Добавил:
Upload Опубликованный материал нарушает ваши авторские права? Сообщите нам.
Вуз: Предмет: Файл:

2015 ARKH-P6-Project Management

.pdf
Скачиваний:
13
Добавлен:
11.03.2016
Размер:
8.24 Mб
Скачать

CONTRACTUAL STRATEGY

DEFINITION

The Contractual Strategy addresses the Contractual Organisation of the realisation of the Plant, organising the split of the realisation into different contracts and purchase orders

It defines the scope of work for each contract/purchase order

It examines the potential synergies obtained in grouping together a number of activities in order to allow the optimisation of

the Means,

the Work Time Schedule,

the Costs.

It is expressed through the Contractual Plan, i.e. the Contractual organisation based on the consistent breakdown of the realisation process of all elements of the Plant into manageable contracts.

There is a large choice of possibilities: from a step by step approach up to a global contract taking care of everything - the Turn key contract.

11

CONTRACTUAL STRATEGY MAIN ALTERNATIVES

SEPARATE CONTRACTS

EPSC

EPSCC

TURN KEY

 

PROCUREMENT /SUPPLY

 

BASIC

DETAIL

CONSTRUCTION

COMMISSIONINGTEST

PRE PROJECT

 

DESIGN

ENGINEERING

 

PROC / SUPPLY LLI

 

 

BASIC

PRE PROJECT ENG / PROC-SUPP/ CONSTRUCTION COMMISSIONINGTEST DESIGN

PROC / SUPPLY LLI

BASIC

PRE PROJECT ENG / PROC-SUPP/ CONSTRUCTION/COMM TEST DESIGN

PROC / SUPPLY LLI

PRE-PROJECT/ CALL FOR TENDER BASIC DESIGN /

DETAILED ENGINEERING /

CONSTRUCTION…………/

COMMISSIONING TESTS

 

Y1

 

Y2

 

Y3

 

Y4

12

 

 

 

 

 

 

 

 

 

 

CONTRACTUAL STRATEGY

Development of SOUTH PARS Phases 2 and 3

28th September 1997 : Contract Signature 1st June 02 : First Production

Dec 02 : start handover operation to NIOC

13

 

SOUTHPARS - Development Scheme

COMMON FACILITIES: (DEVELOPED BY NIOC)

56” EXPORT LINE

SULPHUR HARBOUR CONDENSATE EXPORT SYSTEM

 

 

ONSHORE GAS TREATMENT PLANT

 

 

 

 

 

 

GAS LIQUID SEPARATION

 

 

 

 

 

 

4 PROCESS TRAIN

 

 

 

2 SUB SEA PIPELINES

 

 

2 BSCFD PROCESSING CAPACITY

 

 

 

 

 

 

 

 

32” AND 104 KM LONG

 

 

77,000 b/d CONDENSATE

 

 

 

 

 

 

 

 

WET SCHEME FOR RAW GAS

 

 

500 t/d SULPHUR

 

 

 

2 OFFSHORE PLATFORMS :

 

 

 

 

TRANSPORTATION

 

 

 

 

 

 

 

70 M. WATER DEPTH

 

 

 

 

 

 

 

41/2” PIGGY BACK LINE FOR MEG

NOT NORMALLY MANNED

 

 

 

 

 

 

 

TRANSPORTATION

 

 

 

 

 

 

 

MEG INJECTION OFFSHORE FOR

REMOTE FLARES

 

 

 

 

 

 

 

 

 

 

 

 

 

 

CORROSION CONTROL

10 DEVELOPMENT WELLS EACH

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

SPD3

 

 

 

 

 

 

 

 

 

 

SPD4

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

14

CONTRACTUAL STRATEGY

SP 2/3 Contract Plan - Project Execution Plan

PJT PREPARATION

Project definition

Surveys

Basic Engineering

LONG LEAD ITEMS

Line pipe ( 32" & 4 1/2")

Main structural Steel Platforms 32" valves

Test separators for WHP's Gas Turbine generator Steam turbine Generator Export Gas compressor Propane compressor Reciprocating compressor DCS / ESD

High voltage switch gear & PDCS

EARLY CONTRACT

Onshore Plant Site Preparation

EPSCC

Detail eng., procurement, Supply, Construction, Commissioning

PJT MANAGEMENT, INSPECTION, SUPERVISION, START UP

ONSHORE PLANT

 

 

OFFSHORE FACILITIES

 

 

 

 

SEALINES

 

PLATFORMS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

T.S.P + TECHNIP

 

 

 

 

 

 

 

 

 

 

MANDRO

 

GEOID

 

 

FUGRO ENG

 

FUGRO OCEANIC

 

 

 

 

 

 

TECHNIP + ( ELF, IFP )

 

 

SOFRESID / KVAERNER

 

 

 

 

 

 

 

 

