- •VOLUME 1 CONTENTS
- •NOTATION
- •ENGLISH/METRIC AND METRIC/ENGLISH EQUIVALENTS
- •EXECUTIVE SUMMARY
- •ES.1 Background
- •ES.2 BLM Proposed Action
- •ES.2.1 BLM Purpose and Need
- •ES.2.2 BLM Scope of Analysis
- •ES.2.3 Applications for Solar Energy Development on BLM Lands
- •ES.2.4 BLM Alternatives
- •ES.2.4.1 Program Elements Common to Both BLM Action Alternatives
- •ES.2.4.3 Solar Energy Zone Program Alternative
- •ES.2.4.4 No Action Alternative
- •ES.2.4.5 Reasonably Foreseeable Solar Energy Development
- •ES.2.4.6 Summary of Impacts of BLM’s Alternatives
- •ES.2.4.7 BLM’s Preferred Alternative
- •ES.3 DOE Proposed Action
- •ES.3.1 DOE Purpose and Need
- •ES.3.2 DOE Scope of Analysis
- •ES.3.3 DOE Alternatives
- •ES.3.3.2 No Action Alternative
- •ES.3.4 Summary of Impacts of DOE’s Alternatives
- •ES.4 Public Involvement, Consultation, and Coordination
- •ES.5 References
- •1 INTRODUCTION
- •1.1 Applicable Federal Orders and Mandates
- •1.1.1 Executive Order 13212
- •1.1.2 Energy Policy Act of 2005
- •1.1.3 Energy Independence and Security Act of 2007
- •1.1.4 DOI Secretarial Order 3285A1
- •1.1.5 Executive Order 13514
- •1.1.6 DOI Secretarial Order 3297
- •1.3 BLM Requirements and Objectives for the PEIS
- •1.3.1 BLM’s Purpose and Need
- •1.3.2 BLM Decisions To Be Made
- •1.3.3 Authorization Process for Solar Energy Development on BLM Lands
- •1.3.3.1 New Applications
- •1.3.3.2 Pending Applications
- •1.3.3.3 Approved Applications
- •1.3.4 BLM Land Use Planning Process
- •1.3.5 BLM Scope of the Analysis
- •1.3.5.1 Program Analysis Versus SEZ-Specific Analysis
- •1.3.6 BLM Planning Criteria
- •1.4 DOE Requirements and Objectives for the PEIS
- •1.4.1 DOE’s Purpose and Need
- •1.4.2 DOE Decisions To Be Made
- •1.4.3 DOE Scope of the Analysis
- •1.5 Cooperating Agencies
- •1.6.1 Renewable Portfolio Standards and Other Regional and State Initiatives
- •1.6.2 Related Initiatives
- •1.6.2.1 Energy Corridor Designation
- •1.6.2.3 California Desert Renewable Energy Conservation Plan
- •1.6.2.4 Arizona Restoration Design Energy Project
- •1.6.2.5 Wind Energy Development PEIS
- •1.6.2.6 Geothermal PEIS
- •1.8 References
- •2.1 Introduction
- •2.2 BLM Alternatives
- •2.2.1 Program Elements Common to Both BLM Action Alternatives
- •2.2.1.1 Right-of-Way Authorization Policies
- •2.2.1.2 Monitoring, Adaptive Management, and Mitigation
- •2.2.1.3 Design Features
- •2.2.1.4 Segregation of Lands with Potential for Solar Development
- •2.2.2.1 Proposed Right-of-Way Exclusion Areas
- •2.2.2.2 Proposed Solar Energy Zones
- •2.2.2.3 Proposed Variance Areas for Utility-Scale Solar Energy Development
- •2.2.2.4 Land Use Plans To Be Amended
- •2.2.3 SEZ Program Alternative
- •2.2.3.1 Proposed Right-of-Way Exclusion Areas
- •2.2.3.2 Proposed Solar Energy Zones
- •2.2.3.3 Solar Energy Zone Policies
- •2.2.3.4 Land Use Plans To Be Amended
- •2.3 DOE Alternatives
- •2.3.1 No Action Alternative
- •2.3.2 Action Alternative—DOE’s Proposed Programmatic Environmental Guidance
- •2.3.2.1 General Mitigation Measures
- •2.3.2.2 Institutional and Public Outreach
- •2.3.2.3 Land Use
- •2.3.2.4 Water Resources and Erosion Control
- •2.3.2.5 Biological Resources
- •2.3.2.6 Air Quality
- •2.3.2.7 Cultural Resources and Native American Interactions
- •2.3.2.8 Visual Resources and Aesthetics
- •2.3.2.9 Socioeconomics
- •2.3.2.10 Environmental Justice
- •2.3.2.11 Safety and Health
- •2.4 Description of Reasonably Foreseeable Development Scenario
