Добавил:
Опубликованный материал нарушает ваши авторские права? Сообщите нам.
Вуз: Предмет: Файл:

Экзамен зачет учебный год 2023 / The independence principle of letters of credit and demand guarantees

.pdf
Скачиваний:
10
Добавлен:
23.12.2022
Размер:
30.06 Mб
Скачать

Lite N ature o f D em and Guarantees

Insurance Co.,'2*where there had been substantial argument before the Court of Appeal on the rule in Holme v. Brunskill, Scott L.J. said that the rule did not apply because there was in fact no variation of the underlying transaction ‘and, in any event, the bond was not a guarantee’.4125 This makes it clear that in his view even if there had been a variation of the underlying transaction the rule in Holme v Brunskill would not have applied to the performance bond in that case. More recently, in Wittmann (UK) Ltd v. Wildav Engineering SA'26 Moore-Bick L.J., disagreeing with the trial judge,127 expressly stated that a variation of the underlying transaction in that case could not discharge the issuer because the issuer had expressly contracted as a primary obligor, not merely as a surety. . . and thereby incurred an obligation that was not susceptible of being discharged by dealings of a kind that would ordinarily discharge one whose liability is secondary only’.

5.Section 4 of the Statute of Frauds 1677

3.70A further difference concerns the requirement of writing of section 4 of the Statute of Frauds 1677. The section applies to any promise ‘to answer for the debt default or miscar­ riage of another person’. Since a suretyship guarantee contains such a promise, it is subject to the formal requirement of section 4, namely that it should be in writing. By contrast, since under a demand guarantee the issuer promises to pay, as principal, his own debt rather than the debt of another person, a demand guarantee falls outside the scope of section 4, just as an indemnity.128 However, in practice this difference is unlikely to be very relevant since, considering the commercial context in which most demand guarantees are issued, it would be extremely rare for the issuer’s promise not to be in writing. The URDG 758 defines a demand guarantee as any ‘signed undertaking’ providing for payment on presentation of a complying demand.129

IV. PROBLEMS OF CATEGORIZATION: DEMAND

GUARANTEE OR SURETYSHIP GUARANTEE?

3.71The differences between a demand guarantee and a suretyship guarantee mean that the correct categorization or characterization of a particular instrument is a matter of consider­

able practical importance. In Marubeni Hong Kong and South China Ltd v. Government o f Mongolia,130 for example, the central issue turned on ‘the correct characterisation of

124[1992] 2 Lloyd’s Rep. 365.

125Ibid., at 377.

126[2007] EWCA Civ 824 at [22].

127See also Marubeni v. Governmento fMongolia [2004] 2 Lloyds Rep. 198 at [142] where CressweliJ. held that the issuer’s undertaking was secondary rather than as a primary obligor so that the rule applied. He then went on to express the view, obiter, that the feet that an instrument is one which creates a primary liability does not mean that the rule in Holme v. Brunskill has no application to it. The Court of Appeal ([2005] 2 Lloyds

Rep. 231; [2005] 2 All ER (Comm) 289), expressed no opinion on this point, as it was not necessary to do so, since the court agreed with Cresswell J.’s characterization of the instrument as a suretyship guarantee creating secondary liability.

128AssociatedBritish Ports v. Ferryways NV [2009] EWCA Civ 206 at [1].

129Art. 2. By contrast, in Art. 2 of the UN Convention the undertaking is not required to be in writing

130[2005] 2 AUER (Comm) 289.

52

IV. Problems o f Categorization: D em an d Guarantee or Suretyship Guarantee?

 

the’ instrument.131 Ambiguous drafting in some cases makes the task of the court in determin­

 

ing whether a particular instrument is a demand guarantee or a true guarantee a difficult

 

one.132 It is generally accepted that the correct characterization depends on the construction

 

of the instrument.133 'fire instrument must be construed ‘by looking at it as a whole without

 

preconceptions as to what it is’.134 The commercial context in which the instrument was

 

issued is also relevant.135 This section considers the approach of the English courts when

 

construing an instrument to determine whether it takes effect as a demand guarantee or as a

 

suretyship guarantee.

