3. Identify the part of the building or (he phase of the assembly sequence described in these sentences:
This
cannot be put in place until the upper floor steel columns have
been
erected.
Before fixing these, the
workmen erect the corner units.
During this phase the beams
and bracing are fixed.
The workmen fix these after
constructing the concrete foundations.
The electric wiring is
installed during this phase.
When the balustrade fixing
plates have been fixed, the workmen can start laying this.
4. Read this description of phase 1 of the assembly sequence:
Having
completed the preparation of the site, the workmen begin the initial
stage. This includes excavating the ground, constructing the concrete
foundations, fixing the column base plates and erecting the steel
columns. The workmen begin by excavating the ground. This precedes
the constructing of the concrete foundations because they require
solid ground to support them. This is followed by the fixing of the
column base plates. Finally the steel columns are erected.
Now
use it as a model to write similar descriptions of phases 2,3,and 4.
1.
Describe the difference between old and new constructions.
2.
Read the texts on the disc.
3.
Find information about methods of construction, that will be used in
future.