- •2.4.1 Comparison of RFDS with Lands Available under the Action Alternatives
- •2.5 Other Alternatives and Issues Considered
- •2.5.1 Distributed Generation
- •2.5.2 Conservation and Demand-Side Management
- •2.5.3 Analysis of Life-Cycle Impacts of Solar Energy Development
- •2.5.4 Analysis of Development on Other Federal, State, or Private Lands
- •2.5.5 Restricting Development to Previously Disturbed Lands
- •2.5.6 Restricting Development to Populated Areas
- •2.5.7 Restricting Development to the Fast-Track Project Applications
- •2.5.8 Analysis of Development on the Maximum Amount of Public Lands Allowable
- •2.5.9 Changes to BLM’s Proposed Solar Energy Zones
- •2.5.10 Other Suggested Alternatives
- •2.5.11 DOE Environmental Requirements
- •2.6 References
- •3.1 Technologies
- •3.2 Development Process Overview for All Technologies
- •3.2.1 Site Characterization
- •3.2.2 Site Preparation and Construction
- •3.2.3 Operations
- •3.2.4 Decommissioning and Reclamation
- •3.2.5 Transmission Facilities
- •3.4 Transportation Considerations
- •3.6 Health and Safety Aspects of Solar Energy Projects
- •3.7 Existing Agency Processes and Guidance
- •3.8 References
- •4 UPDATE TO AFFECTED ENVIRONMENT
- •4.1 Introduction
- •4.2 Lands and Realty
- •4.4 Rangeland Resources
- •4.4.1 Livestock Grazing
- •4.4.2 Wild Horses and Burros
- •4.4.3 Wildland Fire
- •4.5 Recreation
- •4.6 Military and Civilian Aviation
- •4.7 Geologic Setting and Soil Resources
- •4.7.1 Geologic Setting
- •4.7.2 Geologic Hazards
- •4.7.3 Soil Resources
- •4.8 Minerals
- •4.9 Water Resources
- •4.9.1 Surface Water Resources
- •4.9.2 Groundwater Resources
- •4.9.3 Water Rights, Supply, and Use
- •4.10 Ecological Resources
- •4.10.1 Vegetation
- •4.10.2 Wildlife
- •4.10.3 Aquatic Biota
- •4.10.3.1 Pacific Northwest Hydrologic Region
- •4.10.3.2 Lower Colorado, Rio Grande, and Great Basin Hydrologic Regions
- •4.10.3.3 California Hydrologic Region
- •4.10.3.4 Upper Colorado River Hydrologic Region
- •4.10.3.5 Missouri River Basin Hydrologic Region
- •4.10.4 Special Status Species
- •4.11 Air Quality and Climate
- •4.11.3 Update to Section 4.11.2.4 of the Draft Solar PEIS: Visibility Protection
- •4.11.4 Update to Section 4.11.2.5 of the Draft Solar PEIS: General Conformity
- •4.11.5 Addition of New Section 4.11.4: Toxic Dust and Snowmelt
- •4.12 Visual Resources
- •4.13 Acoustic Environment
- •4.14 Paleontological Resources
- •4.15 Cultural Resources
- •4.16 Native American Concerns
- •4.17 Socioeconomics
- •4.18 Environmental Justice
- •4.19 References
- •4.20 Errata to Chapter 4 of the Draft Solar PEIS
- •5.1 Introduction
- •5.2 Lands and Realty
- •5.4 Rangeland Resources
- •5.4.1 Livestock Grazing
- •5.4.2 Wild Horses and Burros
- •5.4.3 Wildland Fire
- •5.5 Recreation
- •5.6 Military and Civilian Aviation
- •5.7 Geologic Setting and Soil Resources
- •5.8 Minerals
- •5.9 Water Resources
- •5.10 Ecological Resources
- •5.10.1 Vegetation
- •5.10.2 Wildlife
- •5.10.3 Aquatic Biota and Habitats
- •5.10.3.1 Common Impacts
- •5.10.3.2 Technology-Specific Impacts
- •5.10.4 Special Status Species
- •5.11 Air Quality and Climate
- •5.11.1 Common Impacts
- •5.11.1.1 Construction: Update to Section 5.11.1.2 of the Draft Solar PEIS
- •5.11.1.2 Operations: Update to Section 5.11.1.3 of the Draft Solar PEIS
- •5.12 Visual Resources
- •5.13 Acoustic Environment
- •5.13.1 Common Impacts
- •5.13.1.1 Construction: Update to Section 5.13.1.2 of the Draft Solar PEIS