 

It is submitted that, although categorization of each instrument depends on its terms and

3.72

the context in which it was issued, the effect of the authorities is that where an instrument,

 

issued by a commercial bank, states that the bank undertakes irrevocably and uncondition­

 

ally to pay on demand up to a maximum amount if the demand is accompanied by a certifi­

 

cate (issued by the beneficiary or a third party) stating that the account party has defaulted

 

and that the amount demanded is due and payable by the bank, the court is likely to construe

 

that instrument as a demand guarantee, especially if the instrument states that the certificate

 

shall be conclusive and binding on the bank. Similarly, where an instrument, issued by an

 

individual, describes itself as a performance bond and states that the issuer undertakes irre­

 

vocably and unconditionally, as primary obligor and not merely as surety, to pay on demand

 

up to a specified maximum amount if the demand is accompanied by a certificate (issued by

 

the beneficiary or a third party) stating that the account party has defaulted and the amount

 

demanded is due and payable by the issuer, the court is likely to construe the instrument as

 

a demand guarantee, especially if the instrument contains a provision to the effect that the

 

certificate shall be conclusive and binding on the issuer.

 

In discussing the cases, it may be helpful first to consider any indications that may be derived

3.73

from specific terms before examining the position where the issuer is not a bank. The ques­

 

tion whether any indication may be drawn from the fact that the underlying contract is an

 

international transaction is considered at the end of this section.

 

1. Indications from Specific Terms

In Van DerMerwe v. II Capital LLC,136 Lewison J. said that in considering the meaning of 3.74 an instrument ‘it is necessary to pay attention to the instrument as a whole and not to dissect

it into its constituent parts’. However, he recognized that ‘for the purposes of exposition the points need to be dealt with one by one’.137 It is proposed to consider in turn the terms that have been examined in the principal authorities in which the question of characterization has presented itself. The value of each term as an indication of the nature of the instrument in question will be assessed. It should be noted that no single term is alone decisive. The court

131Ibid., at [9].

132The Wardens and Commonalty ofthe City o fLondon v. New Hampshire Insurance Co [1992] 2 Lloyd s Rep.

365, 374, per Scott L.J.

1331IG Capitall v Van DerMerwe [2008] EWCA Civ 542 at [7].

134Gold Coast Ltd v. CajadeAhorrosdelMediterraneo{2QQ2\ 1 AllER(Comm) 142 at [lSl./'ffTuckey L.J.

See also I!G CapitalLLC v. VanDerMerwe [2008] EWCA Civ 542 at [7].

135IIG CapitalLLC v. Van DerMerwe [2008] EWCACiv 542 at [20].

136[2007] EWLIC 2631 (Ch).

137Ibid., at [37].

53

I

The N ature o f D em and Guarantees

considers all the terms in the context in which the instrument was issued. If, on the whole, there are more features indicating that the issuer’s undertalcing is primary and independent, the court is likely to hold that the instrument is a demand guarantee, even though it also contains some terms indicating that the liability is secondary.

A.Description

3.75The terminology by which the instrument describes itselfor the issuer is a relevant indicator. For example, where an instrument describes itself as a ‘guarantee’ or where it is so described in correspondence between the parties or where it refers to the issuer as the ‘surety’, that is an indication that the instrument is a true guarantee rather than a demand guarantee. In the Trafalgar House case,138 where the instrument described the issuer as ‘the surety’, the use of the word ‘surety’ was one of the important factors that led the House of Lords to conclude that the instrument was a contract of suretyship rather than a demand bond. Indeed where the instrument is described as a ‘guarantee’ or some other language not appropriate to a performance bond and the issuer is not a bank a strong presumption is raised in favour of construing the instrument as a true guarantee {the Marubeni presumption).139 Conversely, where on its face, the instrument is described as a ‘performance bond’ or some other termi­ nology appropriate to a demand guarantee or if it is so described in correspondence between the parties to the underlying contract and the issuer, the court takes that into account.140 In such a case, the Marubeni presumption will not be raised even if the issuer is not a bank.

3.76However, although the terminology used to describe the instrument or the issuer is a relevant indicator, it is not conclusive.141 The terms of the instrument may show that the terminol­ ogy used to describe it is a misnomer. For example, an instrument may describe itself as a performance bond’ but the terms may show that the obligation which it creates is secondary so that it is a true guarantee.14213The reverse is also true. In Gold Coast Ltd v. Caja de Ahorros delM editerranean where the instrument described itselfas a ‘guarantee’ the Court ofAppeal said that that description ‘is simply a label; [the instrument] does not use the language of guarantee’. Since the terms of the instrument showed that the parties’ intention was to create a primary liability, it was held that that was enough to displace the ordinary sense of the term

guarantee and to lead to the conclusion that the instrument in question was a performance bond.144

138Trafalgar House Construction (Regions) Ltd v. GeneralSurety & Guarantee Co Ltd[ 1996] 1 AC 199.

