Working with the EPS

 

In This Section

 

Managing projects using the EPS............................................................................

97

Defining project details ............................................................................................

97

Enter project dates ..................................................................................................

97

Specify a fiscal start month......................................................................................

97

Set project resource options....................................................................................

98

Change a project name ...........................................................................................

98

Change a project ID ................................................................................................

98

Change the project leveling priority .........................................................................

98

Change a project's status ........................................................................................

98

Managing projects using the EPS

The enterprise project structure (EPS) organizes and summarizes all projects within the enterprise hierarchically for top-down budgeting, resource and cost analysis, and global control of data. An enterprise structure enables you to manage multiple projects from the highest levels of the organization to the individuals that perform specific project tasks. You can also use the EPS to define project properties, including dates, budgets, codes, resources, and project defaults.

Defining project details

Use the Project Details tabs in the bottom portion of the Projects window to define project properties and defaults used throughout a project. You can also assign some general properties to the EPS nodes in your hierarchy. Display Details by clicking the Display Options bar and selecting Show on Bottom, Project Details, so that the checkmark appears.

Open each tab to view and edit the selected project’s information. The details include schedule information, project codes, summarization information, default settings such as duration type for new activities, and activity numbering increments.

Enter project dates

1)Choose Enterprise, Projects and display Project Details.

2)Click the Dates tab.

3)Enter planned, anticipated, or actual dates for the project.

Specify a fiscal start month

1)Choose Enterprise, Projects and display Project Details.

2)Click the Settings tab.

97

P6 Professional User Guide

3) Select the month on which the first day of the fiscal year begins.

Set project resource options

Choose Enterprise, Projects and display Project Details, then click the Resources tab.

Change a project name

1)Choose Enterprise, Projects and display Project Details.

2)Select the project whose name you want to change.

3)Click the General tab, then type a new project name.

Change a project ID

1)Choose Enterprise, Projects and display Project Details.

2)Select the project whose ID you want to change.

3)Click the General tab, then type a new project ID.

Change the project leveling priority

1)Choose Enterprise, Projects and display Project Details.

2)Click the General tab, then select a leveling priority from 1 (highest priority) to 100 (lowest priority).

During leveling, this number determines which assignments from other projects to consider within the leveling run. For example, if you specify 5 in the Consider Assignments in Other Projects With Priority Equal/Higher Than field of the Level Resources dialog box, all projects with a project leveling priority of 1, 2, 3, 4, and 5 are considered.

Note

If you are selecting a priority level for an EPS node or project, your selection may affect the order in which the project's activities are leveled. If you level a project according to project priority, all activities in the higher priority project are leveled, and then activities in the lower priority project are leveled.

Tips

You can include assignments from closed projects during leveling by marking the Consider Assignments in Other Projects With Priority Equal/Higher Than checkbox of the Level Resources dialog box. Indicate a Project Leveling Priority for those projects on the General tab in the Projects window.

To use the priority level as a tie breaker during leveling, include Project Leveling Priority under Leveling Priorities in the Level Resources dialog box.

Change a project's status

1) Choose Enterprise, Projects and display Project Details.

98

Working with the EPS

2)Select the project whose status you want to change, then select the project status you want to use for the current project.

This selection affects data access as follows:

Status

Impact

 

 

Planned

Sets all project WBSs to Planned.

 

 

Active

Sets all project WBSs to Active.

 

 

Inactive

Sets all project WBSs to Inactive.

 

 

What-If

Sets all project WBSs to What-If.

 

Project is included when summarizing.

 

Project is ignored by resource profile/spreadsheet and leveling.

 

 

Note

The Status field applies to projects only, not EPS nodes.

99