Project implementation plan

Implementation schedule project

Description of the stages

Start

Completion

Obtaining a grant

07.2016.

08.2016.

Order and delivery of parts

08.2016.

09.2016.

Preparation of the test sample

09.2016.

10.2016.

Presentation of working models

10.2016.

11.2016

Organization of serial production

12.2016

01.2017

Description of the stages of the project

After a positive decision on the implementation of this project, which will take place after the decision to grant extradition, the project will begin. The project will consist of the steps: Order, manufacturing and producing components for the assembly of working models. Assembling, testing and certification work samples. Presentation of existing models will take place in exhibitions in the region and the country to form a positive feedback on alternative energy in Kazakhstan. Further possible elaboration of a feasibility study to address the question of mass production models to consumers. Organization of industrial production Solar Wind Tree available from June 2016.

13

Sole trader «Nuredinov» Solar Wind Tree.

Description of resource requirements

Analysis of location and infrastructure

Because in our region alternative energy is not widely used, we will need to cooperate with manufacturers and experts in this field at the international level. To implement the project at this stage will be used resources of functioning enterprises and design bureaus on alternative energy.

List of the acquired assets

Purpose of investment

Sum $ USD

The total cost of the project

$3 000 000

Total

$3 000 000

Within the project the following assets to be acquired: components and parts for the assembly of existing models of wind and solar power generator, delivery and final assembly functioning samples totaling $3 000 000. Also, the project is planned in the amount of $1000 for promotion of the project that includes the participation in exhibitions and obtain a patent. The total investment in the project is $3 000 000.

The need for personnel

Since at this stage of the project is not commercial, then bring to a permanent job in the project staff is required. All work will be carried out by specialists in this field.

The need for personnel

The organizational structure of our company allows the director to efficiently manage your business, and be informed. To implement the project the following staff should be hired :. Engineer, mechanics, electrician, assembler, installer, designer, technical staff. In the hands of her entire head of the laboratory will focus tactical and methodical work, and it will monitor the level of experts and high-quality production figures. In its submission to production are all professionals. The Director will provide overall guidance.

Staff

State

Salary

Sum

Electrical Engineer

2

$500

$1000

Energy Engineer

2

$500

$1000

Interpreter

2

$450

$900

Designer

2

$400

$800

Janitor

2

$150

$300

Assembling mounter

6

$300

$1200

Welder

2

$400

$800

 Technical staff

 2

 $150

 $300

 Turner

 2

$400

 $800

In total

 

 $7 700

Sole trader «Nuredinov» Solar Wind Tree. 14

The salary taken into account the necessary social security payments and taxes stipulated by the legislation.