Methodology to Aircraft Design, Market Survey, and Airworthiness

 

Table 2.1. Development costs up to certification included

 

 

 

 

 

 

 

 

 

 

 

 

 

Aircraft class (turbofan)

Development cost (US$ )

Unit cost (US$ )

 

 

6-passenger general aviation aircraft

6 to 10 million

1 to 2 million

 

10-passenger business aircraft

20 to 40 million

5 to 8 million

 

50-passenger regional aircraft

50 to 100 million

20 to 30 million

 

150-passenger midsized aircraft

200 to 500 million

40 to 50 million

 

500+ –passenger large aircraft

2 to 10 billion?

140 to 200 million

 

Military combat aircraft (high end)

5 to 15 billion?

100+ million?

Does not include production launch cost. Typical cost at 2000 level.

2.3.3 Typical Cost Frame

A crude development cost up to certification (in year 2000 U.S. Dollars) is shown in Table 2.1. Typical unit aircraft costs by class are also given (there is variation among companies). A substantial part of the budget is committed to Phase 1.

2.3.4 Typical Time Frame

Typical time frames for the phases of different types of projects are shown in Chart 2.4. All figures are the approximate number of months. Exploratory work continues year-round to examine the viability of incorporating new technologies and to push the boundaries of company capabilities – which is implied rather than explicit in Chart 2.4.

2.4 Typical Task Breakdown in Each Phase

Typical task obligations in each phase of civil aircraft design are defined in this section. Military aircraft designs follow the same pattern but more rigorously. Military aircraft must deal with new technologies, which could still require operational proving; therefore, there is uncertainty involved in military aircraft projects.

Phase 1: Conceptual Study Phase (Feasibility Study)

Much of the work in the conceptual study phase can be streamlined through a good market study to identify a product line within a company’s capabilities. In this phase, findings of the market study are developed with candidate configurations; the technology to be adopted is firmed up and the economic viability is finalized. This is accomplished through aircraft sizing, engine matching, preliminary weight estimation, and evolution of a family of aircraft with payload and range combinations (i.e., aircraft performance) for all configurations. Planning portfolios with budgetary provisions, manpower requirements, progress milestones, potential subcontract/risk-sharing partners’ inputs, and so forth are included as the starting point of the design process. In general, at the end of this phase, management decision for a go-ahead is expected with a final configuration selected from the candidate configurations offered. Continuous interaction with potential customers (i.e., operators and subcontractors) occurs during this phase, with the objective of arriving at a family of aircraft as the most “satisfying” design with compromises rather than an

2.4 Typical Task Breakdown in Each Phase

27

 

 

 

GO-AHEAD

 

 

FIRST FLIGHT

CERTIFICATION

Exploratory work

 

Phase 1

 

 

Phase 2

 

Phase 3

 

 

Phase 4

 

 

 

 

 

 

 

 

 

 

 

 

year-round

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Civil

 

 

 

 

 

 

 

 

 

 

 

 

 

General

 

4 - 6

 

 

10 - 12

 

12 - 14

 

 

6 - 8

 

 

 

Aviation

 

 

 

 

approximately

 

24 to 30 months after go-ahead

 

 

 

 

 

 

 

 

 

 

 

 

 

Business

 

6 - 9

 

 

12 - 14

 

12 - 16

 

 

8 - 10

 

 

 

Aircraft

 

 

 

 

approximately

 

32 to 36 months after go-ahead

 

 

 

 

 

 

 

 

 

 

 

 

 

Regional

 

9 - 12

 

 

12 - 16

 

12 - 18

 

 

10 - 12

 

 

 

Aircraft

 

 

 

 

approximately

 

36 to 42 months after go-ahead

 

 

 

 

 

 

 

 

 

 

 

 

 

Midsize

 

12

 

 

12 - 16

 

20 - 24

 

 

12 - 18

 

 

 

Aircraft

 

 

 

 

approximately

 

48 months after go-ahead

 

 

 

 

 

 

 

 

 

 

 

 

 

Wide-Body

 

24

 

 

Airbus 380 took almost 5 years

 

 

 

 

Large Aircraft

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Military

 

 

 

 

 

 

 

 

 

 

 

 

 

Advanced

 

8 - 10

 

 

12 - 16

20 - 24

 

 

18 - 24

 

 

 

Jet Trainer

 

 

 

 

should complete in less than 54 months

 

 

 

 

 

 

 

 

 

 

 

 

Combat

 

If technology demonstrator time is included, then it could take a decade.

