Добавил:
Upload Опубликованный материал нарушает ваши авторские права? Сообщите нам.
Вуз: Предмет: Файл:

Construction Economics and Management

.pdf
Скачиваний:
188
Добавлен:
30.03.2016
Размер:
1.9 Mб
Скачать

UNIT 4

CONTRACTING

4.1Awarding Contracts

1.List the kinds of stakeholders and specialists involved in the execution of a construction project. What are their functions and responsibilities?

E.g.: A project manager organizes the project execution process.

2. Match the nouns with their Russian equivalents.

1) contractor

a) товарищество

2) partnership

b) заказчик

3) client/customer

c) государственное учреждение

4) owner

d) субподрядчик

5) individual

e) физическое лицо

6) subcontractor

f) владелец

7) government body

g) подрядчик

3. Match the words to build up word collocations.

1) bid

a) contractor

2) project

b) supervision

3) onsite

c) specifications

4) general

d) cost

5) overall

e) proposal

4. Study the key participants of a project and answer the questions.

There are various players in the construction process that play distinct roles. The key participants are the owner (acting as a client, customer) and the contractor.

 

 

OWNER

 

 

CONTRACTOR

 

 

 

 

 

The owner of a construction project may

Contractors perform

the construction

be

an

individual,

corporation,

work in accordance with the plans and

partnership, or government body. The

specifications provided by the owner.

owner evaluates whether a project is

 

 

 

 

feasible. The owner then engages an

A general contractor takes full

architect or engineer to design the plans

responsibility for the completion of the

and specifications of the project.

project. The general contractor will

Normally, the owner secures the

normally subcontract out a substantial

necessary financing for the project for

part of the work, while maintaining

both the construction period and

overall

control

through

project

permanent financing upon completion.

managers and onsite supervision.

 

 

 

 

 

 

 

 

 

(Adapted from: http://www.probuildersslo.com/conintro/42-constructionparticipants)

 

 

 

 

 

 

 

31

1)What are the two main stakeholders in a construction project?

2)Who or what can be the owner of a construction project?

3)What is the owner’s role in maintaining a project?

4)What is the general responsibility of the contractor?

5)Does the general contractor perform all the works on its own? What is its function in project implementation process?

5.If you were the owner of a project, how would you select the general contractor? What would you consider? Put these issues in the order of importance (1 to 5).

timing (time needed for the completion of the project) experience of the contractor

environmental impact total price of the project

amount and qualifications of subcontractors

6. Normally, contracts are awarded on the basis of bidding, or tenders. Read the abstract about construction bidding and complete the sentences.

The construction bid process is the process in which a general contractor is selected to work on a construction project. In some cases, the only thing that matters in the construction bid process is presenting the lowest price to the owner; in other cases, the contractor's qualifications are as important, if not more important, than having the lowest currency amount.

A construction bid proposal (tender) is the basis on which many construction companies are hired to serve as the general contractor on a project. Without a tender there would be no way to establish the overall cost of a project.

(Adapted from: http://construction.about.com/od/Bidding-Process/a/How-To-Bid-A-Commercial-Construction-Projects.htm)

1)The purpose of bidding is to ________________.

2)The two main things that determine the selection of a contractor are

______________.

3)A tender is a construction bid proposal which is aimed to ______________.

7.True or false?

1)There should be several key participants in any construction project, like the owner, the client, the contractor, the customer, and the project manager.

2)The owner of a construction project can be both an individual and a company.

3)The owner usually develops project specifications on its own.

4)The project financing and cost control should be guaranteed by the owner.

32

5)The contractor uses the specifications provided by the owner as a basis of construction works.

6)A general contractor can engage other specialists or companies to do various parts of construction works.

7)The main function of the general contractor is onsite supervision.

8)In construction bidding process the contractor’s qualifications are much less important than the price.

8.Find the synonyms of these words in the text.

Total – _____________

To estimate – _____________

To hire – _____________

Experience – _____________

Player – _____________

Client – _____________

9. Complete these sentences with the correct form of the verbs in the box.

award engage evaluate propose secure serve

1)The feasibility of the project is usually ___________ by the owner.

2)The contract was ____________ to the company that offered the lowest price.

3)Our company ___________ as the general contractor of this project.

4)The task of the owner is to ___________ financing of the project.

5)Several architects were ___________ to design the project specifications.

6)Our company ____________ the most qualified bid at the tender.

10.Imagine that you are the owner of a construction project. You wish to construct an underground car park. Look at the proposals submitted by three potential contractors. Which would you select and why?