139MarubeniHong Kongo. Governmento fMongolia [2005J EWCACiv395; [2005] 2A(IER(Comm) 289, discussed in paras 3.95 to 3.98 below.

140Siporex TradeSA v. Banque Indosuez[ 1986] 2 Lloyd’s Rep. 146, where a letter oi guarantee was held to be a performance bond even though the term performance bond’ did not appear anywhere in the guarantee itself. Howevei, the teim was used in the underlying contract and in most of the correspondence between the parties relating to the guarantee (see 151-153).

141 Marubeni. HongKongandSouth China Ltd v. Governmento fMongolia [2005] 2 All ER (Comm) 289 at [30]. 14 e.g. Greenore PortLtd V. Technical & General Guarantee Company Ltd [2006] EWHC 3119 (TCC)

143[2002] 1 All ER (Comm) 142 at [21].

144See also, to the same effect, Van DerMerwe v. TIG CapitalLLC [2007] EWHC 2631 (Ch). In Greenland Bank Ltd v. American Express Bank Ltd [2008] EWHC 421 (Ch), at [3], where the parties described the instrument as a guarantee , Evans-Lombe J . regarded that terminology ‘as confusing because the document in question is not a guarantee’. It was held to be a performance bond.

54

IV. Problems o f Categorization: D em and Guarantee or Suretyship Guarantee?

B. Payment‘on demand’

■Where an instrument states that it is payable ‘on demand’145 or on ‘first demand 146 this

3.77

is taken to be a strong indication that the issuer’s obligation is intended to be independent of

 

the underlying contract. In Gold Coast Ltd v. Caja deAhorros del Mediterranean1where the

 

issuer promised to pay ‘within five (5) days of your first written demand’ it was held

 

that the instrument created an obligation to pay which was independent of the underlying

 

contract. Thomas J. stated that ‘[t]he use of the words “on first written demand” is the lan­

 

guage of an obligation independent of the underlying contract; it indicates that the payment

 

will be made against a demand made without a final decision on the actual position under

 

the underlying contract’.148 In one Australian case, where the instrument required a bank to

 

pay ‘on demand’, Gibbs J. said that to hold that the bank should not pay on receiving a

 

demand, but should enquire into the rights of the parties to the underlying contract to which

 

it, the bank, was not a party, ‘would be to depart from the ordinary meaning of the undertak­

 

ing that the Bank is to pay on demand’.149150Similarly, in Balfour Beatty Civil Engineering v.

 

Techincaldr General Guarantee Co L td )5awhere a bond was payable on ‘first written demand’

 

the Court of Appeal held that the bond contained language which seemed to make it ‘abso­

 

lutely clear’ that it was intended to create an independent obligation.15112And more recently

 

in IIG v. Van DerMerwe152 the fact that the issuer’s obligation was to pay ‘upon demand’ was

 

one of the factors that indicated that the issuer’s obligation in that case was independent of

 

the underlying contract.153

 

However, the fact that a guarantee contains a term stipulating for payment ‘on demand’ does

3.78

not necessarily mean that the issuer’s undertaking is independent. Other terms have to be

 

considered. If, on balance, there are more terms indicating that the undertaking is secondary

 

the court will treat the instrument as a suretyship guarantee in spite of the fact that payment

 

is stated to be ‘on demand’.154

 

C. Undertaking ‘unconditional’

 

The obligation of the issuer to pay under a performance bond does not in the ordinary way

3.79

depend on the correct resolution of any dispute relating to the performance or not of the

 

underlying contract.155 The issuer, as Lord Denning once said, ‘must pay. . . on demand if so stipulated, without proof or conditions’.156 This is the case even though there is no term in

145 e.g. IE Contractors Ltd v. Lloyds Bank Pic [1990] 2 Lloyds Rep. 496; Esal (Commodities) Ltd v. Oriental Credit Ltd [1985] 2 Lloyd’s Rep. 546.

