27.0%), Utah (up 25.5%), and New Mexico (up 23.9%). The

12BLM processed 2,736 ROW applications and issued or amended 1,723 ROWs in FY 2010

13(BLM 2011d).

14

15

16 Transmission Line Projects

17

18Transmission projects, including the expansion projects listed in the TEPPC study, are

19updated in Table 6.5-9; this table is not exhaustive. Other projects in the western states can be

20found in the WestConnect 2012 Final annual 10-Year Transmission Plan and Appendices

21(WestConnect 2012).

22

23

24

Final Solar PEIS

6-42

July 2012

1TABLE 6.5-8 Number of Existing Oil and Gas Pipeline and Transmission Line

2ROWs on BLM Public Lands in FY 2002 and FY 2010

 

 

 

 

 

Total ROWs in FY 2010

Percentage Increase

 

 

 

 

Total ROWs

MLAa

FLPMAb

 

from

 

 

 

State

in FY 2002

Total

FY 2002 to FY 2010

 

 

Arizona

4,503

288

4,447

4,735

5.2

 

 

 

California

5,700

271

6,968

7,239

27.0

 

 

 

Colorado

5,836

1,412

5,326

6,738

15.5

 

 

 

Nevada

7,062

175

8,026

8,201

16.1

 

 

 

New Mexico

24,809

20,928

9,813

30,741

23.9

 

 

 

Utah

4,814

1,221

4,819

6,040

25.5

 

 

 

Total

52,724

24,295

39,399

63,694

20.8

 

 

 

a

MLA = Mineral Leasing Act of 1920.

 

 

 

 

 

 

b

FLPMA = Federal Land Policy and Management Act of 1976.

 

 

3

 

Sources: BLM (2003, 2011b).

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4

 

 

 

 

 

 

 

 

 

5

Natural Gas Pipeline Projects

 

 

 

 

6

 

 

 

 

 

 

 

 

 

7

The following text updates the Rockies Express-West Pipeline project, one of six planned

8

expansion projections on the interstate natural gas pipeline system in the Western Region

9

described in the Draft Solar PEIS (text added since the Draft Solar PEIS shown in bold).

10

Rockies Express-West Pipeline. In April 2007, the Federal Energy Regulatory

11

12

 

 

Commission (FERC) approved the Rockies Express-West interstate pipeline

13

 

 

project to transport more than 1.5 billion ft3 (42.5 million m3) per day of

14

 

 

Rocky Mountain natural gas to supply states east of the Rockies. Two related

15

 

 

components, proposed by TransColorado Gas Transmission Co. and Questar

16

 

 

Overthrust Pipeline Co., were also approved. Together, these projects will

17

 

 

consist of approximately 800 mi (1,287 km) of new pipeline and more than

18

 

 

237,000 horsepower (hp) of compression, meter stations, and other related

19

 

 

facilities. The pipeline system will span portions of Colorado, Wyoming,

20

 

 

Nebraska, Kansas, Missouri, and New Mexico (FERC 2008). The first

21

 

 

segment—a 136-mi (218-km), 36-in. (0.91-m) diameter pipeline that

22

 

 

extends from Meeker Hub in Rio Blanco County, Colorado, to

23

 

 

Wamsutter in Sweetwater County, Wyoming—has been completed and

24

 

 

went into service in February. That portion of the line added

25

 

 

750 million ft3/day (21.2 million m3) of firm capacity to the region.

