![](/user_photo/_userpic.png)
- •5.3 Test Instructions
- •Table of Allowable Rapid Fluctuations of Certain Key Measurements.
- •5.5.6 Data Verification
- •5.6 Results
- •5.7 Analysis
- •5.7.1 Method of Trending Results
- •5.8 Report
- •HP / IP Turbine Efficiency Test
- •Typical Control Room Data Sheet
- •Point ID
- •Condenser
- •Annexure - I
- •CONDENSER DESIGN DATA
- •Annexure - II
- •TEST READINGS
- •Annexure - III
- •TYPICAL CONTROL ROOM READINGS
- •UNITS
- •kcal/hr
- •3.0 Working And Test Set Up
- •TEST ENGINEER (TE):-----------------------------------------
- •ENGINEERING REVIEW
- •PERSONNEL REQUIRED
- •TEST CREW ORIENTATION
- •REFERENCE DRAWINGS
- •LEAK DETECTOR OPERATION
- •TEST LOG
- •ACCESSIBILITY
- •CONTROL ROOM / UNIT DATA
- •LIST OF INSTRUMENTS & ACCESSORIES REQUIRED FOR AIR-IN-LEAK TEST
- •L. P. Turbine
- •*Total time from leak sensing by instrument to retrieval to zero (0)
- •Unit
- •LOW FEED WATER TEMPERATURE
- •EXCESSIVE MAKEUP
- •HIGH WATER LEVEL
- •EXCESSIVE NUMBER OF TUBES PLUGGED
- •HIGH DRAIN COOLER APPROACH TEMPERATURE (DCA)
- •DRAIN COOLER INLET NOT SUBMERGED
- •IMPROPER SETTING
- •EXCESSIVE TUBE BUNDLE PRESSURE DROP
- •HP Heater Test Data
- •Control Room Readings
- •FAULT TREE
- •LP Heater Test Data
- •Control Room Readings
- •FAULT TREE
- •LOW FEED WATER TEMPERATURE
- •EXCESSIVE MAKEUP
- •WORN VENT
- •HIGH WATER LEVEL
- •TUBE LEAKES
- •HEADER PARTITION LEAKS
- •EXCESSIVE NUMBER OF TUBES PLUGGED
- •HIGH DRAIN COOLER APPROACH TEMPERATURE (DCA)
- •DRAIN COOLER INLET NOT SUBMERGED
- •IMPROPER SETTING
- •EXCESSIVE TUBE BUNDLE PRESSURE DROP
- •EXCESSIVE NUMBER OF TUBES PLUGGED
- •Unit
- •BFP Test Data
- •Typical Control Room Readings
- •Boiler Feed Pump A / B / C
- •Typical DAS Readings
- •Description
- •CONTENTS
- •1.0 Introduction
- •3.1 Process Description
- •4 References
- •4.1 ASME Performance Test Code 4.2 – 1969, Coal Pulverizers
- •5 Prerequisites
- •(A clean air test is performed with the primary air to the mill at full load normal conditions with the mill out of service (normal primary airflow, no fuel flow)).
- •Avg. Velocity
- •6.4 Isokinetic Coal Sampling
- •4.5.2 Unburned in Flyash at Economizer Outlet
- •Summary
- •Dry Gas Loss
- •Gas Temp Leaving AH - Corr. to Design Ambient
- •OBJECTIVE : Determine the amount of Power being consumed by the primary plant equipment.
