Добавил:
Опубликованный материал нарушает ваши авторские права? Сообщите нам.
Вуз: Предмет: Файл:

2376

.pdf
Скачиваний:
4
Добавлен:
07.01.2021
Размер:
6.68 Mб
Скачать

Fig. 18

The first components to be built of synthetic materials will be long stabilizing cables. For these cables, the ideal axial stiffness, which is a function of sag, is extremely important [6]. For long spans, lighter carbon fiber cables can achieve the same stiffness with a much smaller cross section than heavier steel cables.

As spans increase, it will become necessary to use synthetic materials for the main suspension cables. Already for 3000 m spans, the weight per unit length of suspension cables is roughly equal to that of the girder it supports. The unit weight of the cables should not increase as spans are increased even further. This can be avoided most simply through the use of a hybrid cable system, in which cables are composed of synthetics and steel acting together. Although the coefficients of thermal expansion are different for these two materials, the stresses redistributed from one material to the other

due to change in temperature are small compared to stresses due to load.

The last step in the development of bridges of extremely long spans may be not only the entire cable system of synthetic materials, but also the girder. The first tests of girders made of synthetics are already under way [7]. The proposed basic structural concept for the design and construction of the towers would remain valid in such a case.

Concluding Remarks

Simple extrapolations of rather conventional concepts usually do not lead to great progress in technological development. This is true as well for extremely long spans in bridge structures. Because today lightweight high strength materials are not yet inexpensive and cannot yet be produced in sufficient quantity, economical and practical designs for extremely long spans require unconventional structural sys-

163

tems. The proposed structural concept,

[3] CASTELLANI, A. The Project for

with its relatively simple construction

the Bridge over the Messina Strait,

technique, is certainly suited for this

ibid., pp. 517-527.

design problem. It is suitable, not only

[4] WALTHER, R., AMSLER, D. Hy-

for great spans but also for narrow

brid Suspension Systems for Very Long

bridges with shorter spans and espe-

Span Bridges: Aerodynamic Analysis

cially also for long span pipeline

and Cost Estimates, ibid., pp. 529-536.

bridges.

[5] GIMSING, N.J. Suspended Bridges

References

with Very Long Spans, ibid., pp. 489-

504.

[1] LEONHARDT, F. Zur Entwicklung

[6] MEIER, U. Carbon Fiber-

aerodynamisch stabiler Hangebrii-

Reinforced Polymers: Modern Materi-

cken. Die Bautechnik 45, Heft 10 und

als in Bridge Engineering. IABSE, Zu-

11,1968.

rich, SEI1/1992, p. 7.

[2] LACROIX, R., et al. 3000 Metres:

(7) SEIBLE, E, BURGUENO, R. Ad-

We Can Make It! Proc. Int. Conf.

vanced Composites in Cable Stayed

IABSE-FIP, Deauville, 1994, Vol. 1,

Bridges. Seminar in Cable-Stayed

pp. 505-515.

Bridges, Miami, FL, Oct. 17-18,1994.

WEST SEATTLE SWING BRIDGE, SEATTLE, WASHINGTON

John H. Clark, Vice Pres.,

Andersen Bjornstad Kane Jacobs, Inc.,

Seattle, WA

Planning

A double-leaf concrete swing bridge across the Duwamish River in Seattle, Washington, represents a revival of a type of movable bridge long out of favor and incorporates new concepts in machinery and movable bridge technology. The bridge connects two portions of the industrial port area of Seattle across one of its major shipping channels.

Prospects for widening the current-46 m wide ship channel to 76 m required replacement of an existing bascule, built in 1927. Navigation traffic in 1994 required approximately 10 open-

ings per day of the existing bridge, which provides 14 m of vertical clearance over high water. Increasing the vertical clearance from 14 m for the existing bascule bridge to 17 m for the new bridge was predicted to be sufficient to reduce the number of openings to 7 per day average, primarily for large ocean-going barges and ships. Roadway traffic is predicted to reach 11000 vehicles per day, with approximately 15 % truck traffic.