26

 

 

 

 

 

 

 

 

 

27An additional project, not included in the Draft Solar PEIS is the Calnev Pipeline

28Expansion Project. Calnev Pipe Line, LLC (Calnev), operating partnership for Kinder Morgan

29Energy Partners, LP, proposes to expand its refined petroleum products pipeline, the Calnev

Final Solar PEIS

6-43

July 2012

1TABLE 6.5-9 Planned Transmission Projects, Including Expansions, in the Six-State Study Area

 

 

 

 

Planned

 

 

 

 

 

In-service

 

 

Project Name

Description

Applicant/Sponsor

Date

Comments

 

Chinook Project

500-kV HVDC from

TransCanada

2020

2008 TEPPC study

 

Montana–Las

Montana to Las Vegas,

 

 

requested

 

Vegas HVDC

Nevada, following the

 

 

 

 

Linea

SWIP corridor from

 

 

 

 

 

Borah, Idaho

 

 

 

 

TransWest Express

±600-kV HVDC from

National Grid, APS,

2015

Initial feasibility

 

Project

Powder River Basin,

PacifiCorp, Western,

 

studies completed;

 

 

Wyoming, through Utah

BLM, and WIA

 

2008 TEPPC study

 

 

to Las Vegas, Nevada

 

 

requested; NOI,

 

 

 

 

 

Jan. 4, 2011b

 

Zephyr Project

New 500-kV DC line

TransCanada

2016

2011 TEPPC study

 

(formerly Northern

from Medicine Bow area

 

 

requested;

 

Lights Inland

in Wyoming, through

 

 

preliminary

 

Project)a

Midpoint, Idaho,

 

 

application filed with

 

 

southward down the

 

 

BLM

 

 

eastern side of Nevada to

 

 

 

 

 

the Las Vegas area

 

 

 

 

SWIP

New 500-kV line from

LS Power and NV

 

ROW approved in

 

 

Twin Falls, Idaho, to

Energy

 

1998; EA, Aug.

 

 

Las Vegas, Nevada

 

 

2007; Final EIS for

 

 

 

 

 

South Portion,

 

 

 

 

 

Jan. 2010c

 

Gateway South

500-kV AC double-

PacifiCorp, National

 

Initial feasibility

 

 

circuit from Aeolus,

Grid, APS, WIA, and

 

studies completed;

 

 

Wyoming, to Mona, Utah

BLMd

 

TEPCC study

 

 

 

 

 

requested; NOI,

 

 

 

 

 

April 1, 2011; ROD

 

 

 

 

 

expected in 2015

 

Wyoming–

345-kV line connecting

Trans-Elect, Inc.,

2014

Phase II status

 

Colorado Intertie

northeastern Wyoming to

Western, and WIA

 

(WECC path rating

 

Project

the Denver, Colorado,

 

 

process); TOT 3

 

 

area

 

 

(WECC Path 36)

 

 

 

 

 

rating increase to

 

 

 

 

 

900 kV in 2007

 

Populus–Terminal

345-kV double-circuit

PacifiCorp

2010

Completed Nov.

 

Project

from new substation in

 

 

2010e

 

 

Idaho looping in various

 

 

 

 

 

lines with connections at

 

 

 

 

 

terminal substations in

 

 

 

2

 

Utah

 

 

 

 

 

 

 

 

 

Final Solar PEIS

 

6-44

 

July 2012

TABLE 6.5-9 (Cont.)

 

 

 

Planned

 

 

 

 

In-service

 

Project Name

Description

Applicant/Sponsor

Date

Comments

Midpoint–White

500-kV line, 275 mif

LS Power and Great

2014g

2008 TEPPC study

Pine Project (SWIP

from Midpoint, Idaho, to

Basin Transmission,

 

requested

North)

White Pine, Nevada

LLC

 

 

Wyoming–

345-kV line from

TransElect, WIA, and

2012

 

Colorado Intertie

northeastern Wyoming to

Western

 

 

Project

Denver, Colorado, area

 

 

 

 

(Pawnee)

 

 

 

Powder River–

 

North American Power

2003

Project dropped

Denver Project

 

Group

 

because of

 

 

 

 

inactivityh

High Plains

500-kV AC (double-

Colorado Springs

2019

Feasibility study

Express

circuit) high-voltage

Utilities, Platte River

 

completed; Stage 3

 

backbone transmission

Power Authority,

 

MOU executedi

 

path from Wyoming,

PNM, SRP,

 

 

 

across eastern Colorado

TransElect, TSG&T,

 

 

 

and New Mexico to

Western, Xcel Energy,

 

