Developing Projects

Create relationships in the Activity Network

1)Move the mouse pointer to the edge of the predecessor activity box until it turns into a relationship pointer (a vertical single-ended arrow).

2)Click and hold the mouse button while dragging to the successor activity box. Release the mouse button.

If you draw from the right edge of the predecessor to the left edge of the successor, you create a finish to start relationship.

If you draw from the right edge of the predecessor to the right edge of the successor, you create a finish to finish relationship.

If you draw from the left edge of the predecessor to the right edge of the successor, you create a start to finish relationship.

If you draw from the left edge of the predecessor to the left edge of the successor, you create a start to start relationship.

Tip

A hint help window appears while you are dragging the relationship line between two activities to tell you what kind of relationship will be created when you release the mouse.

You can add comments about the relationship in the Relationships, Predecessors, or Successors tabs in Activity Details.

Viewing activity relationships

View activity relationships in Activity Details

Activity Details list the selected activity's relationships and details, such as activity type, in different tabs.

1)Select the activity whose relationships you want to view.

2)Click the Layout Options bar, then choose Show on Bottom, Activity Details.

3)To view the selected activity's predecessors, click the Predecessors or Relationships tab.

4)To view the selected activity's successors, click the Successors or Relationships tab.

Tips

If the Predecessors, Successors, or Relationships tab is not displayed, click the Layout Options bar, then choose Bottom Layout Options and add the missing tab to the Display Tabs column list.

To change the displayed columns within each tab, right-click anywhere in the tab, then choose Customize Predecessor Columns or Customize Successor Columns.

121

P6 Professional User Guide

View activity relationships in the Gantt Chart

The Gantt Chart displays a graphical view of all activity relationships for a specific activity filter.

Click the Layout Options bar, then choose Show on Top, Gantt Chart. If no relationship lines are displayed for activity dependencies you have defined, change the Gantt Chart bar options to show relationship lines or click on the Top Layout toolbar.

A line connecting two activity bars indicates an activity relationship. The point at which the line begins on the predecessor bar and the point at which the line ends on the successor bar indicates the type of activity relationship the line represents.

A finish to start relationship line begins on the right side of the predecessor activity’s bar and ends on the left side of the successor activity’s bar.

A finish to finish relationship line begins on the right side of the predecessor activity’s bar and ends on the right side of the successor activity’s bar.

A start to finish relationship line begins on the left side of the predecessor activity’s bar and ends on the right side of the successor activity’s bar.

A start to start relationship line begins on the left side of the predecessor activity’s bar and ends on the left side of the successor activity’s bar.

View activity relationships in the Activity Network

The Activity Network displays a graphical view of all activity relationships for a specific activity filter.

In the hierarchy table on the left side of the Activity Network, select the hierarchy element whose activity relationships you want to view. The Activity Network table displays the selected hierarchy element's activities. A line connecting two activity boxes indicates an activity relationship. The point at which the line begins on the predecessor box and the point at which the line ends on the successor box indicates the type of the activity relationship.

A finish to start relationship line begins on the right side of the predecessor's box and ends on the left side of the successor's box.

A finish to finish relationship line begins on the right side of the predecessor’s box and ends on the right side of the successor’s box.

A start to finish relationship line begins on the left side of the predecessor’s box and ends on the right side of the successor’s box.

A start to start relationship line begins on the left side of the predecessor’s box and ends on the left side of the successor’s box.