- •5.13.1.2 Operations: Update to Section 5.13.1.3 of the Draft Solar PEIS
- •5.14 Paleontological Resources
- •5.15 Cultural Resources
- •5.15.1 Common Impacts
- •5.16 Native American Concerns
- •5.17 Socioeconomics
- •5.18 Environmental Justice
- •5.19 Transportation
- •5.20 Hazardous Materials and Waste
- •5.21 Health and Safety
- •5.22 References
- •5.23 Errata to Chapter 5 of the Draft Solar PEIS
- •6 ANALYSIS OF BLM’S SOLAR ENERGY DEVELOPMENT ALTERNATIVES
- •6.1.2 Minimize Environmental Impacts
- •6.1.3 Minimize Social and Economic Impacts
- •6.1.4 Provide Flexibility to Solar Industry
- •6.1.5 Optimize Existing Transmission Infrastructure and Corridors
- •6.1.6 Standardize and Streamline the Authorization Process
- •6.1.7 Meet Projected Demand for Solar Energy Development
- •6.2 Impacts of the SEZ Program Alternative
- •6.2.2 Minimize Environmental Impacts
- •6.2.3 Minimize Social and Economic Impacts
- •6.2.4 Provide Flexibility to Solar Industry
- •6.2.5 Optimize Existing Transmission Infrastructure and Corridors
- •6.2.6 Standardize and Streamline the Authorization Process
- •6.2.7 Meet Projected Demand for Solar Energy Development
- •6.3 Impacts of the No Action Alternative
- •6.3.2 Minimize Environmental Impacts
- •6.3.3 Minimize Social and Economic Impacts
- •6.3.4 Provide Flexibility to Solar Industry
- •6.3.5 Optimize Existing Transmission Infrastructure and Corridors
- •6.3.6 Standardize and Streamline the Authorization Process
- •6.3.7 Meet Projected Demand for Solar Energy Development
- •6.5 Cumulative Impacts
- •6.5.1 Overview of Activities in the Six-State Study Area
- •6.5.1.1 Energy Production and Distribution
- •6.5.1.2 Other Activities and Trends
- •6.5.2 Cumulative Impact Assessment for Solar Energy Development
- •6.5.2.1 Lands and Realty
- •6.5.2.2 Specially Designated Areas and Lands with Wilderness Characteristics
- •6.5.2.3 Rangeland Resources
- •6.5.2.4 Recreation
- •6.5.2.5 Military and Civilian Aviation
- •6.5.2.6 Geologic Setting and Soil Resources
- •6.5.2.7 Mineral Resources
- •6.5.2.8 Water Resources
- •6.5.2.9 Ecological Resources
- •6.5.2.10 Air Quality and Climate
- •6.5.2.11 Visual Resources
- •6.5.2.12 Acoustic Environment
- •6.5.2.13 Paleontological Resources
- •6.5.2.14 Cultural Resources
- •6.5.2.15 Native American Concerns
- •6.5.2.16 Socioeconomics
- •6.5.2.17 Environmental Justice
- •6.5.2.18 Transportation
- •6.6 Other NEPA Considerations
- •6.6.1 Unavoidable Adverse Impacts
- •6.6.2 Short-Term Use of the Environment and Long-Term Productivity
- •6.6.3 Irreversible and Irretrievable Commitment of Resources
- •6.6.4 Mitigation of Adverse Effects
- •6.7 References
- •7 ANALYSIS OF DOE’S ALTERNATIVES
- •7.1 Impacts of DOE’s Proposed Action
- •7.2 Impacts of the No Action Alternative
- •7.3 Cumulative Impacts
- •7.4 Other NEPA Considerations
- •7.4.1 Unavoidable Adverse Impacts
- •7.4.2 Short-Term Use of the Environment and Long-Term Productivity
- •7.4.3 Irreversible and Irretrievable Commitment of Resources
- •7.4.4 Mitigation of Adverse Effects
- •14.1 Public Scoping and Public Outreach
- •14.2 Government-to-Government Consultation
- •14.3 Coordination of BLM State and Field Offices
- •14.4 Agency Cooperation, Consultation, and Coordination
- •14.5 References
- •15 LIST OF PREPARERS
- •16 GLOSSARY
- •FIGURE ES.2-1 Areas Proposed for Exclusion Since Publication of the Supplement to the Draft Solar PEIS Based on Continued Consultation with Cooperating Agencies and Tribes