- •TEST ENGINEER (TE):
- •REFERENCE: ASME PTC 19.6-1955 and TVA Proc. No. TS/PERF/RTST/FOS/16.0
- •BILL OF MATERIALS
- •BILL OF MATERIALS
- •Note: Quantities to be decided as per the requirement
- •2.4 PORTABLE DATA ACQUISITION SYSTEM
- •BILL OF MATERIAL
- •Acquisition
- •EQUIPMENT: Thermocouple wire for flue gas temperature measurement
- •2.9 HIGH VELOCITY THERMOCOUPLE (HVT) PROBE
- •2.11 HIGH VOLUME FLYASH SAMPLER
|
Centre For Power Efficiency And Environmental |
Procedure Number |
|
NTPC |
Protection, NOIDA |
CENPEEP/EFF/TP/304 |
|
|
|
|
|
|
TITLE |
Rev. 1/EMS |
|
CENPEEP |
LP Heater Performance Test |
Issue Date: 20/04/2000 |
|
|
Page: 14 |
Of 14 |
WORN VENT
ALTERED SET POINT
VENT MALFUNCTION
HIGH WATER LEVEL
TUBE LEAKES
IMPROPER SETTING
HEADER PARTITION LEAKS
NONCONDENSIBLE GASES IN SHELL SIDE
EXCESSIVE TUBE BUNDLE PRESSURE DROP
EXCESSIVE NUMBER OF TUBES PLUGGED
TUBES FOULED INTERNALLY
HIGH DRAIN COOLER APPROACH TEMPERATURE (DCA)
DRAIN COOLER INLET NOT SUBMERGED
LOW WATER LEVEL
IMPROPER SETTING
EXCESSIVE FW HEATER DRAIN BYPASS
IMPROPER SETTING
BYPASS VALVE LEFT OPEN
BYPASS VALVE MALFUNCTION
BYPASS VALVE LEAKS
EXCESSIVE TUBE BUNDLE PRESSURE DROP
EXCESSIVE NUMBER OF TUBES PLUGGED
TUBES FOULED INTERNALLY
FEEDWATER HEATER BYPASSED
FW HEATER BYPASS VALVE LEAKS
![](/html/20012/144/html__weqqT27G8.JYSI/htmlconvd-Kow0Zz92x1.jpg)
(For Internal circulation only)
1.6 ROUTINE BOILER FEED PUMP PERFORMANCE TEST
Procedure No.: CENPEEP/EFF/TP/305
Rev No. |
: 01/EMS |
|
Issue Date |
: April 20, |
2000 |
CENPEEP |
Centre for Power Efficiency & Environmental Protection |
|
National Thermal Power Corporation Ltd. |
A-8A, Sector-24, NOIDA, (U.P.) 201301 India Tel: 011-8-4525197, Fax: 011-8-4538874 email: cenpeep@ntpcrd.ernet.in
|
Centre For Power Efficiency And Environmental |
Procedure Number |
|
NTPC |
Protection, NOIDA |
CENPEEP/EFF/TP/305 |
|
|
|
|
|
|
TITLE |
Rev. 1 /EMS |
|
CENPEEP |
Routine Boiler Feed Pump Performance Test |
Issue Date: 20/04/2000 |
|
|
PAGE: 1 |
OF 14 |
CONTENTS
1.0Introduction
2.0Objective and Scope
3.0Reference
4.0Design Data
5.0Test Instrumentation
6.0Instrument Installation
7.0Test Instructions
8.0Test Frequency and Duration
9.0Personnel Needed
10.0Test Setup
11.0Duration of Test Run and Frequency of Readings
12.0Definitions
13.0Calculation
14.0Report
|
Centre For Power Efficiency And Environmental |
Procedure Number |
|
NTPC |
Protection, NOIDA |
CENPEEP/EFF/TP/305 |
|
|
|
|
|
|
TITLE |
Rev. 1 /EMS |
|
CENPEEP |
Routine Boiler Feed Pump Performance Test |
Issue Date: 20/04/2000 |
|
|
PAGE: 2 |
OF 14 |
1.0 Introduction
A boiler feed pump is a component designed to feed water to the boiler at the rated conditions of pressure, temperature and flow. By plotting efficiency, capacity, total head, balance drum leak off and pump input power on control charts, showing historical and expected data, the current condition of the pump can be assessed. The maintenance requirements can be planned based on the gaps, adverse trends and sudden changes.
2.0 Objective and Scope
The scope is limited to boiler feed pumps.
The objectives of the boiler feed pump test is to establish rules for conducting tests on pumps to determine under specified conditions one or more of the following parameters:
2.1Total Head Produced by the Pump.
2.2The Capacity or Rate of Flow.
2.3Power Input to the Pump.
2.4Train Efficiency.
2.5Balancing Drum Leakoff Flow
3.0Reference
Based on ASME performance test code PTC 8.2 ,1990 on Centrifugal Pumps.
4.0Design Data
BFP design data as per Anneuxre – I
5.0Test Instrumentation
The parameters required to be monitored to conduct the boiler feed pump performance test consists of temperature, pressure and differential pressure.
|
Centre For Power Efficiency And Environmental |
Procedure Number |
|
NTPC |
Protection, NOIDA |
CENPEEP/EFF/TP/305 |
|
|
|
|
|
|
TITLE |
Rev. 1 /EMS |
|
CENPEEP |
Routine Boiler Feed Pump Performance Test |
Issue Date: 20/04/2000 |
|
|
PAGE: 3 |
OF 14 |
5.1Test Instruments and Measurement Required
The No. of instruments required per BFP is as follows:
Measurement |
Temperature |
Pressure |
Remarks |
Booster Pump Suction |
1 |
1 |
|
BFP Suction |
1 |
1 |
|
BFP Discharge |
1 |
1 |
|
Balancing Drum |
|
|
|
Leak Off (BDLO) |
- |
1 |
|
dp BDLO |
- |
1 |
|
dp BFP flow orifice |
- |
1 |
|
Ambient |
1 |
1 |
|
In addition to the above power measurement is to be carried out with high accuracy power meter, and motor and pump speed with high accuracy tachometer or stroboscope.
