Appendix 4
WHAT IS A GANTT CHART?
A Gantt chart is a project management tool used to plan and visualize tasks over a specified timeline. It shows each task's start dates, duration, and end dates in a project schedule. A bar stretching across the timeline represents each task, showing how long it'll take. This makes it easy to track progress, as you can easily gauge whether each task is on time or overdue.
In addition to the basic information about tasks and timelines, Gantt charts show dependencies between project tasks. For instance, if one task needs to be completed before another one can begin (e.g., buying materials before construction starts), this is indicated with an arrow connecting the two tasks in the chart.
Why is a Gantt chart important?
Gantt charts are essential for project planning, as they provide a concise visual overview of the project timeline and enable you to monitor progress. Here are some advantages of using Gantt charts for project management:
1. Visually track project progress
With Gantt charts, it's easy to see how much work has been done and how much is left to do in a project. You can also easily spot tasks running behind schedule or identify potential problems before they become major issues.
2. Plan dependencies between tasks
A Gantt chart makes it easier to plan dependencies between tasks, ensur­ing that activities happen in the correct order according to your schedule. This ensures efficient use of resources and helps to keep the timeline on track.
3. Streamline communication
A Gantt chart is a concise way to communicate the project schedule and project updates with everyone involved, from team members to stakeholders. This clearly lays out what needs to be done and makes it easier for everyone to understand how their tasks fit into the bigger picture.
How do I create a Gantt chart?
Now that you've seen some Gantt chart examples let's look at how you can create one for your projects. Two main ways to make a Gantt chart are in Excel or in project management software.
61
Create a simple Gantt chart using Excel
Excel is a popular spreadsheet software from Microsoft that everyone is familiar with. Hence, the most straightforward way to create a Gantt chart is by using Excel.
To do this, you'll need to:
Set up and format your data in an Excel spreadsheet. This should in- clude tasks, start and end dates, duration, and the task owner.
Then insert a bar chart into the spreadsheet and customize it with your data. You can add different colors or patterns to differentiate between tasks.
Adjust the format to look like a Gantt chart (i.e., adding task labels and changing scales and structures).
Your chart is ready and can be shared with stakeholders and the project team.
With Microsoft Excel, you can create a simple but effective Gantt chart to help you stay organized and on track with your project.
62
Appendix 5
PROJECT CHARTER TEMPLATE
Some organizations like to keep their project charters to a single page. This concise version of our project charter is a one-page version which in­cludes all the essential elements of a charter. This concise version states the scope of the project, gives the Project Manager authority over the project, provides summary milestones, states the project budget and identifies funding sources. We also have a longer version of our project charter which spans multiple pages.
Project Charter Template (Single Page Version)
Paragraph 1: Formally authorize the project in this section of the Project Charter.
This Charter formally authorizes the Payroll Project to develop and im­plement a new payroll system for use in Jones Consulting Company’s payroll group. A project plan will be developed and submitted to the Project Sponsor for approval. The project plan will include: scope statement
; schedule; cost estimate; budget; and provisions for scope, resource, schedule, communica­tions, quality, risk, procurement, and stakeholder management as well as project control. All resources will be assigned by the Project Sponsor, Van Johnson, Human Resources Director.
Paragraph 2: Project Scope – State the scope of the project, its deliverable and what business needs, problems or opportunities the project addresses – a market demand, business need, legal requirement, social need, customer re­quest or technological advance.
The purpose of the Payroll project is to improve the
timeliness and accu-
racy of payroll operations. This project meets Jones Consulting’s need for improved efficiencies across all departments by reducing payroll cycle time and minimizing staffing required for payroll operations. The project delive­rables shall include payroll system design, all coding, testing, implementation of an integrated system for use with
existing IT infrastructure, and a user’s
guide. The objectives of the Payroll project are to reduce payroll cycle time
63
by 30 % and reduce payroll staffing by 20 %. High level risks for this pro­ject include ensuring implementation is completed without impacting on­going payroll operations and ensuring there are no issues with migrating payroll accounts from the legacy system to the new system. Success will be determined by the Project Sponsor
once the system is implemented and one full payroll cycle has been completed that meets the objectives with no discrepancies.
Paragraph 3: Identify the Project Manager and give him authority to
apply organization resources to the project.
The Project Manager, Bill Smith, is hereby authorized to interface with management as required, negotiate for resources, delegate responsibilities within the framework of the project, and to communicate
with all contractors and management, as required, to ensure successful and timely completion of the project. The Project Manager is responsible for developing the project plan, monitoring the schedule, cost, and scope of the project during imple­mentation, and maintaining control over the project by measuring perfor­mance and taking corrective
action.