146e.g. Balfour Beatty Civil Engineering v. Technical & General Guarantee Co Ltd [2000] CLC 252.

147Gold CoastLtd v. Caja deAhorros DelMediterraneo, 2 May 2001, QBD, Commercial Court, affd [2002]

1All ER 142.

148Ibid., at [29].

149WoodHallLtd v. The PipelineAuthority (1979) 141 CI..R 443, 451.

150[2000] CLC 252.

151See also Esal (Commodities) Ltd v. Oriental Credit Ltd [1985] 2 Lloyds Rep. 546; Siporex Trade SA v.

Banque Indoseuz [1986] 2 Lloyd’s Rep. 146.

152[2008] EWCA Civ 542.

153Ibid., at [31].

154e.g. Marubeni Hong Kong v. GovernmentofMongolia [2005] 2AllER(Comm) 289.

155Esal (Commodities) Ltd v. Oriental Credit Ltd [1985] 2 Lloyd’s Rep. 546.

156Edward Owen Engineering Ltd v. Barclays Bank InternationalLtd [197H\QB 159, 171.

55

The N ature o f D em and Guarantees

the instrument expressly specifying that the issuer’s obligation is unconditional.15718960Therefore, where the issuers obligation is expressly stated to be unconditional’, the court will be more inclined to construe it as being independent of the underlying transaction. Thus, in Wood Hall Ltd v. The Pipeline Authority,™ where the issuer unconditionally’ undertook to pay, Gibbs J. said that to hold that the instrument was conditional on the making of a demand that conformed to the requirements of the underlying contract ‘would of course be quite inconsistent with the express statement in the bank guarantees that the undertaking of the Bank is unconditional’. And in Gold Coast Ltd v. Caja de Ahorros del Meditteraneo159 the Court of Appeal construed the issuer’s obligation as being independent of the underlying contract partly because it was expressed to be irrevocable and ‘unconditional’. Although the guarantee in that case also stated that it was subject to certain ‘conditions’, such as that a demand should be accompanied by a third party’s certificate of default, the court did not consider that those ‘conditions’ made the issuer’s obligation to pay conditional in the sense that the obligation could only arise upon proof of the account party’s default under the underlying contract.

D.Primary obligor clause

3.80A term in an instrument to the effect that the issuer is liable as ‘primary’ or ‘principal’ obligor and ‘not merely as a surety’ indicates that the parties are likely to have intended that the issuer’s obligation should be independent of the underlying contract. In Van Der Merwe v. TIG Capital LLC 160 the issuer’s undertaking was to pay on demand upon presentation of a certificate of default stating the amount due and payable under the guarantee. The guarantee also stated that the certificate was to be conclusive evidence of the issuer’s liability to pay the amount stated. There was a clause stating that the guarantor’s undertaking to pay was ‘as principal obligor and not merely as surety’. In concluding that the instrument created an obligation independent of the underlying contract, Lewison J. took into account the fact that the obligation was ‘cast in the form of a primary obligation’.161 The decision was upheld by the Court of Appeal where it was held that the obligation to pay ‘as principal obligor’ ‘not merely as a surety’ indicated that the issuer undertook something more than a secondary obligation.162

3.81However, the mere fact that an instrument contains a clause stating that the issuer is liable as ‘primary obligor’ does not necessarily lead to the conclusion that the issuer’s obligation is completely independent of the underlying contract. In some cases a ‘primary obligor’ clause may be inserted in an instrument which otherwise creates a secondary obligation in order to make the issuer liable as primary obligor in limited circumstances only. In such cases the instrument will remain a suretyship guarantee though the issuer will be liable as principal obligor in the limited circumstances envisaged by the instrument.163

157e.g. Howe Richardson Scale Co Ltd v. Polimex-Cekop and National WestminsterBank Ltd [1978] 1 Lloyd s Rep. 161; Esal(Commodities) Ltdv. Oriental Credit Ltd [1985] 2 Lloyd’s Rep. 546.

158(1979) 141 CLR 443,451.

159[2002] 1 A1IER (Comm) 142, 149.

160[2007] EWHC 2631 (Ch).

161Ibid., at [49]. See also [51] and [531.

162[2008] EWCA Civ 542 at [31 ].

163z.g.Healdv, O’Connor \\97\\1 WI.R497; GeneralProduce Co v. UnitedBank 7fc/[l 97912 Lloyds Rep. 255, esp. at 259.