5.2Instrument Accuracy Requirement
The instrumentation selected for the test shall be capable of achieving the following measurement accuracies:
Instrument |
Unit |
Range |
Accuracy |
Remarks |
RTDs |
o C |
0-600 |
Class A |
12 point calibration |
|
|
(At 600 o C +/- 1.35 °C) |
curve to be used |
|
Pressure |
kg/cm2 0-60 |
+ / - 0.075% |
12 point calibration |
|
Transmitters |
|
|
|
curve to be used |
Pressure |
kg/cm2 0-200 |
+ / - 0.075% |
12 point calibration |
|
Transmitters |
|
|
|
curve to be used |
Diff. Pr. |
kg/cm2 0 – 1.5 |
+ / - 0.075% |
12 point calibration |
|
Transmitter |
|
|
|
curve to be used |
|
Centre For Power Efficiency And Environmental |
Procedure Number |
|
NTPC |
Protection, NOIDA |
CENPEEP/EFF/TP/305 |
|
|
|
|
|
|
TITLE |
Rev. 1 /EMS |
|
CENPEEP |
Routine Boiler Feed Pump Performance Test |
Issue Date: 20/04/2000 |
|
|
PAGE: 4 |
OF 14 |
5.3Instrument Calibration
The instruments used for the test will be calibrated once in two years. The calibration records of these instruments will be maintained as permanent records and reference to current calibration will be made in the report.
5.4The performance test data from test instruments will be recorded using sample format as given in Annexure - II.
5.5Measurement required from station instruments are given in Annexure - III This format will be used for collecting station measurement during the performance test.
5.6Data required from DAS are given in Annexure - IV. These data will be used for comparison of DAS data with test instrument data.
6.0Instrument Installation
6.1Pressure Measurement
Pressure instruments which operate above atmospheric pressure require all pressure sensing lines to be blown down prior to installing the instrument, and the instrument vented after it is pressurized, if possible. The pressure sensing lines should be plumbed with a continuous downward slope from the pressure tap to the sensor to prevent pockets of steam or air. The appropriate waterleg measurements for each pressure instrument should be made and entered as part of the data for each instrument.
6.2Temperature Measurement
All thermowells should be cleaned and the bottoms polished prior to installing the temperature sensors. All temperature sensors should be installed in a manner to ensure they make good contact with the bottom of the well and secured to ensure they are held firmly against the bottom during use. All temperature sensors whose shafts extend past the thermowells should be insulated.
6.3Speed Measurement
The speed shall be measured by any reliable revolution counter, accurately calibrated tachometer or a portable stroboscope.
|
Centre For Power Efficiency And Environmental |
Procedure Number |
|
NTPC |
Protection, NOIDA |
CENPEEP/EFF/TP/305 |
|
|
|
|
|
|
TITLE |
Rev. 1 /EMS |
|
CENPEEP |
Routine Boiler Feed Pump Performance Test |
Issue Date: 20/04/2000 |
|
|
PAGE: 5 |
OF 14 |
6.4Data Acquisition System (DAS) and Processor and Analyzer System
It is preferable to use a portable DAS and processor and analyzer for performance testing. This will ease the testing process and provide on line monitoring of test data and results. It will also help in tracking the process stability and thereby reduce the uncertainty level of results.
6.4.1Portable Data Collection Unit
One/two portable units may be used to cover the inputs at the test location. Each DAS unit should have a minimum of 16 universal inputs as given below:
a)PT 100, 4 Wire RTD
b)4-20 mA, 2 Wire Transmitter output with a built-in facility to power the Transmitter.
6.4.2Portable Processor and Analyzer Unit
•IBM compatible portable machine with a Pentium processor.
•Graphic display compatibility.
•32 megabytes of RAM
•Windows 95 with Microsoft Excel version 7.0
•IDAAS and DALITE Software as analyzer.
6.4.3Installation
The following precautions should be taken during installation of the data collection unit with the portable processor.