 

 

connect with facilities in

WIA, New Mexico

 

 

 

Arizona

Renewable

 

 

 

 

Transmission

 

 

 

 

Authority, and

 

 

 

 

Colorado Clean

 

 

 

 

Energy Authority

 

 

Eastern Plains

500-kV line running

TSG&T and Xcel

2012–2013

 

Project

south to north in the

 

 

 

 

eastern plains region of

 

 

 

 

Colorado

 

 

 

Devers–Palo Verde

Single-circuit, 500-kV

SCE

Project No. 2

AC line following the

 

 

route of Devers–Palo

 

 

Verde #1, from Devers,

 

 

California, west to

 

 

Colorado River

 

 

Substation (midpoint)

 

 

west of the City of

 

 

Blythe, California, and

 

 

from Devers to Valley

 

 

substations in California,

 

 

along the existing

 

 

Devers–Valley #1 ROW

 

2013 ROD July 13, 2011j; authorization to begin construction Sept. 20, 2011k; the Arizona portion of the project was canceled

Final Solar PEIS

6-45

July 2012

TABLE 6.5-9 (Cont.)

 

 

 

Planned

 

 

 

 

In-service

 

Project Name

Description

Applicant/Sponsor

Date

Comments

SunZia Project

Two 500-kV AC (or one

Southwestern Power

2016

DEIS May 2012l

 

AC and one DC)l from

Group II, LLC

 

 

 

southern New Mexico to

 

 

 

 

southern Arizona

 

 

 

Sonora–Arizona

500-kV line from Palo

PNM

2004

 

Interconnection

Verde, Arizona, to Santa

 

 

 

Project

Ana, Mexico; other

 

 

 

 

sources report two

 

 

 

 

345-kV circuits,

 

 

 

 

approximately 300 mia

 

 

 

 

long

 

 

 

Palo Verde–Yuma

500-kV, 115-mi line

APS

2014

Arizona Corporation

West Project

 

 

 

Commission granted

 

 

 

 

APS a Certificate of

 

 

 

 

Environmental

 

 

 

 

Compatibility on

 

 

 

 

Jan. 15, 2008m

Canada–Northern

500-kV line from British

PG&E

2015

 

California

Columbia to Round

 

 

 

Transmission

Butte/Grizzly, Oregon,

 

 

 

Project, Phase 1

and ±500-kV HVDC

 

 

 

 

from Round

 

 

 

 

Butte/Grizzly, Oregon, to

 

 

 

 

Tesla/Tracy, California

 

 

 

Interconnection to

500/230-kV transformer

Avista Corp.

2015

 

California–

at Devils Gap Substation

 

 

 

Northern

in Spokane, Washington,

 

 

 

California

area and possible phase

 

 

 

Transmission

shifters

 

 

 

Project

 

 

 

 

Central California

500-kV double-circuit

PG&E

 

 

Clean Energy

from Midway to Fresno,

 

 

 

Transmission

California

 

 

 

Project

 

 

 

 

Lake Elsinore

500-kV line Talega

Nevada Hydro

2012

 

Advance Pumped

Escondido/Valley

Company, Inc., and the

 

 

Storage Project and

Serrano, California

Lake Elsinore Valley

 

 

Interconnection

 

Municipal Water

 

 

 

 

District

 

 

Final Solar PEIS

6-46

July 2012

TABLE 6.5-9 (Cont.)

 

 

 

Planned

 

 

 

 

In-service

 

Project Name

Description

Applicant/Sponsor

Date

Comments

San Francisco Bay

500/230-kV substation

PG&E

2013

 

Area Bulk

and 500-kV and 230-kV

 

 

 

Transmission

lines with configuration

 

 

 

Reinforcement

changes

 

 

 

Project

 

 

 

 

Southern Navajo

Increase rating to

APS

2010

 

Path 51

3,200 MW (upgrade of

 

 

 

 

four existing series

 

 

 

 

capacitors)

 

 

 

TOT 3 (WECC

230-kV line

Western

2019

WECC Phase II

Path 36) Upgrade

 

