- •1.1 What this chapter contains
- •1.2 What is Pinch Technology?
- •1.3 From Flowsheet to Pinch Data
- •1.3.1 Data Extraction Flowsheet
- •Thermal Data
- •1.4 Energy Targets
- •1.4.1 Construction of Composite Curves
- •1.4.2 Determining the Energy Targets
- •1.4.4 The Pinch Principle
- •1.5 Targeting for Multiple Utilities
- •1.5.1 The Grand Composite Curve
- •1.5.2 Multiple Utility Targeting with the Grand Composite Curve
- •1.6 Exergy Analysis
- •1.6.1 Carnot factor calculations
- •1.6.2 Constructing an exergy balance
- •1.7 Capital - Energy Trade-offs
- •1.7.1 New Designs
- •Setting Area Targets
- •Setting Minimum Number of Units Target
- •Determining the Capital Cost Target
- •1.7.2 Retrofit
- •Retrofit Targeting based on Capital-energy trade-off
- •Maintaining Area Efficiency
- •Payback
- •Retrofit targeting based on DTmin - Energy curves
- •DTmin Calculation in PinchExpress and PROCESS
- •Retrofit targeting based on experience DTmin values
- •Typical DTmin values for various types of processes
- •Typical DTmin values used for matching utility levels against process streams
- •Typical DTmin values used in retrofit targeting of various refinery processes
- •1.8 Process Modifications
- •1.8.1 The plus-minus principle for process modifications
- •1.8.2 Distillation Columns
- •Stand-alone column modifications
- •Column integration
- •1.9 Placement of Heat Engines and Heat Pumps
- •1.9.1 Appropriate integration of heat engines
- •Identifying opportunities for heat engine placement
- •1.9.2 Appropriate integration of heat pumps
- •Identifying opportunities for heat pump placement
- •1.10.1 The Difference Between Streams and Branches
- •1.10.2 The Grid Diagram for heat exchanger network representation
- •1.10.4 The New Design Method
- •Design Above The Pinch
- •Design Below The Pinch
- •Completed Minimum Energy Requirement Design
- •Stream splitting in network design
- •Network evolution: Heat load loops and heat load paths
- •Network design for multiple utilities
- •Summary: New heat exchanger network design
- •1.10.5 Heat Exchanger Network Design for Retrofits
- •Pinch Design Method with maximum re-use of existing exchangers
- •Correcting Cross-Pinch Exchangers
- •Use cross-pinch analysis to find a promising project in the current network
- •Use the Grid Diagram to design the project
- •Other steps
- •Analysis of Exchanger Paths
- •Retrofit example
- •1.11.1 Do not carry over features of the existing solution
- •1.11.2 Do not mix streams at different temperatures
- •1.11.3 Extract at effective temperatures
- •1.11.4 Extract streams on the safe side
- •1.11.5 Do not extract true utility streams
- •1.11.6 Identify soft data
- •1.12.1 Total site data extraction
- •Constructing Total Site Profiles
- •Adding steam users not accounted in process stream data
- •1.12.2 Total site analysis
- •Setting total site targets
- •Case study - Total site analysis
- •1.12.3 Selection of options: Total Site Road Map
- •Summary: Total Site Improvement
- •1.15 Index
Chapter 1 |
Pinch Technology |
11 |
The targeting involves setting appropriate loads for the various utility levels by maximising cheaper utility loads and minimising the loads on expensive utilities.
1.6 Exergy Analysis
The use of pinch analysis techniques has already resulted in a significant impact on savings in utility consumption. However, traditional techniques tend to be mainly effective in situations where utility costs are dominated by heat loads. In contrast, in the case of utility systems which involve power as well as heat they cannot directly account for the power component. Such problems can now be addressed by the combined pinch and exergy approach, which was originally developed for refrigeration shaftwork targeting. Most importantly, the method can also be extended to above ambient applications involving heat and power. Exergy analysis techniques are therefore applicable to the design and optimisation of a wide range of overall site utility systems.
Exergy Analysis provides the information needed to consider shaftwork targets at the same time as considering the heating or cooling requirements of a chemical plant or site. The information is used as follows:
1.For a sub-ambient plant, the engineer can determine the minimum refrigeration shaftwork that will be required in the target network. This can be used for costing and for site-wide combined heat and power studies.
2.For an above-ambient plant, the engineer can determine the maximum potential for the plant to produce shaftwork. This is most relevant when there is a nearby sub-ambient plant to which this work can be exported. In some cases, however, the work may also be exported to an electrical grid. If none of the potential is recovered then the target represents the lost work in the process.
1.6.1 Carnot factor calculations
For the calculation of exergy targets the point targeting curves are redrawn using Carnot Factor, instead of temperature, as the Y axis co-ordinate. The Carnot factor is defined as follows:
nc = (1 - TTo )
where:
To = ambient temperature
T = stream temperature
The exergy value of a constant temperature stream can then be calculated from: Exstream = H*(1 - TTo )
where:
Pinch Technology Introduction