    1. Requirements to measurement assurance/metrological support

Metrological provision applies to information-measuring channels, lines and sensors, algorithms implemented ACS TP process control, including computational algorithms.

The structure and content of works on the ACS TP measurement assurance at all stages of design, implementation and operation shall meet requirements of the Law of Ukraine “On metrology and metrological activity”, GKD 34.20.507-2003 “Operation of power station and power grids. Rules”.

Measuring instrumentation employed in ACS TP, shall be included in the state Registry of means of measurement as the instruments permitted for us in Ukraine or pass the State metrological certification.

The ACS TP measuring channels in the course of ACS TP trial operation shall pass metrological certification according to the developed programs and methods that are to be used further in the ACS TP operation for periodic testing of their metrological characteristics.

    1. Requirements to spare parts and accessories

The Supplier must provide a list of spare parts, supplies and equipment necessary, in his opinion, for the construction, installation, commissioning, and maintenance and repair of the SHS for 10 years of operation of the equipment.

The scope of spare parts shall ensure meeting requirement of preparedness and serviceability of SHS throughout the guaranteed service life.

The equipment set shall include specific checker devices, which are required for assembly, adjustment, start-up, maintenance and repairs of every supplied item of software/hardware (microprocessor-based checker devices, digital equipment testers, calibrators for checking the measuring channels etc.).

    1. Requirement to Documentation

The producer (supplier) of each system (subsystem) as part of ACS TP should provide a complete set of technical and operational documentation in Ukrainian or Russian, composed of all necessary for design, installation, adjustment, start-up, commissioning, ensuring the correct and safe operation, equipment and SHS maintenance that are delivered.

It agrees with GOST 34.602-89 and with RD of 50-34.698-90 requirements to documents which should be given out, regulated on the basis of table 2 GOST 34.201-89.

      1. Technical documentation

All hardware and software components of supplied system must be provided with the standard technical documentation of the Supplier, including:

  • Technical forms on the components of hardware with confirmation (certificates) of the requested technical and functional requirements for these components, which may be set out in the technical descriptions and specifications of supplied hardware.

  • Conformance certificate for provided within the system software data exchange protocols, confirmed by authorized testing centers.

  • Software components documentation, including:

    • Description of software components

    • User’s guide

    • Instructions for installation and maintenance of software

    • Service instruction for operating personnel

      1. Project documentation

At development stage ACS TP project documentation in full according to GOST 34.602-89, GOST 34.201-89 should be executed, RD50-34.698-90 and to include the following sections:

  • all-system decisions;

  • information support;

  • organizational providing;

  • technical providing;

  • software.

Besides, should be presented:

  • scheme structural of the system’s complex of means;

  • scheme of cable channels (FOCL, communication, etc.);

  • the scheme of secondary connections between hardware components ACS TP and external relations;

  • journal of cables and wires;

  • equipment specification;

  • sheet of requirement for materials and local estimates;

  • connection diagram of external wiring;

  • linkup diagram of external wiring;

  • table of connections and linkups;

  • general drawing;

  • layout of wiring, equipment, installation of technical equipment;

  • schemes basic.

As a part of project documentation it should be executed:

  • calculation of reliability of ACS TP according to a IEC standard

  • calculation of efficiency of ACS TP according to a IEC standard.

Detailed documentation on the ACS TP should be coordinated with the corresponding services of the Employr with the established procedure.