Updating, Scheduling, and Leveling 297

Updating Activities Manually

You can also manually update future period unit values for assignments to activities. For more information, refer to “Managing Resource Assignments” on page 323.

In addition to updating activities automatically or using timesheets, you can manually update data for each activity. Record actual dates, actual resource use, and costs incurred up to the data date or “time now.” There are different activity types, percent complete types, and duration types to accommodate your scheduling requirements. You should set these variables at the start of the project when you establish your update procedures.

For more information on defining activity and duration types, see “Working with Activities” on page 201.

Set percent complete type An activity’s percent complete can be calculated according to activity duration, activity units, or a physical percent complete that you enter for each activity. Choose Project, Activities, and display the Activity Details General tab or add a column for Percent Complete Type in the Activity Table.

You can add a column to review or modify the percent complete type.

Select the percent complete type for the activity.

Select the percent complete type based on how you report progress for the activity.

nSelect Physical Percent Complete when activity progress can most easily be reported based on personal judgment. Enter the activity percent complete.

nSelect Duration when activity progress can be easily reported in terms of actual calendar days of work remaining.

Primavera - Project Management

298 Part 4: Updating and Managing the Schedule

To update any other activity data, such as remaining duration or actual units, you must first enter an actual start date for the activity.

Duration % Cmp = [(Original Duration – Rem Duration) / Original Duration] x 100

nSelect Units when progress is best reported based on the work effort that has been accomplished and how much effort remains. Enter the actual and remaining units.

Units % Cmp = [Actual Units / At Completion Units] x 100

Update actual dates Once an activity is underway, update its start and finish dates and other status information. Choose Project, Activities and display the Activity Details Status tab. If the activity has actually started, mark the Started checkbox, then specify the actual start date in the Started field. If the activity is complete, mark the Finished checkbox, then specify the actual finish date in the Finished field.

Update activities with Duration percent complete type In the Activities window, select the activity to update and display the Activity Details Status tab. In the Remaining field, type the remaining number of workperiods needed to complete the selected activity. When you schedule or apply actuals, the actual duration is calculated as the total working time from the actual start date to the current data date (for in-progress activities) or to the actual finish date (for completed activities), using the activity’s calendar.

If resources are assigned to the activity, each resource’s remaining units are calculated as the activity’s remaining duration multiplied by its remaining units per time.

Type a new remaining duration for the activity.

Update activities with Physical percent complete type In the Activities window, select the activity to update and display the Activity Details Status tab. Enter the physical percent complete and the remaining duration for the activity. If resources are assigned, you must also update each resource’s actual regular units.

Primavera - Project Management

Updating, Scheduling, and Leveling 299

Type the percent complete for the activity when the percent complete type is Physical.

The module calculates the actual duration

 

 

 

Type a new remaining duration for the activity.

 

 

 

 

 

 

for the activity when you apply actuals or

 

 

schedule the project.

 

 

Actual Regular Units for a resource indicate the actual amounts without considering overtime units. Actual Units include Actual Regular Units plus Actual Overtime Units.

Update activities with Units percent complete type If you are updating activities with the Units percent complete type, most likely your focus is on resource planning and scheduling. (You may also have specified the activity type as Resource Dependent and the Duration type as Fixed Units/Time.) You should update the labor units (and/or nonlabor units) for the activity, rather than the duration. If multiple resources are assigned to an activity, you should update each resource individually in the Resources tab. In the Activities window, select the activity to update and display the Activity Details Resources tab.

When you update activities manually, you should turn off Auto Compute Actuals settings; otherwise, your changes are overwritten when you apply actuals or calculate the schedule.

Primavera - Project Management

300 Part 4: Updating and Managing the Schedule

Update the actual regular units and the remaining units for each resource.

When you update units in the

 

The Labor Units amounts in the

 

Resources tab, the Started

Status tab total the amounts for all

checkbox in the Status tab is

resources assigned in the

automatically marked.

Resources tab.

 

 

 

The units % complete is calculated from

Primavera - Project Management

Updating, Scheduling, and Leveling 301

How Activity Duration, Units, and Resource

Units/Time Are Synchronized

The module automatically synchronizes the duration, labor/nonlabor units, and resource units/time for activities so that the following equation is always true for each activity: Duration = Units / (Resource Units/Time). Since three variables are involved (duration, units, and units/time), when you change the value of one variable, the module must alter the value of a second to balance the equation.

The Duration Type setting for an activity allows you to control how the module synchronizes these variables when any one of the equation’s variables are changed.

The following table lists the value that is automatically changed to synchronize these variables whenever the value of one of the duration type variables is changed.

 

When you

When you

When you

Activity

change units,

change the

change units/

duration type

this value

duration, this

time, this value

 

changes...

value changes... changes...

When you add

When you add

the first

additional

resource, this

resources, this

value changes...

value changes...

Fixed Units/

Duration

Units

Duration

Units

Duration

 

Time

 

 

 

 

 

 

Fixed Duration

Units/Time

Units

Units

Units

Units

 

& Units/Time

 

 

 

 

 

 

Fixed Units

Duration

Units/Time

Duration

Units

Duration

 

Fixed Duration

Units/Time

Units/Time

Units

Units

Units/Time of

 

& Units

 

 

 

 

each resource

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Primavera - Project Management