56

IV. Problems o f Categorization: D em an d Guarantee or Suretyship Guarantee?

 

E. Certificate of liability

 

Where an instrument refers to the event that will give the beneficiary the right to demand

3.82

payment (such as the account party’s failure to perform his obligations under the underlying

 

contract) and then states that the issuer shall pay on demand accompanied by a beneficiary’s

 

certificate or a certificate issued by a third party, such as a bank, stating that the event has

 

occurred, that is regarded as a strong indication that the issuer’s liability to pay arises

 

not when the specified event has occurred but when a demand is made accompanied by the

 

required certificate.16415In Gold Coast Ltd v. Caja de Ahorros del M editerranean for example,

 

there was an irrevocable and unconditional undertaking to pay ‘if and when’ any instalment

 

payment became refundable from the account party under the underlying contract. The

 

instrument required a demand to be accompanied by a certificate issued by Lloyds Bank

 

certifying that the buyer had become entitled to a refund. It was held that the instrument was

 

a performance bond conditioned upon the certificate rather than the fact that the buyer was

 

entitled to refund. Tuckey L.J., with whom the other members of the Court of Appeal

 

agreed, explained that ‘the “if and when” part of the instrument does no more than identify

 

the contractual events which trigger the right to call the refund guarantees in the same way

 

as the bond in the Esal case referred to the underlying liability’.16617In the subsequent case

 

of Marubeni v. Government o f Mongolia'61 Carnwath L.J., referring to the decision in

 

Gold Coast, said that the fact that the provision of a bank certificate was a trigger for pay­

 

ment was ‘a clear indication that the obligation to pay was independent’ of the underlying

 

contract.16819

 

F. Conclusive evidence clause

 

Where the instrument provides that a required certificate shall be conclusive evidence of

3.83

default or of the amount due and payable this is considered to be a strong indication that the

 

issuer’s obligation is independent and primary. The reason is because such a clause makes it

 

clear that the parties intended that the issuer’s liability shall depend on the certificate rather than the correct resolution of disputes arising from the underlying contract. In Bache & Co (London) Ltd v. Banque Vernes et Commerciale deParis SAU9 a conclusive evidence clause in a bank guarantee was upheld by the Court ofAppeal. I he guarantee was issued to commodi­ ties brokers on behalfof their customer. The clause provided that a beneficiary’s notice to the bank stating that the account party was in default was conclusive evidence that the bank’s liability under the guarantee had accrued in respect of the amount claimed. It was held that if a notice was given the bank was liable to pay. The bank’s liability did not depend on the underlying facts. Scarman L.J. said that it was clear beyond dispute that the words ‘conclu­ sive evidence’ in the instrument were to be a bar to any evidence being tendered to show that the statement in the notice of default was not correct. The same approach was adopted in

164IE Contractors Ltd v. Lloyds Bank Pic [1990] 2 Lloyd’s Rep. 496, 500. See also Siporex Trade SA v. Banque Indoseuz [1986] 2 Lloyd’s Rep. 146, where the undertaking was to pay on demand In the event that no letter of credit had been opened by a specified date and the bond required any demand for payment to be supported by the beneficiary’s declaration to that effect. Hirst J. held that the bond was independent of the underlying events. The payment obligation was triggered by a demand plus a declaration to the effect that no credit had been opened.

165[2002] 1 All ER (Comm) 142.

166Ibid., at [23].

167[2005] 2 AUER (Comm) 289.

168Ibid., at [29].

169[1973] 2 Lloyd’s Rep. 437.

57

The N ature o f D em a n d Guarantees

Balfour Beatty Civil Engineering Ltd v. Technical & General Guarantee Co Ltd.'70 In that case the instrument required a beneficiary’s demand to include a statement that the account party had defaulted on his obligations under the underlying contract and that the sum demanded was due and payable. The instrument provided that such a statement was to be accepted by the issuer as conclusive evidence’ that the sum demanded was due under the instrument. Waller L.J. held that the instrument contained ‘the clearest possible indication’ that as between the issuer and the beneficiary there was to be no investigation into the underlying facts.