 

Civil Engineering,

Underground

Car Park Engineering

 

Ltd

Constructions JSC

PLC

 

 

 

 

Price

$1.9 mln

$3.4 mln

$2.2 mln

 

 

 

 

Timing

14 months

9 months

10 months

 

 

 

 

Experience

5 years in residential

30 years in

10 years

 

construction:

infrastructure

Specializes in surface

 

individual houses,

construction: roads,

car park arrangement;

 

apartment blocks,

tunnels, underground

no experience in

 

townhouses

facilities

underground works

33

4.2Types of Contracts in Construction

1.What is the role of the contract in the construction process? What issues should be included into the contract?

2.Match the nouns on the left and their definitions on the right.

1) fixed fee

g)

one payment

2) incentive

h)

a stimulus; a motivation

3) cost overrun

i)

an agreed payment that does not change

4) solution

j)

higher costs than originally forecast

5) lump sum

k)

a means of dealing with a problem

3. Study the major types of construction contracts and match them with the descriptions below.

 

design and construct

fixed amount of money

 

 

cost of materials and labour plus extra payment

 

 

 

 

 

 

Lump Sum

 

Cost Plus

Turnkey

 

 

 

 

In this contract the client

The client pays all the

One person or company is

agrees to pay a fixed

costs of the project, plus

responsible for

all the

amount of money for the

extra payment so that the

work. Normally

a client

finished

project.

The

contractor makes a profit.

has to work with a

client knows exactly how

In a cost plus fixed fee

designer and a contractor.

much the

project

will

contract the client covers

In a turnkey solution, the

cost. But if there are any

any cost overruns, but the

client only has to deal

problems,

the contractor

contractor

only gets a

with one person who is

has to pay the extra costs.

fixed fee, so there is an

responsible for the whole

The contractor is

taking

incentive to finish the job

project and at the end

the risk.

 

 

quickly.

 

gives the key to the client.

1) ___________________

2) ___________________

3) ___________________

 

 

 

 

 

 

 

(Adapted from: E. Frendo. English for Construction. Course Book 2. Pearson Education Limited, 2012)

4. Compare the three types of contracts from the viewpoint of a client and a contractor. What are the advantages and disadvantages?

34

5. Read the text and study the peculiarities of an EPC/Turnkey Contract.

EPC stands for Engineering, Procurement, Construction and is a prominent form of contracting agreement in the construction industry. The engineering and construction contractor will carry out the detailed engineering design of the project, procure all the equipment and materials, and then construct to deliver a functioning facility to their clients. Companies that implement EPC Projects are commonly referred to as EPC Contractors.

The EPC phase of the project is also known as the Execution phase which normally follows what is known as a FEED or Front End Engineering Design phase. The FEED is a preliminary engineering design used as the basis for the EPC phase.

Normally the EPC Contractor has to execute the project within an agreed time and budget, commonly known as a Lump Sum Turn Key (LSTK) Contract. An EPC LSTK Contract places the risk for schedule and budget on the EPC Contractor.

The Project Owner will normally have a presence in the EPC Contractors offices during the execution of the EPC Contract. The Owner places what can be termed a Project Management Team (PMT) to overlook the EPC Contractor. The client PMT may require specialist help and engage Project Management Consultants (PMC’s) to assist. The PMT/PMC will ensure the EPC Contractor is carrying out the works in accordance with the agreed scope of works and in accordance with the Contract. It is quite common for the Engineering and Construction Contractor which worked on the FEED to be offered a Project Management Consultancy Contract.

(Adapted from: http://www.epcengineer.com/definition/132/epc-engineering-procurement-construction)

6. Decipher the following abbreviations and explain their meanings.

EPC ________________________________________________

FEED ________________________________________________

LSTK ________________________________________________

PMT ________________________________________________

PMC ________________________________________________

7.Complete the sentences.

1)The task of an EPC contractor is to ___________________.

2)The EPC phase of the project usually follows __________________.

3)Under an EPC LSTK the contractor takes risks for_________________.

4)The PMT has to ________________.

35

8.Choose the correct alternative.

1)According to an EPC contract the materials and equipment are usually

 

delivered by ________________.

 

 

 

 

a) the client

b) the owner

c) the contractor

 

2)

The EPC phase of the project usually includes _______________.

 

a) preliminary design

b) detailed design

c) feasibility study

3)

Under a Lump Sum Turn Key contract the risk for time and money is

 

usually taken by _______________.

 

 

 

 

a) the contractor

b) the project management team

c) the project owner

4)

The task of the Project Management Consultant is to ______________.

 

a) develop a FEED

b) execute the project

c) assist the client PMT

9. Match the verbs on the left with the nouns on the right to make word collocations.

1) take

a) the job

2) execute

b) costs

3) finish

c) a profit

4) pay

d) a consultant

5) make

e) the risk

6) engage

f) the project

10.Complete the sentences using the word collocations from exercise 9. Put the verbs in the correct form.