 

 

status

Project (Miracle

 

 

 

 

Mile)

 

 

 

 

Navajo

500-kV line from Four

Dine Power Authority

2010

Pending ROD;

Transmission

Corners, New Mexico, to

 

 

access across Indian

Project–Segment 1

a point south of Navajo,

 

 

reservation is on

 

Arizona, on Navajo–

 

 

hold

 

Moenkopi line and

 

 

 

 

500-kV line from

 

 

 

 

Moenkopi to

 

 

 

 

Mead/Marketplace area,

 

 

 

 

Nevada

 

 

 

Sigurd to Red

345-kV, 164-mi line from

Rocky Mountain

2015

Scoping meetings

Butte to Crystal

Sigurd to Red Butte in

Power

 

were held in Oct.

(Segment G)

southwest Utah and from

 

 

2009; Draft EIS,

Project (part of the

Red Butte to the existing

 

 

May 27, 2011n; Final

Gateway South

substation at Crystal

 

 

EIS expected in 2012

Project, running

 

 

 

 

from Wyoming to

 

 

 

 

the desert

 

 

 

 

Southwest)

 

 

 

 

ON Line Project,

500-kV east of the Dry

NV Energy

2013

Under construction

formerly Ely

Lake Valley North SEZ

LS Power

 

 

Energy Center

 

 

 

 

Project (SWIP

 

 

 

 

South)

 

 

 

 

Final Solar PEIS

6-47

July 2012

TABLE 6.5-9 (Cont.)

 

 

 

Planned

 

 

 

 

In-service

 

Project Name

Description

Applicant/Sponsor

Date

Comments

Sunrise Powerlink

New line about 123 mi

SDG&E

2012

Under construction

Project

from the Imperial Valley

 

 

 

 

Substation in Imperial

 

 

 

 

County to the western

 

 

 

 

part of San Diego County

 

 

 

 

(in Imperial County the

 

 

 

 

line is a 500-kV line

 

 

 

 

extending to a new

 

 

 

 

Suncrest Substation south

 

 

 

 

of I-8; from there, the

 

 

 

 

line proceeds as a 230-kV

 

 

 

 

line to the Sycamore

 

 

 

 

Canyon Substation on

 

 

 

 

Marine Corps Air Station

 

 

 

 

Miramar)

 

 

 

Path 27 Upgrade

Intermountain DC line

Los Angeles

2009

 

 

(Utah)

Department of Water

 

 

 

 

& Power

 

 

Southline

345-kV double circuit,

Southline

2015

NOI April 4, 2012p

Transmission

350 mi from Afton, New

Transmission LLC,

 

 

Projecto

Mexico, to Tucson,

BLM, Western

 

 

 

Arizona

 

 

 

Energia Sierra

230-kV double circuit or

Sempra Generation,

2014

DEIS Aug. 2010

Juarez

500-kV single circuit,

DOE

 

 

Transmission

1.65 mi (0.65 mi in the

 

 

 

Projectq

United States) across the

 

 

 

 

United States–Mexico

 

 

 

 

border near Jacumba,

 

 

 

 

California

 

 

 

Barren Ridge

230-kV double-circuit,

Los Angeles

2016

DEIS Aug. 2011

Renewable

75 mi from Barren Ridge

Department of Water

 

 

Transmission

Switching Station to

and Power , Forest

 

 

Projectr

Haskell Canyon and

Service, BLM

 

 

additional 12 mi to the Castaic Power Plant

Final Solar PEIS

6-48

July 2012

TABLE 6.5-9 (Cont.)