3.84A conclusive evidence clause has the same potency even in the case of an instrument issued by an individual rather than a bank. In Van DeMerwe v. IIG CapitalLLC'1' guarantees were given by a husband and wife to secure the liability of a company in which they were the only shareholders to repay a loan advanced to the company. The guarantee contained a clause stipulating that a beneficiary’s certificate stating the amount ‘due and payable’ under the guarantee shall, save for manifest error, be ‘conclusive and binding’ on the issuer for purposes of the guarantee. Lewison J. did not hesitate to conclude that the instrument created a liabil­ ity independent of the underlying obligation. After a careful consideration of the features indicating that the instrument created a secondary obligation, as the guarantors contended, and those indicating that it created a primary and independent obligation, as the beneficiary argued, the learned Judge said that what clinched the argument in favour of the beneficiary was the conclusive evidence clause.1720 The Court of Appeal agreed with Lewison J. that the conclusive evidence clause ‘puts the matter beyond doubt’.173

3.85However, for a conclusive evidence clause to be regarded as a strong indication that the issuer’s liability is primary and independent, the certificate or statement to which it relates must extend to the liability rather just the amount.17415And since conclusive evidence clauses are interpreted strictly, with any ambiguity resolved in favour of the guarantor, if there is any ambiguity as to whether a particular clause includes liability, it is resolved in favour of the guarantor. The recent case of Carey ValueAdded SL (Formerly Losan Hotels World ValueAdded ISL) v. Grupo Urvasco SAm concerned an application for summary judgment by the benefi­ ciary. The relevant clause provided that ‘[a]ny certification or determination by [the benefi­ ciary] of a rate or amount under any Transaction Document or this deed is, in the absence of manifest error, conclusive evidence of the matters to which it relates’. Blair J. held that although a certificate under this clause was conclusive evidence as to ‘amount’ it was not conclusive evidence as to liability, since, unlike the clause in IIG Capital which covered both amount and liability, the clause in this case related only to amount. Blair J. explained that there was a major difference between a certificate as to ‘amount’ and a certificate as to ‘amount due and payable’. He said that in so far as there was any ambiguity in the clause, it was to be resolved in favour of the guarantor, by holding that a certificate given under the clause

170(1999) 68 Con LR 180.

171[2007] EWHC 2631 (Ch).

172Ibid., at [51].

173HG Capital LLC v. Van Der Merwe [2008] EWCA Civ 542 at [32]. The position is different where the instrument requires a certificate from an expert, such as an engineer, and requires the expert to give reasons. In such a case if the instrument provides that the certificate shall be conclusive evidence save for manifest error, the court may conclude that the clause permits an investigation into the reasons of the expert: Invensys Pic v. Automotive Sealing Systems Ltd, 8 November 2001.

174VosslohAktiengesellschaft v. Alpha Trans (UK) Ltd[20U)\ EWHC 2443 (Ch) at [50].

175[2010] EWHC 1905 (Comm).

58

IV. Problems o f Categorization: D em and Guarantee or Suretyship Guarantee?

was not conclusive evidence as to liability.176 The result was that the issuer had shown that it was arguable that the instrument in this case did not contain language indicating that it was a demand bond.

G. Whether issuer s liability is со-extensive with that of account party

 

A provision in the instrument to the effect that the issuer’s liability is not со-extensive with

3.86

that of the account party is an indication that the instrument is intended to take effect as a

 

demand guarantee. In Van De Merwe v. IIG CapitalLLC)11 for example, the guarantee was

 

issued to secure repayment of a loan. It was held that the guarantee took effect as a demand

 

guarantee partly because under the terms of the instrument the liability of the issuer was not

 

со-extensivewith that ofthe borrower. LewisonJ. explained that the definition oFGuaranteed

 

Monies’ in the instrument was of considerable significance. It included not only those which

 

the borrower actually owed the lender ‘but also monies “expressed to be due, owing or pay­

 

able” by [the borrower] to [the lender]. These words point towards the conclusion that the

 

Guaranteed Monies may extend beyond what is actually owing by [the borrower] to [the

 

lender]; and hence that the liability of [the issuers] is not necessarily со-extensive with that

 

of [the borrower]’.178

 

 

The reverse is true. Where the terms of the instrument are to the effect that the liability of the

3.87

issuer is со-extensive with that of the borrower, it is an indication that the instrument was not

 

intended to take effect as a demand guarantee. In Carey Value Added SL (Formerly YLosan

 