Pedestrians and bicycles are also provided for on the new swing span, but are excluded from the high level bridge. The total structure width of 15.2 m provides for two traffic lanes and one combined bicycle/pedestrian way 3.66 m wide.

164

Fig. 19

The swing bridge alignment was

the alignment was chosen, the span

placed on the existing bridge align-

lengths were fixed. The west approach

ment to minimize required right of way

length of 153 m is determined by the

and revisions to the existing street

need to cross over a railroad track and

network. This alignment results in the

an intersecting street. The east ap-

bridge axis being skewed approxi-

proach length of 147 m was deter-

mately 45° to the channel. A total of

mined by the maximum grade of 7%

nineteen different alignments and three

and vertical curve lengths required for

basic structure types were evaluated

proper sight distance. Stair towers for

before selection of the swing bridge for

pedestrian access are provided on each

final design development. Other struc-

approach. A control tower for the

ture types investigated in the prelimi-

bridge operator is adjacent to, but sep-

nary design stages were a vertical lift

arate from, the west pivot pier. The

bridge and a bascule bridge.

control tower is a 36 m high structure,

The 146 m span center-to-center of

so that the bridge operator has unre-

pivot piers (Fig. 19) for the swing

stricted view of the channel and all of,

bridge was established by the width of

the approach roadway.

the open west leaf and the location of a

Structural Design

column of the adjacent high level

bridge. The east pivot pier is then

 

placed symmetrically about the center-

The crossing site is near the mouth of

line of the proposed channel. The tail

the Duwamish River. Soils encoun-

span length of 53 m was also set by the

tered at the site range from hydraulic

column of the high level bridge. Once

fill and recent alluvial sands and silts

165

to heavily pre-consolidated glacial till.

transverse stiffness of the piles which

Depth to the till varies from 15 m on

would have led to eccentricity between

the west end of the project to 60 m on

the center of mass and center of rigid-

the east end. Lenses of loose silt exist

ity. These two problems were ad-

erratically throughout

the alluvium

dressed by the new concept of "seismic

layer. The loose surficial silts and hy-

isolation" sleeves.

 

draulic fill are deemed susceptible to

Considerations in the choice for the

liquefaction in major seismic events.

superstructure design were construc-

Densification by vibro-flotation was

tion economy, maintenance costs, traf-

specified to prevent such liquefaction.

fic safety and aesthetic compatibility

Seismicity in the area is moderately ac-

with the adjacent high-level bridge (a

tive. Seismic design criteria generally

concrete box girder). Two designs

followed the Guide Specifications for

were prepared and advertised for bids,

Seismic Design of Highway Bridges,

a post-tensioned segmental concrete

1983, of the American Association of

box girder and a steel box girder with a

State Highway and Transportation Of-

precast prestressed concrete deck made

ficials, with appropriate

modifications

composite after erection. Typical cross

for the unique structure. The basic

sections of the concrete alternative are

seismic coefficient, amax is 0.30 g and

shown in (Fig. 20).

 

the soil type is Type III.

 

A major challenge in the design of the

The main piers and superstructure

concrete box girder bridge was control

comprise a structural unit which does

of long-term deformations. Provisions

not contain the "ductile element" upon

for control of both long-term and

which the Guide Specifications are

short-term deformations included ad-

 

 

ditional post-tensioning beyond that

 

 

required for stress control, provision of

 

 

some unbonded tendons, provision for

 

 

additional future tendons,

provisions

 

 

for adjustment of approach span eleva-

 

 

tion at the tail span joint, provision for

 

 

vertical adjustment of each leaf as a

 

 

whole,

and specifications

requiring

 

 

nearly

simultaneous construction of

 

 

the two movable leaves.

