302 Part 4: Updating and Managing the Schedule

For more information on the Project Details, Calculations tab, refer to the Help.

Removing Progress from Activities

You can remove progress from an activity by removing the Actual Start and/or Actual Finish from the activity. When the actual start or actual finish is removed from an activity, the activity’s budgeted units and its durations are recalculated. How the module calculates these changes is based on the project setting in the Project Details, Calculations Tab. Depending on the option selected, the module will either redistribute the remaining work on the activity by setting the original duration equal to the remaining duration, and setting the budgeted units equal to the remaining units; or, the module can distribute the original work by setting the remaining duration equal to the original duration, and setting the remaining units equal to the budgeted units.

If the Link Budget and At Completion for Not Started Activities checkbox is cleared in the Resource Assignments section in the Projects window, Calculations tab, only activity and assignment dates will be adjusted when progress is removed from an activity.

Choose to re-distribute the remaining work or the original work for activities, when progress is removed.