Hotels World Value Added I SL) v. Grupo Urvasco &4179 the issuer undertook to be responsible

 

as primary obligor for any failure of the borrower to discharge any of the guaranteed obliga­

 

tions when due. The guaranteed obligations were defined in the instrument as ‘all obligations

 

of the [borrower] under or in connection with the’ underlying transaction. Blair J. said that

 

this term was an indication that the guarantor’s liability was the same as that ofthe borrower.180

 

Another provision in the instrument, clause 2.1(d),181 which created an obligation on the

 

issuer to indemnify the beneficiary was qualified by a proviso that the amount in question shall

 

be equal to the amount that the beneficiary would otherwise have been entitled to recover

 

under the loan agreement. Blair J. also held that the language of this clause ‘appears to me to

 

be the language ofсо-extensive liability, and certainly not indicative of the unqualified liability

 

which arises under a demand bond’.182 It was therefore held that it was arguable that on the

 

whole the instrument did not contain language that was appropriate to a demand guarantee.

 

H. Guarantee subject to URDG

 

If, by its terms, a guarantee or bond is subject to the URDG 758 this should be a strong

3.88

indication that the parties intended the instrument to be a demand guarantee. Since the

 

176

Ibid., at [40].

 

 

177

[2007] EWHC 2631 (Ch)

[2008] EWCA Civ 542.

 

178[2007] EWHC 2631 (Ch) at [48].

179[2010] EWHC 1905 (Comm).

180Ibid., at [37].

181Set out in para [25] of the judgment.

182[2010] EWHC, 1905 (Comm) at [37]. It may be open to doubt whether the issuer’s liability under clause 2.1(d) was со-extensive with that of the borrower. Although, in terms ofamount, the extent of the issuers liability under the clause was equal to that of the borrower, in terms of conditions of liability, under the clause (2.1 ,(d)(ii)) the issuer may be liable in circumstances where the borrower may not be liable, as where any of the guaranteed obligations became ‘unenforceable, invalid or illegal’. This appears to be the language of a demand guarantee.

59

T—

Mi

i f f

The N ature o f D em a n d Guarantees

URDG 758 only applies to demand guarantees or counter-guarantees’83 and under the rules a guarantee is by its nature independent of the underlying contract,11843 if the parties decide to make their guarantee subject to those rules then this should be a very strong indication that they intended their guarantee to be the kind regulated by the rules. Therefore, unless there are compelling reasons to the contrary, a guarantee subject to the URDG 758 is likely be construed as a demand guarantee rather than a suretyship guarantee.185

I. Clause excluding the effect of a variation of the underlying contract

3.89 A provision in an instrument to the effect that a variation of the terms of the underlying contract shall not have the effect of discharging the issuer from his liability is normally an indication that the instrument is a suretyship guarantee. The reason is because such a clause is required in a suretyship guarantee since, as indicated above, without it the guarantor will be discharged by a material variation of the underlying contract without his consent. The leading case is Trafalgar House Construction (Regions) L td v. General Surety & Guarantee Co Ltd786 The main contractor for the construction of a leisure complex for a borough council entered into a subcontract for ground works. To support the subcontract a guarantee com­ pany provided a bond for 10 per cent of the value ofthe subcontract. The subcontractor was unable to carry out the work so the contractor completed the work and claimed under the bond. The question was whether the liability of the guarantor was independent of the sub­ contract. The Court of Appeal held that the obligation created by the bond was ‘an indepen­ dent obligation to pay’. The House of Lords held that by so holding, the Court ofAppeal was effectively treating the bond ‘as a type of on demand bond’.187 Their Lordships reversed the decision of the Court of Appeal and held that the bond was a suretyship guarantee. One reason why the House of Lords construed the bond in this way was the fact that it contained a clause to the effect that no alteration in the terms of the underlying contract would release the guarantor from his liability. Lord Jauncey ofTullichettle, with whose speech all the other members of the Judicial Committee agreed, stated that in the absence of such a provision a surety would normally be released from his obligation by any subsequent material alteration to the provisions of the underlying contract agreed between the parties without the consent of the surety.188 Therefore, he explained, the clause was only necessary because the parties regarded the issuer’s obligation under the instrument as a secondary obligation dependent on the underlying liability.18910

3.90 Although such a clause is an indication that the instrument is a suretyship guarantee, it is not decisive. If other terms of the instrument strongly indicate that the instrument is a demand guarantee the court will construe it as such. In Gold Coast Ltd v. Caja de Ahorros del Mediterraneo190 an instrument was construed as a demand guarantee even though it con­ tained a provision that the issuer’s liability would not be affected by any variation of the

183Art. l.a.