Aircraft

 

Flight-testing time would be about twice that of large civil aircraft because

 

 

 

of weapons and systems integration of many new technologies.

Military aircraft projects have large variations.

Chart 2.4. Typical project time frame

“optimum” solution. Management may request a level of detail (e.g., risk analysis) that could extend the study phase or flow into the next phase, thereby delaying the go-ahead decision to the early part of Phase 2. This is likely if the candidate aircraft configurations are short-listed instead of finalized. For those designers who have planned ahead, Phase 1 should finish early – especially if they are well versed in the product type and have other successful designs in their experience.

Phase 2: Project Definition Phase (Preliminary Design)

This phase begins after the go-ahead has been given to a project, and a “point of no-return” is reached during this phase. Project definition sometimes may overlap with the detailed design phase (i.e., Phase 3). During the advanced design phase, the project moves toward a finer definition, with a guarantee that the aircraft capabilities will meet if not exceed the specifications. Some iteration invariably takes place to fine-tune the product. Details of the technology level to be used and manufacturing planning are essential, and partnership outsourcing is initiated in this phase. Procurement cost reviews and updates also are ongoing to ensure that project viability is maintained. Many fine aircraft projects have been stalled for lack of proper

28

Methodology to Aircraft Design, Market Survey, and Airworthiness

planning and financial risk management. (Readers may study recent case histories of products such as the Swearingen SJ30 [now certified and under production] and the Fairchild–Dornier 928.) The beginning of metal cutting and parts fabrication as well as deliveries of bought-out items (e.g., engine and avionics) must be completed in Phase 2. In this phase, extensive wind-tunnel testing, CFD analysis, detailed weights estimation, detailed structural layout and FEM analysis, system definitions, production planning, and so forth are carried out.

Phase 3: Detailed Design Phase (Full-Scale Product Development)

In this phase, manufacturers push toward completion – when peak manpower is deployed for the project. Normally, projects cannot sustain delay – time is money. All aspects of detailed design and systems architecture testing are completed in this phase. (The test rig is called an “iron bird” – it simulates full-scale control and system performance.) At the end of Phase 3, the aircraft assembly should near, if not achieve, completion.

Phase 4: Final Phase (Certification)

Phase 4 must start with the rapid completion of the aircraft assembly for groundtesting of installed systems and other mandatory structural strength-testing to prepare for flight-testing. In general, two to four aircraft are needed to complete nearly 200 to 800 flight-testing sorties (depending on the type of aircraft) toward substantiation for certification of the airworthiness standard. At this stage, there should be no major setbacks because the engineers have learned and practiced aircraft design well with minimal errors.

Each project has a characteristic timeline; – this book uses a 4-year project time. Remember, however, that some projects have taken more or less time. Section 2.4.2 is a detailed breakdown of a small aircraft project for a small or medium company. The author recommends that similar detailed milestone charts be drawn for coursework projects to give an idea of the manpower requirements.

2.4.1 Functional Tasks during the Conceptual Study (Phase 1: Civil Aircraft)

Because this book is concerned only with Phase 1, it is important to delineate functional task obligations assigned to individual designers – also known as top-level definition. Market specifications should first be delineated to develop task content, as shown in Chart 2.5 for the mission profile. Payload determines the fuselage size and shape and leads into undercarriage design, depending on wing and engine positioning. Wing design largely determines the range, operational envelope, and fieldperformance objectives. Considering all requirements together, the aircraft configuration evolves: There can be more than one candidate configuration (e.g., high or low wing, nacelle location, and empennage arrangement).

Aircraft configuration starts with the fuselage layout followed by the steps worked out in this book. The military aircraft design approach is not significantly different except that the payload is armament, which is generally underslung or kept inside the fuselage bay.