- •FIGURE ES.2-4 BLM-Administered Lands in Colorado Available for Application for Solar Energy ROW Authorizations under the BLM Alternatives Considered in This PEIS
- •FIGURE 1.2-2 Solar Direct Normal Insolation Levels in the Southwestern United States
- •FIGURE 2.2-3 BLM-Administered Lands in Colorado Available for Application for Solar Energy ROW Authorizations under the BLM Alternatives Considered in This PEIS
- •FIGURE 2.2-7 Areas Proposed for Exclusion Since Publication of the Supplement to the Draft Solar PEIS Based on Continued Consultation with Cooperating Agencies and Tribes
- •TABLE ES.2-3 Proposed SEZs and Approximate Acreage by State
- •TABLE ES.2-5 Summary-Level Assessment of Potential Environmental Impacts of Utility-Scale Solar Energy Development by Alternative
- •TABLE ES.2-6 Comparison of BLM’s Alternatives with Respect to Objectives for the Agency’s Action
- •TABLE 2.2-3 Proposed SEZs and Approximate Acreage by State
- •TABLE 4.15-3 ACECs Designated for Protection of Cultural Resource Values That Are near BLM-Administered Lands Available for Application through the Variance Process
- •TABLE 6.1-2 Summary-Level Assessment of Potential Environmental Impacts of Utility-Scale Solar Energy Development by Alternative
- •TABLE 6.4-1 Comparison of BLM’s Alternatives with Respect to Objectives for the Agencies’ Action
- •TABLE 6.5-10 Recreational Visits for the BLM and NPS in FY 2000 and FY 2010 and for USFS in FY 2000 and FY 2010
1TABLE 3.1-1 Technology-Specific Assumptions for Environmental Impact Analyses
Parameter |
Parabolic Trough |
Power Tower |
Dish Engine |
PV |
Facility power capacities (MW) |
100–400 |
100–400 |
10–750 |
10–750 |
Land area requirements |
5 |
9 |
9 |
9 |
(acres/MW)a |
|
|
|
|
Operational water use |
|
|
|
|
(ac-ft/yr/MW) |
|
|
|
|
Wet (recirculating) coolingb |
4.5–14.5 |
4.5–14.5 |
NAe |
NA |
Dry coolingb |
0.2–1.0 |
0.2–1.0 |
NA |
NA |
Hybrid systemc |
0.9–2.9 |
0.9–2.9 |
NA |
NA |
Mirror/panel washing/otherd |
0.5 |
0.5 |
0.5 |
0.05 |
Chemicals/hazardous materials |
HTF, water |
HTF, water |
Hydrogen tanks; |
Encased |
present on-site |
treatment |
treatment |
herbicides |
semiconductor |
|
chemicals; |
chemicals; |
|
materials; |
|
herbicides |
herbicides |
|
herbicides |
aLand area estimates were based on areas required for existing facilities and estimated areas for proposed facilities. In some cases disturbed area estimates were not available; thus values were based on total plant area (should approximate disturbed area). The estimated land use values for parabolic trough and tower facilities are minimums; the land area requirement could be higher if thermal energy storage (TES) were incorporated into facilities.
bWet-cooling and dry-cooling requirements are based on estimates given as gal/h/MW in DOE (2009). An
assumed range of operational hours of 30 to 60% of annual hours (1 gal = ~3.1 10–6 ac-ft) was used to generate ac-ft/yr/MW values.
cHybrid systems are assumed to use 20% of the water requirements of wet-cooling systems.
dThe mirror washing estimates originate from the assumed 2% of total water needs of wet-cooled parabolic trough facilities from DOE (2009). This estimate equals 20 gal/h/MW, which corresponds to 0.5 ac-ft/yr/MW, with no assumption on operational time (conservative estimate). The panel washing estimate for PV facilities was assumed to be a factor of 10 less than that for CSP technologies (see Appendix M of the Draft Solar PEIS).
eNA = not applicable.