184Art. 5.a.

185In UzinterimpexJSC v. Standard Bank Pic [2007] EWHC 1151, where the guarantee was subject to the URDG 458 it was common ground that it was an independent guarantee rather than a suretyship guarantee.

186[1996] 1 AC 199.

187Ibid., at 207.

188Ibid., at 205.

189Contra. WoodHallLtd v. The PipelineAuthority (1979) 141 CLR443, 445, where BarwickC.J. saidofa similar clause in a guarantee, that it had been ‘sensibly included as a precaution’ and therefore it did not indicate that the parties intended the issuer’s obligation to be secondary.

190[2002] 1 All ER 142.

60

IV. Problems o f Categorization: D em and Guarantee or Suretyship Guarantee?

 

underlying contract. Tuckey L J. said that there might have been a good reason for including

 

such a provision in an instrument intended to take effect as a demand guarantee.191 However,

 

the decision was based on the ground that although the clause excluding discharge for

 

variation of the underlying contract was an indication that the instrument was a suretyship

 

guarantee, on balance, there were more indications from other terms of the instrument

 

pointing in the opposite direction. More recently, a similar view was adopted in IIG Capital

 

LLC v. Van DerMerwe™2where Waller L.J. said that a clause in the guarantee in that case to

 

the effect that any variation of the underlying contract shall not affect the issuer’s obligation

 

would only be necessary if the issuer was or might be undertaking a secondary liability and

 

accepted that the clause pointed in favour of the view that the instrument did not create a

 

primary liability.193 However, as there were other terms, including a conclusive evidence

 

clause, pointing in the opposite direction, it was held that the issuers’ liability was in fact

 

primary and independent.

 

J. Undertaking to pay ‘damages’

 

A term in an instrument stating that upon a default by the account party the issuer shall

3

satisfy or discharge the ‘damages sustained by’ the beneficiary, is likely to be regarded as

 

indicating that the issuer’s liability is secondary and dependent on the position as between

 

the parties to the underlying contract. The reason is because the word ‘damages’ is seen as

 

defining the issuer’s obligation not just by reference to the loss which the beneficiary has

 

suffered as a result of the account party’s breach but also by reference to any sums which

 

would normally be set against it in an action for damages against the account party. In

 

Trafalgar House Constructions (Regions) Ltd v. General Surety & Guarantee Co.)94 the issuer

 

undertook to pay the beneficiary a certain amount. A condition of the instrument was that:

 

‘if on default by the [account party] the surety shall satisfy and discharge the damages sus­

 

tained by the [beneficiary] thereby up to the amount [specified in the instrument] then this

 

obligation shall be null and void’. The House of Lords rejected a contention that the words

 

‘damages sustained’ defined the obligation of the issuer solely by reference to the amount of

 

the beneficiary’s loss without reference to any sums which would normally be set against it in

 

an action for damages against the account party. Lord Jauncey said that ‘the use of the word

 

“damages” is far more consistent with the compensation arrived at after taking into account

 

all sums due to or by the account party’.195 He said that if the parties had intended to produce

 

the result contended for it would have been easy for them to use a suitable form of words.

 

However, an undertaking is not necessarily a secondary obligation simply because it is

3

to pay ‘damages’. Where, for example, an issuer undertakes to pay unconditionally and

 

on demand ‘damages which you claim are owing to you’ by the account party under the

 

underlying contract, it may be construed as only requiring the beneficiary to include in his demand for payment a statement that his claim is for damages brought about by the account

191At [25]: ‘It might, for example, have been included to avoid argument that variation of the shipbuilding contract by, for example, postponing a stage payment or remitting part of it in settlement of any cross-claim would imperil recovery under the refund guarantees. It could have been inserted simply to ensure that the rule applicable to true guarantees did not apply to this instrument.’

192[2008] EWCA Civ 542.

193Ibid., at [30].

194[1996] 1 AC 199.

195Ibid., at 208. Therefore claims by the account party against the beneficiary for unpaid sums had to be

taken into account in determining the extent of the issuer’s liability under the instrument.