•Identify the location of power supply
•List out the inputs with respect to Channel No.
•Review the status of fuses.
•Tag input leads at both ends by masking tape, etc.
•Connect the inputs as per channel listing. Cascade the output from one data collection unit to other, connect network cable from data collection to the interface unit/portable processor unit.
•The network cable should be laid away from movement areas, without obstructing the plant equipment and 2-3 meters above the floor level.
•Ensure the tightness of all connections.
•Charge the power supply and check for the channel’s functionality.
|
Centre For Power Efficiency And Environmental |
Procedure Number |
|
NTPC |
Protection, NOIDA |
CENPEEP/EFF/TP/305 |
|
|
|
|
|
|
TITLE |
Rev. 1 /EMS |
|
CENPEEP |
Routine Boiler Feed Pump Performance Test |
Issue Date: 20/04/2000 |
|
|
PAGE: 6 |
OF 14 |
•Verify the system is networking.
•Carry out a test run to scan and ensure proper system functioning.
7.0Test Instructions
7.1Unit should be in operation at normal full load in steady state condition.
7.2Ensure that the recirculation valve is closed.
7.3Feed water flow to be maintained constant at the required level for the duration of the test run. Variations in feedwater flow shall not exceed
+/- 2%.
7.4First test run is conducted at normal feed flow. Subsequently other test runs are conducted by varying the feed flow at levels above and below normal flow.
7.6Speed measurement is carried out during the duration of the test run using tachometer or portable stroboscope.
8.0Test Frequency and Duration
8.1Routine testing every 12 months
8.2Special requests for various reasons.
8.3Each run shall continue for a period sufficiently long to ensure accurate and consistent results. With the online computational software described in Section 6.4 each run duration should be of 20 minutes after attaining steady state condition.
9.0 Personnel Needed
The test requires two persons, for test set-up and for taking data at site and at control room.
|
Centre For Power Efficiency And Environmental |
Procedure Number |
|
NTPC |
Protection, NOIDA |
CENPEEP/EFF/TP/305 |
|
|
|
|
|
|
TITLE |
Rev. 1 /EMS |
|
CENPEEP |
Routine Boiler Feed Pump Performance Test |
Issue Date: 20/04/2000 |
|
|
PAGE: 7 |
OF 14 |
10.0Test Setup
10.1First notify the Shift Incharge and Unit Controller about the program for conducting the test and inform about test equipment/instrument being installed.
10.2Install the Pressure transmitters and RTDs (as per Section 6.1 & 6.2) at the locations described as per Section 5.1
10.3The output of transmitters and RTDs to be connected to data collection unit and this in turn to be connected to data processing unit as indicated in Section No. 6.4
11.0Duration of Test Run and Frequency of Readings
11.1 CASE I - Testing by Using DAS and Processor & Analyzer System
11.1.1Test duration: Each test run should be conducted for a period of 15-20 minutes, after achieving minimum uncertainty.
11.1.2Frequency of test data: After achieving the point of minimum uncertainty as shown by the data processor, the test may be commenced and the readings taken at a frequency as given below:
•test instrument readings by data processor as per normal scan rate.
•manual readings from control room at an interval of 5 minutes.
11.2CASE II - Testing by manual data collection
11.2.1Test Duration: Each test run should be conducted for a period of 30-45 minutes after achieving stable parameters.
11.2.2Frequency of Test Data: All readings should be taken at 5 minute intervals.
11.3Data Verification
During the course of testing compare the historical performance data showing expected value of the critical measurements as appropriate. This will help in assessing the error, if any, in data being collected.
|
Centre For Power Efficiency And Environmental |
Procedure Number |
|
NTPC |
Protection, NOIDA |
CENPEEP/EFF/TP/305 |
|
|
|
|
|
|
TITLE |
Rev. 1 /EMS |
|
CENPEEP |
Routine Boiler Feed Pump Performance Test |
Issue Date: 20/04/2000 |
|
|
PAGE: 8 |
OF 14 |
12.0Definitions
Refer to Annexure - V
13.0Calculation
Refer to Annexure - VI
14.0Report
The report should include a narrative describing any unusual findings as well as the following:
14.1Executive Summary
14.2Objective
14.3Scope
14.4Background
14.5Test Methodology
14.6Results
14.7Discussions
14.8Conclusions
14.9Recommendations
14.10Acknowledgment
14.11References
14.12Complete set of Appendices
14.12.1Analysis and Results
14.12.2Test Data