SALZGITTER

MANNESMANN

TORMENE

MANGIAROTTI

ALSTOM

FRAMATOME

NUOVO PIGNONE

DEMAG

NUOVO PIGNONE

KVAERNER

ALSTOM

KAYSON / BEC

HDEC HHI NPCC

TSP & THIRD PARTIES

15

CONTRACTUAL STRATEGY

EXAMPLE OF GIRASSOL PROJECT CONTRACTUAL PLAN

Drilling

FPSO &

Loading Buoy

Umbilicals &

Deep water lines - UFL

Production System

Underwater - SPS

16

CONTRACTUAL STRATEGY:

EXAMPLE OF GIRASSOL CONTRACTUAL PLAN

 

 

 

 

1

 

2

 

3

 

 

 

 

Phase

SPS

UFL

FPSO & BUOY

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Conceptual Studies

 

 

 

TFEA

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

FEED

Design Competition

Design Competition

 

EPCI Risk and

 

 

 

 

 

 

 

 

Reward Lump Sum

 

 

Detailed Engineering

EPC Lump Sum

EPCI Lump Sum

 

 

 

Contract

 

 

 

 

 

Contract

 

 

 

 

Procurement

 

 

Contract

 

 

 

 

 

 

 

 

 

 

 

 

 

 

MAR PROFUNDO

 

 

 

 

 

 

 

ALTO MAR

 

 

 

Construction

 

 

 

 

 

 

 

KONGSBERG

 

GIRASSOL (MPG)

 

 

 

 

 

GIRASSOL (AMG)

 

 

 

Transport

 

OFFSHORE

 

JV BOS/STOLT

 

 

 

 

 

 

 

 

 

 

 

 

 

 

JV BOS/STOLT

 

 

 

Offshore Installation

 

 

 

 

OFFSHORE

 

 

 

 

 

OFFSHORE

 

 

 

 

 

 

 

 

 

 

 

 

 

Hook-up/Tie-in

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Commissioning

 

 

 

TOTAL

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Start Up

 

With contractors’ assistance

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4

 

 

 

 

 

 

 

 

 

4: Drilling Units :

 

 

PRIDE FORAMER

 

 

 

 

 

 

 

 

 

 

 

 

17

PROJECTS CONTRACT

Main Contract documents for an EPSC/EPSCC

 

 

 

 

 

 

 

 

 

 

 

 

 

INSTRUCTIONS TO TENDERERS

 

 

 

 

 

 

 

 

 

ITT

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(Introduction & Instructions)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

AGR.

 

 

 

 

AGREEMENT & ANNEXES

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(Terms & Conditions)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

EXHIBITS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(Scope & Requirements)

 

 

 

 

 

 

 

 

 

Scope

 

Design

 

 

 

 

 

 

 

 

A

 

E

 

I

Company

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Dossier

 

 

Items

 

 

 

 

 

 

 

Schedule

 

Particular

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

B

 

F

 

J

Subcontractors

 

 

 

 

 

 

 

 

 

 

of Prices

 

Conditions

 

 

& Vendors

 

 

 

 

 

 

 

Work Time

 

Co-ordination

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

C

 

G

 

K

Contractors

 

 

 

 

 

 

 

 

 

 

Schedule

 

Procedure

 

 

Organisation

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

D

 

Performance

H

Quality

 

L

HSE

 

 

 

 

 

 

 

 

 

 

Guarantees

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

18

PROJECTS CONTRACT

Main Contract documents for an EPSC/EPSCC

AN EPSC / EPSCC CONTRACT CONTAINS THREE MAIN PARTS: AGREEMENT, ANNEXES, EXHIBITS.

THE AGREEMENT (in the range of a 120 page document) IS OFTEN CONSIDERED AS THE LEGAL PART OF THE CONTRACT. CERTAINLY IT IS MUCH MORE AS MOST OF THE FUNDAMENTALS OF THE PROJECT ORGANISATION COMMON RULES ARE INCLUDED: i.e. RELATION BETWEEN THE PARTIES, REPORTING, SAFETY….

THE AGREEMENT IS DIVIDED INTO CHAPTERS AND EACH CHAPTER, SPECIFIC OF ONE KEY PART OF THE RELATIONSHIPS BETWEEN OPERATOR AND CONTRACTOR, INTO ARTICLES.

THE AGREEMENT IS SPECIFIC TO ONE PROJECT AND IS PREPARED FROM COMPANY STANDARD CONDITIONS

19

PROJECTS CONTRACT

Main Contract documents for an EPSC/EPSCC

.

THE COMBINATION OF THE AGREEMENT (+ IT’ANNEXES) AND THE EXHIBITS

CONSTITUTES THE CONTRACT

THESE DOCUMENTS IN THEIR ORIGINAL VERSION PREPARED BY THE OPERATOR ARE THE BODY OF THE CALL FOR TENDER

FOLLWING RECEIPT OF THE BIDS,CLARIFICATIONS AND NEGOCIATIONS,THE MAIN CONTRACT DOCUMENTS WILL BE FINALISED

PRIOR TO THE AWARD

THE CONTRACT WILL REMAIN THE REFERENCE DOCUMENT DURING THE COURSE OF THE PROJECT

20

Соседние файлы в предмете [НЕСОРТИРОВАННОЕ]