1)One of the main peculiarities of a lump sum contract is the fact that it is the contractor who __________________ for the budget and schedule.

2)Under a cost plus contract the client has to ______________ for the project.

3)The client can ________________ to assist the Project Management Team.

4)There is an incentive for a cost plus contractor to _____________ as soon as possible.

5)The PMT has to ensure that the contractor is _______________ within the budget and time limits.

6)The client usually provides some extra payment for the contractor to

______________.

11.Imagine that you are going to realize some construction project. How many and what kind of contracts will you have to award in order to have your project executed? Which stages of the project life cycle will be covered with these contracts? Consult Figure 2 on page 10.

36

UNIT 5

PRESENTATIONS

5.1 Presenting a Company

1.Discuss the questions.

1)How often do you give presentations in your job/studies?

2)Who do you normally present to?

3)Have you ever given a presentation in English? Was it a success?

4)How do you feel about presenting in a foreign language?

5)In your opinion, what kind of presentation is good/bad?

6)What is a slideshow? In what way is it related to the presentation?

2.Read the text and make a list of tips for a good presentation.

When you make a presentation, the first stage is to plan it. You should start by thinking about your audience – who they are, what they know about the subject and what they expect from you. Will they be interested, enthusiastic, cooperative or perhaps critical?

If possible, try to visit the room where you are going to give the talk. Check the equipment and make sure you can be heard in the back of the room if you don’t want to use a microphone.

You are now ready to prepare what you are going to say. Stage one is the opening. A good opening is essential as you will be nervous and you need to grab the attention of the audience. You start by introducing yourself and then you use a technique to get the audience’s interest. You can do this in various ways. You can: ask a question; use a famous quotation; use a striking visual image; appeal directly to the audience’s interests or needs.

Once you have the audience’s attention, you should tell them the structure of your presentation. You give them the map of the talk, so they know what you will cover.

After the opening and a brief introduction of your subject, you come to the main body of your presentation. Then you have a conclusion during which you summarize the key points, and give your final opinion and recommendations. After that it’s the question and answer session.

(Adapted from: Cotton, D., Falvey, D., Kent, S. Market Leader. Intermediate Business. English Course Book. Pearson ELT, 2009)

37

3. Look at the first slide of the presentation of Yapi Merkezi Holding – one of the well-known construction companies in Turkey and all over the world.

How does it grab the audience’s attention? Do you think it is a success?

4. Study the useful phrases to start a presentation.

Introducing yourself

On behalf of myself and Focus Engineering, I’d like to welcome you. May name’s Jennifer Parker.

Good morning, everyone. I’m

Frank Scott. Good to see you all.

Introducing the topic

I’m going to tell you about our company, its background and experience.

This morning, I’d like to outline the project concept we’ve developed for you.

Structuring the presentation

I’ve divided my talk into three parts. Firstly, I’ll describe the general profile of the company.

Secondly, I’ll present the engineering activities we’ve been engaged in. Finally, I’ll talk you through our social responsibility programmes.

Inviting questions

If you have any questions, please do not hesitate to interrupt me.

I’ll be glad to answer any questions at the end of my talk.

5. Imagine that you are given a task to present the construction company you work for. Think of an opening for your presentation. What would you say in the beginning?

38

6. Plan your presentation of the construction company. What should you include in it? Consult the following table and continue the list if necessary.

Piece of information

Useful expressions

 

 

When the company was

The company started / began / was founded /

founded

was established / was setup in…

How the company developed

The company opened new branches / factories /

 

plants in…

 

The company was engaged in / completed the

 

project.

 

The company won / was awarded a contract

 

for…

What the company does

The company designs / produces / makes /

 

manufactures / constructs / offers / organizes /

 

invests in

Where the company is located

The company has offices / subsidiaries /

 

warehouses / project management centers in…

How many people work for the

The company employs

company

 

What are the company’s profits

The annual net profit / annual turnover of the

and turnover

company is…

What are the company’s targets

The company aims at / strives to / works for /

 

tries to

What is the company’s

The company has designed / has constructed /

experience

has produced / has provided

What is the company’s

The company has good financial relations with

financial background

… investment banks

What are the strengths of the

The company has an excellent reputation

company

The company is proud of its highly-skilled

 

professionals

 

We keep up with trends

 

We have a long-term experience in dealing with

 

unfavourable geology

How the company manages the

The company has an ISO certificate in

quality of works

construction…

What is the company’s social

We invest in education / science / culture /

responsibility

health service / environmental protection

7. Look at some slides presenting Yapi Merkezi Holding. What information about the company can you get from these slides? Tell about Yapi Merkezi using the expressions from exercise 6.

39

40