- •Version 1.0g
- •The tag Introduction to prince2
- •Course Objectives – Classroom Preparation Course
- •Course Contents
- •Organization
- •Project Organization Introduction
- •What is a Programme?
- •Organization Roles
- •The Executive Role
- •The Senior Supplier Role
- •The Project Manager Role
- •The Team Manager Role
- •The prince2 Process Model Diagram
- •Process Model Diagram Introduction
- •Direction
- •Initiating a
- •Delivery
- •Process Model Using Color
- •Four Management Levels
- •Process Model – Processes
- •Initiating a Project (ip)
- •Exercise Diagram
- •Work Package mp Outputs
- •The prince2 Process Model
- •Direction
- •Delivery
- •Project Mandate Contents
- •Direction
- •Delivery
- •Su: Starting Up a Project
- •Starting Up a Project: Three main deliverables
- •Starting Up a Project Activities
- •Direction
- •Delivery
- •Su: Project Approach
- •Direction
- •Delivery
- •Карпова ______________________
- •Su: Assemble Project Brief
- •Direction
- •Delivery
- •Su: Plan the Initiation Stage
- •Plan the Initiation Stage Tasks
- •Direction
- •Delivery
- •Request to Initiate a Project
- •Dp: Authorize initiation
- •Direction
- •Ip: Initiation Stage
- •Initiating a Project Process introduction
- •Direction
- •Delivery
- •Initiating a Project Process – 8 Activities
- •Ip: Project Initiation Documentation (pid)
- •Project Initiation Documentation
- •Project Initiation Documentation Contents
- •Direction
- •Delivery
- •Sb: Managing a Stage Boundary after the Initiation Stage
- •Direction
- •Delivery
- •Inputs:
- •Dp: Authorize the project
- •Direction
- •Delivery
- •Cs: Controlling a Stage
- •Direction
- •Initiating a
- •Delivery
- •Cs: Controlling a Stage / Managing Product Delivery
- •Assign Work to Teams using Work Packages
- •Direction
- •Delivery
- •Initiation Stages - Execution
- •Managing Product Delivery Objectives
- •Mp: Managing Product Delivery: Outputs
- •Direction
- •Delivery
- •Initiation Stages - Execution
- •Cs: Controlling a Stage – Give ad hoc direction
- •Direction
- •Delivery
- •Initiation Stages - Execution
- •Cs: Project Manager Day to day activities
- •Direction
- •Delivery
- •Work Package
- •Initiation Stages - Execution
- •Sb: Managing a Stage Boundary
- •Managing a Stage Boundary and Objectives
- •Direction
- •Delivery
- •Initiation Stages - Execution
- •Managing a Stage Boundary Outputs
- •Dp: Authorize a Stage or Exception Plan
- •Authorize a Stage or Exception plan
- •Direction
- •Delivery
- •Initiation Stages - Execution
- •Exception Plans - Authorize a Stage or Exception Plan Activity
- •Last Controlling a Stage Process
- •Cp: Closing a Project: Introduction and Objectives
- •Closing a Project and Premature Close
- •Direction
- •Delivery
- •Closing a Project Objectives
- •Cp: Closing a Project Outputs
- •Closing a Project Outputs
- •Direction
- •Delivery
- •Last actions for Project Manager in Closing a Project
- •Dp: Authorize project closure
- •Project Board activities in “Authorize project closure”
- •Direction
- •Delivery
- •“Authorize project closure” activity outputs
- •Summary
- •Course Summary
- •Direction
- •Initiating a
- •Delivery
- •Learn Thru Questions
- •Introduction
- •About Learn Thru Questions
- •Introduction to prince2
- •Acknowledgements
- •Distribution Copyright
- •Customize this book
- •About the Author
- •The prince2 Training Manual: Book
- •About tag
- •The Process Model Learn Thru Questions
- •Appendix a
- •Appendix b Simple Glossary
- •Issue Register
Closing a Project Objectives
The Project Manager carries out the work in Closing a Project, and the objectives are:
Check that all required products have been delivered and accepted.
Capture lessons learned in the Lesson Report, as this can be valuable for future projects.
Ensure that the products can be supported after the project is disbanded.
Hand over products to the customer, as described in the Configuration Management Strategy document.
Evaluate the project by comparing project objectives with actuals, and write the End Project Report.
Assess the benefits already realized and plan a review of benefits that will be realized after the project is complete.
Cp: Closing a Project Outputs
Closing a Project Outputs
The Closing a Project diagram shows that the Project Manager provides some documents to the Project Board and other documents to the Operations/Maintenance group who will support the products once the Project is complete.
Corp..
Corporate or Programme Managementwww.Mgm tPlaza.com
Direction
Project Board
Directing a Project (DP)
Authorize a Stage or Exception Plan
Management
Project Manager
Authorize stage
End Stage Report Next Stage Plan or Exception Plan
Give ad hoc direction
Closure Notification
close soon
Auth. project closure
Highlight Reports
Advice
Premature Close
Closure Recommend. End Project Report FAR, Lessons Rpt Draft Closure Notificat.
CP
To: P ro je c t Bo a rd
ERP , LR, PP, BRP, draft PCN
To: Op s /Ma int.
FAR, Products, CIR
Exception Report
(Issue / Change & Risk)
(SB) Managing a Stage Boundary
Controlling a Stage (CS)
Closing a project (CP)
Clo s e d
LL, DL, RR, IR, QR
Clos in g a P ro ject outputs
End Project Report
Follow on actions recommendations
Lessons Report
Project Plan & Benefits Review Plan
Project Closure Notification & CIR
Delivery
Team Manager
Based on OGC PRINCE2® material. Reproduced under license from OGC
Stages - Execution
Close
Fig 3.21 Closing a Project outputs
The documents given to the Project Board are:
The End Project Report (ERP): This is written by the Project Manager and compares the project with the Project Initiation Documentation.
The Lessons Report (LR): This records useful lessons that were learned during the project and can be applied to future projects.
Other documents given to the project board are: Project Plan (PP), which has been kept up to date during the project, Benefits Review Plan (BRP), and draft Project Closure Notification.
The Project Manager provides the Operations / Maintenance group with:
The follow on actions recommendations (FAR): This is a document that includes information on outstanding issues that are taken from the Issue and Risk Logs and requires follow-up action after the project has ended.
The Project Manager also hands over product information, including the Configuration Item Records (CIR) for each product, to the operations and Maintenance Group.