Managing Risks 339

Calculating a Risk’s Impact

The module uses the top-down estimation method to apply a risk’s exposure values and calculate impact on a project’s schedule, cost, and duration. The module applies these values to activities that finish on or after the risk’s impact date. This does not include completed, locked, or milestone activities.

When applying exposure values, the module uses any WBS elements and activities the WBS contains, along with resource assignments and information (such as price and availability), then schedules the project according to your current scheduling preferences.

You must first determine a risk’s exposure values on the Impact tab before calculating a risk’s impact.

Calculate a risk’s impact Schedule the project whose risk impact you want to calculate, then choose Project, Risks. Select the risk whose impact you want to calculate. Click Calc Impact in the command bar. The module applies any resource units, then schedules the project using the current scheduling options.

Use this dialog box to view the

 

The number of activities the risk will

 

selected risk’s effect on the

 

affect. This is not the total number of

project’s schedule cost and

 

activities contained in the WBS element.

duration.

 

 

 

 

 

Primavera - Project Management

340 Part 4: Updating and Managing the Schedule

Creating and Deleting Risk Types

You can create risk types, or categories of possible risks, that you can assign to risks in any project. You can use risk types to classify and standardize risks for all projects.

Add a new risk type Choose Admin, Admin Categories. Click the

Risk Types tab, then click Add. Type the name of the new risk type.

To move a risk type up or down in the list, select it, then click Shift Up or Shift Down.

Delete a risk type Choose Admin, Admin Categories. Click the Risk

Types tab, then select a risk. Click Delete. Click Yes to delete it.

Primavera - Project Management

Managing Risks 341

Customizing Risk Layouts

Use the Columns dialog box to specify which columns you want to display in the current risk spreadsheet layout.

Customize risk layout columns In the Project Risks window, click the Display Options bar and choose Columns, Customize.

Double-arrow buttons add/remove all available

 

Click to change the column

 

columns in the current layout; single-arrow buttons

title of a selected item.

add/remove selected items in the current layout.

 

Modify the columns shown in the risk layout by clicking the right/left arrow buttons to move data items between the Available Options and Selected Options columns.

Items listed in the Selected Options column will appear in the current layout when you click OK. Click Apply to see your changes without closing the dialog box.

Filter, group, and sort risk layouts You can select the risks you want to view and specify how you want to display them, and you can restrict which risks you view. In the Project Risks window, click the Display Options bar. Choose Filter By or Group and Sort By and the option that best describes how you want to view risks.

Primavera - Project Management

342 Part 4: Updating and Managing the Schedule

This risk layout is grouped by WBS element and filtered by open risks for quick analysis.

Primavera - Project Management