 

 

 

The first line of defense against un-

 

 

wanted long-term deformation was the

 

 

adoption of the principle of load bal-

 

 

ancing for the design of the longitudi-

Fig. 20

 

nal post-tensioning. The amount of

based. The location of the piers in the

prestress provided is the amount re-

sloping bank of the existing and future

quired to provide 100% load balancing

channel created a problem of differing

for the final dead load condition. This

166

required approximately 30% more post-tensioning than the amount re quired to satisfy service load stress conditions. The deck of the box girder is post-tensioned transversely and vertical post-tensioning is included in the webs. The additional longitudinal posttensioning reduced the need for vertical post-tensioning in some areas.

Static balance of each leaf about the pivot pier is achieved by thickening the webs and bottom slab in the tail span and by the addition of ballast concrete and galvanized reinforcing steel bars such that the last 12 m of the tail span is solid except for an access shaft. Asbuilt measurements were taken after

casting of each section so that the final static balance could be closely predicted. It was found necessary to explicitly account for the measured density of the concrete (from quality control test cylinders) and the actual weight of reinforcing and prestressing steel in each segment to accurately predict the static balance. Allowable static imbalance during construction while the bridge rested on temporary service bearings was 72 MNm. Static imbalance during service operations of the movable leaves was limited to 6.8 MNm to avoid stick-slip chatter in the pivot shaft guide bearings.

Fig. 21

167

Pier House and Machinery

The 12.8 m diameter pier house carries the superstructure loads to the foundations and houses the drive machinery, emergency generators, and part of the control system. The pier table element of each leaf is supported by a transition element which provides two load paths to the foundation. The closed position path (serving vehicular traffic) is from the superstructure pier table through a conical shell to the walls of the pier house. Service bearings made up from steel plates with reinforced elastomers separate the transition element from the roof of the pier house. These service bearings are placed on an 11.4 m diameter circle. Temporary bearings were placed between the permanent service bearings to provide stability during construction of the cast-in-place segmental concrete leaves.

The operating position load path is from the pier table through the center portion of the transition element to the 3.66 m diameter pivot shaft. The pivot shaft is a concrete-filled steel shell 44 mm thick which in turn rests on the hydraulically operated lift-turn cylinder. The pivot shaft is maintained in the vertical position by guide bearings (Fig. 21) at the roof and operating floor level of the pier house. In the operating position, the whole movable leaf including transition element and pivot shaft are raised approximately 25 mm to transfer the load from the service bearings to the pivot shaft. A reinforced concrete footing founded on 36

concrete filled steel pipe piles, 91 cm diameter, completes both load paths. Heavy locks at the tail span joint and at the center joint are provided for transfer of seismic response loads and to restrain differential displacements due traffic, differential temperature, and accidental misalignment. The torsional stiffness of the box section is sufficiently high that locks were provided only on the longitudinal centerline of the section. The locks are driven by hydraulic rams powered by local pumps.

Twin hydraulic slewing cylinders (56 cm bore x 234 cm stroke) rotate each movable leaf from the closed position to the open position to allow for passage of ships. The operational cycle is based on a normal two minute slewing time, total cycle including traffic lights and gates is approximately 4.5 minutes. Friction is minimized due to the fact that the structure is supported on the hydraulic fluid of the lift-turn cylinder. The principal source of friction is the pivot shaft guide bearings which maintain vertical alignment.

Power for raising and rotating the movable leaf is provided by 3-75 kW, 8-liter-per-second hydraulic pumps in each pier house. Normal operation is with two pumps, the third pump alternates as a spare. Other redundancies built into the system include the ability to slew the bridge using only one slewing cylinder (with increased cycle time) and even to slew the bridge against the friction of the service bearings, should the lift/turn cylinder fail to operate.

168

Hydraulic system components are designed to operate at a normal pressure of 11.7 MPa and an emergency (slewing against the service bearing friction) pressure of 41.4 Mpa.

The control unit is a programmable controller which sequences operations, and provides status information to the bridge operator. The primary position control is limit switches which initiate braking via the controller. The control system is essentially the same as manual operation except that the controller "pushes the buttons," checks interlocks, and announces the status on a monitor. Manual override is possible for most steps of the operation.