Paragraph 4: Provide the summary milestone schedule in the Project
Charter.
The project plan will be submitted and approved in accordance with the milestone schedule below. Upon approval of the project plan resources will be assigned to the project and work will commence within 5 business days. The Project Sponsor must approve any schedule changes which may impact milestones
. A detailed schedule will be included in the project plan. The high
level milestone schedule is:
Feb 1, 20xx – Project Plan Complete and Approved
Mar 31, 20xx – Payroll Design Completed
May 31, 20xx – Coding Completed
June 30, 20xx – Testing Completed
July 31, 20xx – Beta Testing Completed
Sept 30
, 20xx – Implementation Completed
Oct 15, 20xx – One Payroll Cycle Complete and Project Completion
Paragraph 5: Project Budget – state the budget for the project and iden­tify funding sources.
64
The budget for the Payroll project is $420,000. It is to be funded through the FYxx Human Resources Technology Budget.
Sponsor Acceptance
Approved by the Project Sponsor:
_____________________________________Date:____________________ <Project Sponsor Name> <Project Sponsor Title>
65
REFERENCES
1. Drew C. (July 29, 2023). 101 Long-term Personal Goals Examples. Helpful
Professor. Available at: http://heplfulprofessor.com/long-term-personal-goals-exam­ples (accessed 1 April, 2025)
2. Eby K. (January 3, 2023) Project Management Examples: Success, Stories
case Studies, and Examples. Available at: https://www.smartsheet.com/content/suc­cessful-project-examples (accessed 1 April, 2025)
3. Free Single Page Project Carter Templates – Project Management Docs. Available at: https://www.projectmanagementdocs.com/template/project-initiation/ project-charter-single-page-version (accessed 1 April, 2025)
4. Gantt Chart. What it is, How it works, Examples. Available at: https://learn­ingloop.io/glossary/gantt-chart (accessed 1 April, 2025)
5. Kerzner E (2019) Project Management: Best Practices. 4th ed. International Institute for Learning, Inc., Wiley.
6. Adriana Girdler, CET, PMP – CornerStone Dynamics. Available at: https://www.cornerstonedynamics.com/adriana-girdler (accessed 1 April, 2025)
66
CONTENTS
Unit 1. GOAL SETTING ........................................................................................... 3
Unit 2. PROJECT TERMINOLOGY ...................................................................... 11
Unit 3. PROJECT ACTIVITY LIST ....................................................................... 18
Unit 4. TEAMWORK .............................................................................................. 26
Unit 5. PROJECT RISKS ........................................................................................ 32
Unit 6. PROJECT BUDGETING ............................................................................ 39
Unit 7. PROJECT COSTS ....................................................................................... 47
Appendix 1. How to create a project presentation. A guide for impactful
content ................................................................................................. 54
Appendix 2. Project Management Examples: Success, Stories case Studies,
and Examples. Part 1 ........................................................................... 58
Appendix 3. Project Management Examples: Success, Stories case Studies,
and Examples. Part 2 ........................................................................... 60
Appendix 4. What is a Gantt chart? ......................................................................... 61
Appendix 5. Project Charter Template .................................................................... 63
References ................................................................................................................ 66
67
Хвостенко Анна Александровна
Ридная Юлия Викторовна
Кривенко Елена Владимировна
АНГЛИЙСКИЙ ЯЗЫК
ДЛЯ МАГИСТРАНТОВ
ВВЕДЕНИЕ В УПРАВЛЕНИЕ
ПРОЕКТНОЙ ДЕЯТЕЛЬНОСТЬЮ
ENGLISH FOR MASTER STUDENTS
INTRODUCTION TO PROJECT
Учебное пособие
В авторской редакции
Выпускающий редактор И.П. Брованова
Дизайн обложки А.В. Ладыжская
Компьютерная верстка Л.А. Веселовская
Налоговая льгота – Общероссийский классификатор продукции
Издание соответствует коду 95 3000 ОК 005-93 (ОКП)
__________________________________________________________________________
Подписано в печать 10.04.2025. Формат 60 × 84 1/16. Бумага офсетная. Тираж 50 экз.
Уч.-изд. л. 3,95. Печ. л. 4,25. Изд. № 62. Заказ №
__________________________________________________________________________
Отпечатано в типографии
Новосибирского государственного технического университета
630073, г. Новосибирск, пр. К. Маркса, 20
MANAGEMENT
110. Цена договорная
68
Соседние файлы в предмете [НЕСОРТИРОВАННОЕ]