    1. Inspections and site tests

Upon arrival at the installation site and during installation, the structures and equipment shall be inspected and tested.

The Contractor shall timely reveal and eliminate the defects, if any, prior to commencement of installation and/or tests.

The site tests are subdivided into two stages:

  • tests during installation and after completion of installation;

  • acceptance tests.

The tests during installation and after completion of installation are performed as per the requirements of factory's instructions, to confirm that the equipment has been properly installed.

The acceptance tests are performed to check the correctness and safety of the equipment's operation and, in particular, to check and confirm the quality of the works implementation. The acceptance tests are performed as per the requirements of factory's instructions, SOU-45.21.3-00100227-22:2010 and SOU-N EE 20.302:2007.

After all structures and equipment are installed and assembled at the site, they shall be tested and trial-operated for the site's conditions.

The tests to be performed by the Contractor at the commissioning stage, are specified by the Technical Requirements.

If any of the test results specified in the Technical Requirements does not satisfy these requirements, the Employer has the right to reject this equipment and demand from the Contractor to replace this equipment with re-testing.

Upon request of the Employer, the Contractor shall perform additional tests specified in the Technical Requirements or in the Contract. In addition, the Employer may request to perform additional tests or repeat the tests already performed, based on the results of the analysis of already performed tests of materials or in case of deviations from standard technology of installation or testing of equipment at the site.

  1. Test reports and test programs

    1. Factory test reports

The results of factory tests shall be recorded in the test reports along with relevant technical data requirements.

The results of factory tests shall be submitted in the approved report format.

Certificates of the tests shall reflect the actual results and conditions of the tests performed.

All test reports shall be submitted to the Employer in four (4) copies in English and Ukrainian languages.

    1. Test programs

Within the terms stipulated by the Contract, the Contractor shall submit the Test Program of completed facility to the Employer for approval, but at least three months prior to the beginning of the tests. The Test Program is developed by the Contractor and approved by the Employer, taking into account the requirements of SOU-45.21.3-00100227-22:2010.

The Test Program proposed by the Contractor will be approved only after all certificates (reports) of type tests are submitted to the Employer.

  1. Warranty

The Contractor shall guarantee the reliable operation of all equipment and structures that the Contractor has supplied and installed, within at least 3 years from the commissioning date.

The Contractor shall ensure that the facility's operation meets all requirements of relevant standard sand provisions of the Contract.

During this warranty period, the Contractor, at own cost, shall eliminate all defects and repair any part of the equipment that was properly installed and operated, but failed due to structural defects or spoilage in production.

The above warranty period covers the equipment that was repaired or replaced, starting from the date of repair or replacement.