2015 ARKH-P6-Project Management
.pdfPROJECT CONTRACTS
Contract Award Process
PRESELECTION STEP/ MARKET SURVEY
Pre-selection means: thorough analysis of selected companies to check their capabilities to perform: technically, structurally, availability of means and personnel, reference for similar jobs.
The pre-selection process is not always needed (the company may have already enough experience of a specific market).
But it can be a very useful step when the knowledge of the potential contractor/supplier is insufficient.
The process may last several months: preparing a list of companies and a questionnaire , checking their data, visiting some of them if necessary, obtaining management approval for the final list.
21
PROJECT CONTRACTS
Contract Award Process
HOW TO PERFORM THE PRESELECTION ?
Preparing the questionnaire:
Contractor side :all details, organisation ,references, consortium? JV? ….
Company side : why such a questionnaire, project description ,scope of the potential contract
The points to be clarified: competences, expertise, means, premises ,..
How and when to answer
Contacting potential contractors, checking their willingness to answer. Recommendation for consortium.
Confidentiality
22
PROJECT CONTRACTS
Contract Award Process
INSTRUCTION TO TENDER
The document is to present the procedure to be followed by the potential contractors to submit their proposal to the Client adressing following aspects :
Definitions: tender, tenderer, work…..
Acknowledgement by tenderer
Closure date
Conditions of tender: cost of tender, partial or full answer, company acceptation and right to reject, …
Bid bond
confidentiality
Conditions for alternative tender
Validity of the tender
The way to take exceptions to the Company’s requirement
Clarification procedure
23
PROJECT CONTRACTS Contract Award Process
Tendering Procedure
|
|
|
|
Prequalification of potential Tenderers |
|
|
|
|
|
|
4 to 8 months |
|
Preparation of the call for tenders (by client) |
|
|
|
|
||
|
|
|
|
Conditions for tender preparation & issue |
|
|
|
|
|
|
|
|
|
Contract conditions (clauses, prices, etc…) |
|
|
|
|
Scope of work and specifications |
|
|
|
2 to 6 months |
|
|
|
|
|
Tenders preparation (by Tenderer) |
|
|
|
|
|
|
|
|
|
Technical and commercial |
|
|
|
|
Competition analysis |
|
|
|
|
Positioning and tender submission |
2 to 4 months
Tenders analysis (by Client)
Receipt and formal opening
Comparison
Clarification meetings
Additional submissions
Evaluation and recommendations
??Decision
24
PROJECT CONTRACTS
Tendering Procedure Opening of the Tenders
Several philosophies exist for Tenders opening:
|
|
|
|
Technical and |
Updated tenders |
|
|
contractual |
|
|
|
|
|
|
|
Analysis, clarifications, |
|
Recommendation |
|
|
|
||
|
|||
|
confirmations |
|
|
Commercial |
|
||
|
|
||
|
|
|
|
|
|
|
|
|
|
|
|
Same opening date
|
|
Commercial |
|
|
|
Short |
|
|
|
|
list |
|
|
|
|
Updated tenders |
|
|
|
|
|
|
|
|
Technical and |
Analysis, clarifications, |
|
Lowest bid |
|
contractual |
technical confirmations |
|
||
|
selected |
|||
|
|
|
||
|
|
|
||
|
|
|
|
|
Technical opening date
25
PROJECTS CONTRACT
Contract Award Process
. |
FINAL SELECTION |
|
Opening of final tenders and selection of the Contractor
After having checked that each tenderer has accepted (through his initialling) the Contract conditions, the Operator opens the commercial proposals.
The selection is made in principle on the lowest price basis, or at least on the most economical solution, based upon “Life cycle cost” (OPEX +CAPEX)
If it is not the case, the Operator is usually requested to document his decision, (detailed scored evaluations)
To accept at the last minute an uncontrolled price reduction from one contractor outside the normal competitive procedure would be :
Risky, as the Contractor will probably try to recover such reduction during the performance of the Contract
Unfair to the other Tenderers (and counter-productive for next project)
26
PROJECT CONTRACTS
Contract Award Process
AWARDING THE CONTRACT
•Through a preliminary agreement (MOU, letter of intent)
•With conditions precedent (i.e. subject to state agreement)
•Full and definitive signing
27
PLANNING & PROGRESS CONTROL
THE PLANNING FUNCTION: WHY ?
To determine the time required to achieve a Project
To optimize the cash flow in line with the Project requirements To provide the economics with schedule information
To follow-up the mobilisation of means (human resources and equipment To identify any potential deviations from the initial planning
To quantify the current progress (i.e. monthly percentage) To forecast the future taks and events
At any time during the project life
28
PROJECTS CONTRACTS: WBS (Work Breakdown Structure)
TYPICAL
PROJECT
Major Work Split = M.W.S.
BASIC |
PLTF1 |
FPSO |
Work Unit = W.U.
Onshore |
Offshore |
Jacket |
Deck |
Hull |
Topsides |
Onshore Plant |
Links |
Unit 1 |
Wharf |
Pipeline |
S/S Cable |
SPS |
X-Tree |
Manifolds |
Sub Work Unit = S.W.U.
Engineering |
Engineering |
Procurement |
L.L.I. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
details of SWU |
|
|
|
|
|
- Process Design |
|
|
|||||||||
|
|
|
|
- Safety |
- L.L.I. 1 (TC's) |
||||||||||
|
|
|
|
- Pressure Vessels |
- L.L.I. 2 |
(TG's) |
|||||||||
|
|
|
|
- Civil Works |
- L.L.I. 3 |
(Pumps) |
|||||||||
|
|
|
|
- Structure |
- etc... |
|
-Piping / Install
-Valves / mater.
-Mechanical
-Electrical
-Instrumentation
-Control System
-Architectural
-Telecom
-Package
-Protection Insul.
-Links / Pipelines
-Naval architect.
-Procurement
Onshore |
Transportation |
Installation |
Offshore |
Commissioning |
|
Construction |
|
|
Construction |
|
|
Prefabrication |
|
Prefabrication |
Preparation |
||
|
|
|
|
|
|
Decommissioning |
|
Decommissioning |
Realisation |
|
Erection |
|
|
|
Off-Shore Works |
|
- On-Shore |
|||||
|
|
|
||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
- Off-Shore |
|
|
|
|
|
|
|
|
|
|
|
-Equipment
-Civil Works
-Structure
-Piping
-Electrical
-Instrumentation
-Architectural
-Painting
-Insulation
-Mech.Complet.
-Equipment
-Civil Works
-Structure
-Piping
-Electrical
-Instrumentation
-Architectural
-Painting
-Insulation
-Mech.Complet.
29
PLANNING PREPARATION
Planning (or scheduling) is one of the fundamental task and tools of the Project Management.
A Bar Chart is the most common way to schedule a project by non specialist.
A Bar Chart is easy to prepare, easy to read.
But a bar chart is not enough to evaluate a complex sequence of tasks.
A Bar Chart is totally insufficient to schedule a project.
A Pert network or CPM is in fact the only way to have a realistic view of a project, then bar charts can be produced from the network.
30