2
3
4 3.2 DEVELOPMENT PROCESS OVERVIEW FOR ALL TECHNOLOGIES
5
6
7 3.2.1 Site Characterization
8
9During site characterization, generally very little modification of the site occurs. The
10activities could include construction of meteorological towers, surface hydrology assessment
11and floodplain mapping, slope evaluation, soil stability studies, due diligence assessment for
12lands with previous industrial uses, evaluation of seismic stability and potential storm event
13runoff, and soil coring (especially where substantial foundations would be required). The site
Final Solar PEIS |
3-2 |
July 2012 |
1characterization phase would include conducting surveys for ecological, cultural, and
2 paleontological resources (including surveys for special status species if needed). Many of these 3 activities would involve minimal or no site disturbance. The more detailed description of these 4 activities provided in the Draft Solar PEIS remains valid.
5
6
7 3.2.2 Site Preparation and Construction
8
9Construction of any solar energy development project is likely to involve the following
10major actions: establishing site access; performing site grading; constructing laydown areas and
11an on-site road system; removing vegetation from the solar field and construction and laydown
12areas (primarily for fire safety); and constructing the solar field, power block area (for parabolic
13trough and power tower facilities), central control building, electrical substations, and
14meteorological towers (if not done during site characterization). Additional activities may also
15be necessary at some facilities, including pile driving, constructing a concrete batching plant,
16constructing sanitary facilities and temporary offices, and landscaping. Construction would
17generally be divided into two phases, which would include a site preparation phase of relatively
18short duration (e.g., a few months) followed by a much longer assembly, testing, and start-up
19phase. The description and information about site preparation and construction activities
20provided in the Draft Solar PEIS remains valid.
21
22
23 3.2.3 Operations
24
25Operation of solar facilities would require varying numbers of on-site personnel,
26depending on the technology and the capacity of the facility; PV facilities might require very few
27(less than 5) personnel on-site daily, whereas larger solar trough or power tower facilities would
28require an operations workforce on the order of 100 individuals. All facilities would require
29facility control staff to monitor solar array and substation operations, and the power block if
30present. All solar facilities would require provisions for reflector/mirror washing at frequencies
31appropriate to the technology being utilized. Facilities utilizing steam cycles and circulating both
32steam water and heat transfer fluids (HTFs) would have additional maintenance activities. The
33description of operations in the Draft Solar PEIS remains valid.
34
35
36 3.2.4 Decommissioning and Reclamation
37
38Decommissioning would include removal of equipment, removal of permanent structures
39and on-site roads, proper closure of all on-site wells, removal of all hazardous materials and
40wastes and closure of related storage areas, remediation of all spills or leaks of chemicals, and
41return of the site to its native state to the greatest extent possible, including re-establishment
42of the native vegetative communities. The removal of electrical substations would require
43inspection for contamination of the soil and decontamination as necessary. The description of
44decommissioning and reclamation in the Draft Solar PEIS remains valid.
45
46
Final Solar PEIS |
3-3 |
July 2012 |
1 3.2.5 Transmission Facilities
2
3 As described in Section 3.2.5 of the Draft Solar PEIS, construction and operation of 4 transmission lines to tie solar energy facilities into the main power grid would be required for
5 most new solar energy facilities. The length of transmission line required would depend on the 6 distance from the site to existing lines having sufficient uncommitted capacity to accept power 7 from the facility (if such lines exist). If no capacity is available on existing lines, it is possible 8 that entirely new lines would be needed to transmit electrical power from solar facilities to load 9 centers (i.e., populated areas with a demand for the generated electricity).
10
11An analysis of the distance from all eligible solar facility locations on BLM-administered
12lands in the six-state study area to the existing transmission grid or to federally or locally
13designated transmission corridors was provided in the Draft Solar PEIS; the analysis showed that
14few locations are greater than 25 mi (40 km) from these existing lines or corridors1
15(see Appendix G of the Draft Solar PEIS).
16
17The general information on transmission facilities provided in Section 3.2.5 of the Draft
18Solar PEIS remains valid. The following paragraphs describe the changes in the analysis of the
19impacts of construction and operation of transmission facilities to support solar energy
20development that are being presented in this Final Solar PEIS.
21
22In Chapter 5 of the Draft Solar PEIS, a general analysis of the impacts of transmission
23line construction and/or line upgrades was provided for each resource area addressed. The
24description of these impacts remains valid.