Diesel powered emergency generator sets (350 kW) are provided in each pier house on the lower floor. Fuel storage is placed in day tanks on the shore.

Construction Costs

Bids for the construction of the project were received in September 1988. Five bids were received for the concrete box girder alternative ranging from USD 33.5 to USD 37.6 million, including demolition of the south bascule, all approach work and site work. The cost breakdown for major work categories (based on the low bid) is presented in Table 1. The contract called for a 22 month construction schedule.

Item

Cost

 

USD

 

Millions

Mobilization

2. 80

Demolition

3.76

Civil: streets, utilities,

3.38

traffic

 

Approach spans

4.66

Swing piers

6.87

Swing spans

5.60

Machinery

3.98

Electrical

1.06

Controls, control tower

0.94

Pier protection

0.48

Total

33.53

Table 1: Cost breakdown (low bid)

Owner: City of Seattle, WA

Design:

Andersen Bjornstad Kane Jacobs,

Seattle, WA

Parson Brinckerhoff Quade and

Douglas, Seattle, WA

Tudor Engineering, Seattle, WA

Contractor:

Kiewit-Global Joint Venture,

Seattle, WA

Service date August 1992

PRECAST SEGMENTAL HIGHWAY VIADUCTS, HAWAII

Gerard Sauvageot, Vice Pres.

Oahu Island, in the Hawaiian Islands,

J. Muller International, San Diego, CA

with the state capital Honolulu and the

General Description

bay of Pearl Harbor, is presently expe-

riencing significant new urban arid

 

169

tourism development. To link the most populated areas of the south to the towns and military bases on the northeast, the Hawaiian Department of Transportation, with the financial support of the US Federal Highway Administration, is building an extension of the H-3 Freeway across the steep and volcanic Koolau Mountains. Because of its natural beauty and archaeological significance, the whole area is very sensitive environmentally. From the vicinity of Pearl Harbor, the freeway includes the North Halawa Viaducts, the Haiku Tunnels under the mountain range, and the Windward Viaducts on the north slope, where it will connect to the north end of H-3 already in service

The new Windward Viaducts consist of twin parallel prestressed concrete structures approximately 2 km long with 24 spans each. The maximum span length is 91.5 m and column height varies from 3.6 to 48.8 m. The width of each bridge varies from 12.8 to 17.4 m. The geometry of the viaducts includes reverse curves with radius varying between 470 and 753 m and cross slope between 5.5 % on one side and 6.8% on the other side. The longitudinal slope of the structure is about 5 %. The horizontal distance between the structures is constant on most of the length at 21.3 m, but increases at one end where it connects to the two separate tunnels. Crosswise the elevation of the two parallel decks varies by as much as 4.6 m.

Value Engineering Design

The structure was designed as a vari-

able depth concrete box girder to be built in balanced cantilever with 4.9 m long superstructure segments cast in place with travelling forms. The structure shown in the base design would have been supported by cast-in-place hollow concrete piers with a single row of fixed or sliding bearings at the top. The foundations consisted of 400 mm diameter, octagonal precast driven piles.

After bidding on the base design, an alternate was proposed according to "Value Engineering" procedure, whereby certain economic and technical conditions must be met, such as sharing any savings with the owner and retaining the appearance, geometry, and alignment of the structure, which had been the object of a lengthy environmental impact assessment.

The alternate design accepted by the contractors’ joint venture and the owner, included the following changes:

-piers and superstructure were made monolithic

-precast piles were replaced with 1.5 m diameter drilled shafts

-precast segmental construction was used for the superstructure.

The project specifications allowed 1360 days for the construction of the viaducts. This schedule did not provide additional time for rainy days, which are frequent on the windward side of the island. Precast construction has the advantage of decreasing the amount of work performed at the site, improving quality and speed of erection and significantly, allowing the superstructure

170

to be entirely constructed from above

expansion joint is located every four

in this difficult terrain.

spans, at about one-quarter of the span.

