Добавил:
Опубликованный материал нарушает ваши авторские права? Сообщите нам.
Вуз: Предмет: Файл:
reading / Primavera P6™ Project.pdf
Скачиваний:
0
Добавлен:
12.06.2025
Размер:
10.82 Mб
Скачать

Project Issues and Thresholds 353

Threshold Parameter Definitions

A threshold consists of a parameter, or type, and a lower and/or upper threshold value. The module generates an issue automatically when a threshold parameter is below or equal to the lower threshold or equal to or above the upper threshold value.

The following paragraphs define the available threshold parameters.

Accounting Variance (AV) An Accounting Variance (AV) threshold value is expressed as a monetary value. An issue is generated if the Accounting Variance (the difference between the activity’s budgeted cost according to the schedule and the actual cost of performing the activity) falls beyond the threshold values.

Accounting Variance is computed as AV = Planned Value Cost – Actual

Cost.

A negative value indicates that actual costs have exceeded the scheduled costs. A positive value indicates that actuals costs have not reached the scheduled costs.

If the lower threshold value is zero, an issue is generated as soon as actual costs are greater than scheduled costs.

Cost % of Budget Cost % of Budget threshold values are expressed as a percentage. An issue is generated if the ratio of the activity’s actual cost to its budgeted cost (actual cost / budgeted cost * 100) falls beyond the threshold values.

Actual cost is the same as Actual Cost, and budgeted cost is the same as

Budget at Completion (BAC).

The Cost % of Budget will reach 100 percent when the actual cost reaches the budgeted cost. The Cost % of Budget may be greater than 100 percent.

CPI – Cost Performance Index A Cost Performance Index (CPI) threshold value is expressed as a ratio. An issue is generated if the CPI falls beyond the threshold values.

The Cost Performance Index is computed as CPI = Earned Value Cost / Actual Cost. A value less than one indicates that actual costs have exceeded the value of work performed.

Primavera - Project Management

354 Part 4: Updating and Managing the Schedule

If the lower threshold value is one, an issue is generated whenever the actual costs exceed the value of the work performed.

Cost Variance (CV) A Cost Variance (CV) threshold value is expressed as a monetary value. An issue is generated if the CV (the difference between the activity’s earned value and the actual cost of performing the activity) falls beyond the threshold values.

Cost Variance is computed as CV = Earned Value Cost – Actual Cost. A negative value indicates that actual costs have exceeded the value of work performed, which may be considered a cost overrun.

If the lower threshold value is zero, an issue is generated as soon as actual cost of the work is greater than the value of the work. A larger negative value for the threshold indicates that a certain amount of cost overrun may be tolerated before an issue is generated.

Cost Variance Index (CVI) A Cost Variance Index (CVI) threshold value is expressed as a ratio. An issue is generated if the CVI (the ratio of the cost variance to the earned value of work performed) falls beyond the threshold values.

The Cost Variance Index is computed as CVI = Cost Variance (CV) / Earned Value Cost.

A value less than zero indicates that actual costs have exceeded the value of work performed.

If the lower threshold value is zero, an issue is generated whenever the actual costs exceed the value of the work performed.

Duration % of Original A Duration % of original threshold value is expressed as a percentage. An issue is generated if the ratio of the activity’s actual duration to its original duration (actual duration / original duration * 100) falls beyond the threshold values.

The ratio of actual duration to original duration may be greater than 100.

Finish Date Variance A Finish Date Variance threshold value is a specified number of days. An issue is generated if the difference between the activity’s planned and current finish date (calculated as Planned Finish Date – Finish Date) falls beyond the threshold values.

If an activity’s status is Not Started or Active, then the Finish date will be the Planned Finish date, and the finish date variance is always zero. If an activity’s status is Completed, then Finish date is the actual finish date.

Primavera - Project Management

Project Issues and Thresholds 355

A negative value for Finish Date Variance indicates that the current finish date is later than the planned finish date.

Free Float A Free Float threshold value is a specified number of days. An issue is generated if an activity’s free float (the amount of time the activity can be delayed without delaying the Early Start of any successor activity) falls beyond the threshold values.

Free Float threshold monitoring can only be applied at the activity level, not at the WBS level.

Schedule Performance Index (SPI) A Schedule Performance Index (SPI) threshold value is expressed as a ratio. An issue is generated if the Schedule Performance Index (the ratio of the earned value of work performed to the budgeted cost of work that was scheduled) falls beyond the threshold values.

The Schedule Performance Index is computed as SPI = Earned Value Cost / Planned Value Cost. A value less than one indicates that less work was actually performed than was scheduled.

If the threshold value is one, an issue is generated whenever the value of the work performed falls below the expected cost of performing that work, according to the schedule.

Start Date Variance A Start Date Variance threshold value is a specified number of days. An issue is generated if the difference between the activity’s planned and current start dates (calculated as Planned Start Date – Start Date) falls beyond the threshold values.

If an activity’s status is Not Started, then the Start date will be the Planned Start date, and the start date variance is always zero. If an activity’s status is Started or Completed, then Start date is the actual start date.

Schedule Variance (SV) A Schedule Variance (SV) threshold value is expressed as a monetary value. An issue is generated if the Schedule Variance (the difference between the activity’s earned value and the planned value) falls beyond the threshold values.

Schedule Variance is computed as SV = Earned Value Cost – Planned Value Cost. A negative value indicates that less work was actually performed than was scheduled. The activity may be considered behind schedule.

Primavera - Project Management

356 Part 4: Updating and Managing the Schedule

If the threshold value is zero, an issue is generated as soon as the earned value of the work performed falls below the amount of work that was supposed to be performed, according to the schedule. A larger negative value for a Schedule Variance threshold indicates that an activity may be behind schedule by that amount before an issue is generated.

Schedule Variance Index (SVI) A Schedule Variance Index (SVI) threshold value is expressed as a ratio. An issue is generated if the Schedule Variance Index (the ratio of the schedule variance to the planned value) falls beyond the threshold values.

The Schedule Variance Index is computed as SVI = Schedule Variance (SV) / Planned Value Cost. A value less than zero indicates that the value of the work performed is less than what was scheduled.

If the threshold value is zero, an issue is generated whenever the value of the work performed falls below the expected cost of performing that work, according to the schedule.

Total Float A Total Float threshold value is a specified number of days. An issue is generated if an activity’s total float (the amount of time the activity can be delayed without delaying the project finish date) falls beyond the threshold values.

Variance at Completion (VAC) A Variance at Completion (VAC) threshold value is expressed as a monetary value. An issue is generated if the Variance At Completion (the budgeted total cost – latest total cost estimate) falls beyond the threshold values.

Variance At Completion may also be expressed as VAC = Budget at Completion (BAC) – Estimate At Completion (EAC).

A negative value indicates an estimated total cost overrun. If the threshold value is zero, an issue is generated as soon as the latest estimate for total cost exceeds the planned total cost. A larger negative value for a Variance At Completion threshold indicates that a certain amount of estimated total cost overrun may be tolerated before an issue is generated.

Primavera - Project Management