25
26The analysis of transmission impacts for the proposed SEZs presented in the Draft Solar
27PEIS assumed land disturbance from construction of a new line from each SEZ to the nearest
28existing transmission line; it was acknowledged that if additional construction or line upgrades
29were necessary for specific solar projects within SEZs, developers would need to analyze those
30environmental impacts. The transmission analysis for the SEZs did not evaluate the available
31capacity on existing lines; the assumption was made that existing lines could be upgraded if
32additional capacity were needed. Comments were received stating that this assumption was
33generally not valid because of almost full allocation of the transmission grid capacity in the study
34area. These comments correctly pointed out that it was possible that new transmission line
35construction might be required to transport power from the SEZs along at least part of the route
36to the purchasing load center. For this Final Solar PEIS, an analysis for each SEZ has been added
37estimating the potential costs and land disturbance associated with constructing new transmission
1 Subtitle F of the Energy Policy Act of 2005 required various federal agencies, led by the DOE and the BLM, to designate corridors for energy transmission in the 11 western states, including the six-state study area of this PEIS. Local BLM offices have also designated corridors under separate authorities. Both federally and locally designated corridors are addressed in the Programmatic Environmental Impact Statement, Designation of Energy Corridors on Federal Land in the 11 Western States (Corridor PEIS) (DOE and DOI 2008). The Corridor PEIS, as well as various state and regional initiatives, such as California’s Renewable Energy Transmission Initiative (RETI) (see http://www.energy.ca.gov/reti/index.html and Appendix D of this PEIS), should help to facilitate solar development by creating corridors through which power from remotely located solar facilities can be efficiently delivered to customers with minimum adverse impacts.
Final Solar PEIS |
3-4 |
July 2012 |
1 lines along the entire route to likely load centers. These analyses also include estimates of costs 2 and land disturbance associated with required new transmission substations, as requested in
3comments. The new analyses provide upper bound estimates of the costs and environmental
4impacts (in terms of land disturbance) of providing transmission to each of the SEZs. SEZ-
5 specific dedicated line transmission (DLT) analyses are provided for each of the proposed SEZs 6 carried forward in the Supplement to the Draft Solar PEIS (BLM and DOE 2011) in Chapters 8 7 through 13 of this Final Solar PEIS.
8
9
103.3 LAWS AND EXECUTIVE ORDERS POTENTIALLY APPLICABLE TO SOLAR
11ENERGY AND TRANSMISSION LINE PROJECTS
12
13Section 3.3 of the Draft Solar PEIS discussed in general terms the existing major laws,
14E.O.s and policies that might impose environmental protection and compliance requirements on
15the siting, construction, operation, and decommissioning phases of utility-scale solar energy and
16transmission line projects. Related lists of specific E.O.s, federal and state laws, and county
17ordinances that might be applicable, were provided in Appendix H of the Draft Solar PEIS. The
18information presented in Section 3.3 of the Draft Solar PEIS remains valid, with the following
19update.
20
21The text of Section 3.3 of the Draft Solar PEIS stated the following regarding noise: “The
22EPA issued guidelines for outdoor noise levels that are consistent with the protection of human
23health and welfare against hearing loss, annoyance, and activity interference. The guidelines
24state that annoyance and undue interference with activity will not occur if outdoor levels of noise
25are maintained below an energy equivalent of 55 dB. However, these levels are not legally
26enforceable standards.” Note that noise and soundscape protection policies have been developed
27by the NPS. These policies are discussed in Section 5.13 of this Final Solar PEIS.
28
29
30 3.4 TRANSPORTATION CONSIDERATIONS
31
32Section 3.4 of the Draft Solar PEIS addressed transportation requirements to support
33solar energy development during construction, operations, decommissioning, and reclamation.
34This information is summarized below; there are no updates for this section.
35
36In general, heavy equipment and materials needed for site access, site preparation, and
37solar array foundation construction are typical of road construction projects and do not pose
38unique transportation considerations. Solar collectors would be assembled on-site, and materials
39would be delivered to the project location by regular truck shipments without the need for
40oversize or overweight permits. The total number of shipments over the course of the
41construction period would depend on the type of solar technology and the size of the facility. The
42number of workers required during different phases of development would vary, but increased
43commuter traffic in the vicinity of the project may require road improvements or other measures
44to alleviate congestion or traffic hazards. Deliveries of materials during operations could also
45include hazardous materials such as fuels or ammonia. Shipments from facilities would include
46wastes for disposal.
Final Solar PEIS |
3-5 |
July 2012 |