Each viaduct is a single box made of

This disposition reduces deflections

precast segments with vertical webs

and changes of angle at the joint. The

and parabolic intrados. The depth var-

two hinge segments are temporarily

ies from 4.9 m at pier to 2.45 m at

prestressed and treated as one piece

midspan (Fig. 22). The length of the

during the erection process. Tendons

precast segments are such that the

through the hinge are released after the

maximum weight is 70 t. A 2-segment

next span is installed and stressed.

Fig. 22

The longitudinal post'-tensioning lay-

plied to the bridge at the end of con-

out was conventional with straight 19 x

struction according to the original pro-

13 mm strand tendons placed within

ject specifications.

the top slab and anchored at the seg-

Erection System

ment joints, close to the top of the

webs, 32 tendons were used in each

 

typical cantilever. The continuity post-

A special erection system was de-

tensioning consists typically of 18-19 x

signed and used for this structure with

13 mm strand tendons placed in the

a self-launching gantry that allowed

bottom slab and anchored in concrete

both viaduct structures to be built si-

blocks. No draped tendons were re-

multaneously. The system is designed

quired in the webs, except for the

to accommodate variable cross slopes,

hinge and abutment spans. Additional

curves, differential elevations, and

deviation blocks running from pier

variable distances between the two

segment diaphragm to pier segment

structures.

diaphragm provide for any future ex-

The system includes two independent

ternal post-tensioning contingencies. A

erection trusses, steel support beams

75 mm thick reinforced overlay is ap-

supporting the trusses, a gantry crane

171

and lifting trolley. The gantry crane is

26.2 m away) is entirely controlled by

supported by two trusses, one on each

an electronic device monitoring the

bridge.

speed of the hydraulic motors and

Transverse cross beams act as supports

keeping the "lag" within acceptable

for the trusses. Each truss rests on

tolerances.

three cross beams, one at the rear, at

The launching of the trusses to the next

the tip of the previous cantilever, one

pier is done by fixing the gantry crane

on top of the pier segment of the can-

to the concrete deck through a tempo-

tilever under construction and a third,

rary attachment and activating its hy-

mobile, on the front arm of the con-

draulic motors which then push the

crete cantilever and supporting the

trusses under the gantry instead of

truss as the construction progresses,

moving the gantry on the trusses. The

reducing deflections and moments in

trusses are launched one at a time to

the truss. This was possible because of

minimize the load on the cantilever.

the moment-resisting connection be-

A complete launching from pier to pier

tween the deck and pier shaft. Each

took about 18 hours (Fig. 23). After

cross beam is set horizontally on the

completion of the learning curve, the

concrete deck.

contractor typically achieved the re-

A gantry crane rolls longitudinally on

sults shown in Table 2. On the best

the top members of the two trusses.

day, the contractor was able to set 16

The gantry crane carries a lifting trol-

segments.

ley running transversely to the two

 

trusses. The segments are delivered by

 

truck at the extremity of the previous

 

cantilever, picked up by the gantry

 

crane/lifting trolley and delivered at

 

either ends of the twin cantilevers un-

 

der construction. The gantry crane is

 

equipped with two legs on wheels. The

 

leg on the mountainside truss is the

 

"fixed leg." The leg on the ocean side

 

truss is the pendulum leg. Each leg is

Fig. 23

built with the minimum degree of free-

dom compatible with its motion and

The remarkable speed that this erection

the stability of the gantry crane. The

system is able to achieve is due to its

longitudinal displacement on top of the

separation of the two operations which

trusses is by a rack-and-pinion hydrau-

were performed for each pair of seg-

lically driven system insuring total

ments, i.e., placing and post-ten-

safety on the 5 % longitudinal slope of

sioning. During the operation of plac-

the bridge. The relative longitudinal

ing a pair of segments, which included

motion of one leg with regard to the

bringing the segments to the erection

other (each leg running on one truss

equipment, applying epoxy and tem-

172

Соседние файлы в предмете [НЕСОРТИРОВАННОЕ]