 

 

 

Planned

 

 

 

 

In-service

 

Project Name

Description

Applicant/Sponsor

Date

Comments

Hidden Hills

230-kV single circuit,

Valley Electric

2015

NOI Oct. 11, 2011

Transmission

9.7 mi from Hidden Hills

Association, BLM

 

 

projects

Solar Electric Generating

 

 

 

 

Facility to the Bright

 

 

 

 

Source Energy (BSE)

 

 

 

 

Tap Substation, 53.7 mi

 

 

 

 

of new 500-kV single-

 

 

 

 

circuit transmission line

 

 

 

 

from the BSE Tap

 

 

 

 

Substation to the existing

 

 

 

 

Eldorado Substation; a

 

 

 

 

230-kV transmission line

 

 

 

 

from the Tap Substation

 

 

 

 

to Pahrump

 

 

 

Bordertown to

120 kV, 10.2 mi along

NV Energy, USFS,

 

NOI Nov. 21, 2011

California

the Nevada–California

BLM

 

 

Transmission Line

state line, 15 mi west of

 

 

 

Projectt

Reno Nevada

 

 

 

Sun Valley to

500-kV single circuit and

APS, BLM

2016

NOI April 11, 2011

Morgan

230-kV single circuit,

 

 

 

Transmission Line

38 mi from the Buckeye,

 

 

 

Projectu

Arizona, to Peoria,

 

 

 

 

Arizona

 

 

 

Central New

345 kV from Guadalupe,

Public Service

 

 

Mexico Collector

New Mexico, to Belen,

Company of New

 

 

Expansion Project

New Mexico

Mexico

 

 

Indian Hills–

500-kV line

Los Angeles

2010

 

Upland Project

 

Department of Water

 

 

 

 

& Power; Imperial

 

 

 

 

Irrigation District

 

 

Abbreviations: AC = alternating current; APS = Arizona Public Service; DC = direct current; BLM = Bureau of Land Management; EIS = environmental impact statement; HVDC = high-voltage direct current; I-8 = Interstate-8; MOU = Memorandum of Understanding; NOI = Notice of Intent; PNM = Public Service Company of New Mexico; ROD = Record of Decision; ROW = right-of-way; SDG&E = San Diego Gas & Electric; SEC = Southern California Edison; SRP = Salt River Project; SWIP = Southwest Intertie Project; TEPCC = Transmission Expansion Planning Policy Committee; TOT = time of transmission; TSG&T = Tri-State Generation & Transmission Association; WECC = Western Electricity Coordinating Council; Western = Western Area Power Administration; WIA = Wyoming Infrastructure Authority.

Foonotes on next page.

1

2

Final Solar PEIS

6-49

July 2012

TABLE 6.5-9 (Cont.)

aTransCanada (2011).

bBLM (2011c).

cWestern (2010).

dBLM (2012a).

ePacifiCorp (2011).

fTo convert mi to km, multiply by 1.609.

gWECC (2011).

hWECC (2009).

iWIA (2012).

jBLM (2011d).

kCPUC (2011).

lBLM (2012g).

m APS (2012).

nBLM (2012b).

oSouthline Transmission (2012).

pBLM (2012c).

qDOE (2010).

rLADWP (2011).

sBLM (2012d).

t USFS (2012).

uBLM (2012e).

Sources: TEPPC (2008); WECC (2012).

1

2

3 Pipeline System. The existing system extends from the North Colton Terminal in Colton,

4San Bernardino County, California to the North Las Vegas Terminal, in Las Vegas, Clark

5County, Nevada. The Calnev Pipeline Expansion Project would involve the construction,

6operation, and maintenance of 233 mi (377 km) of new 16-in. (0.41-m) diameter pipeline from

7the North Colton Terminal to the Bracken Junction near the McCarran International Airport in

8 Las Vegas, Nevada, which would parallel the existing system for most of the route. In addition to

9the new pipeline, the Proposed Project would include a new pump station, electrical substation,

10and ancillary facilities near Baker, California; a new 3-mi (5-km) lateral from the Bracken

11Junction to McCarran International Airport; and new or modified connections to new or

12modified laterals, valves, and ancillary modifications. This would increase the existing Calnev

13system capacity from 156,000 barrels (24,800 m3) to approximately 200,000 barrels (31,800 m3)

14of petroleum products per day (BLM 2012f).

15

Final Solar PEIS

6-50

July 2012