Working with Activities 201

Working with Activities

 

 

 

 

Activities are the fundamental work elements

 

In this chapter

of a project. They are the lowest level of a

 

Activities Overview

work breakdown structure (WBS) and, as such,

 

are the smallest subdivision of a project that

 

Adding Activities

 

directly concerns the module. If you divide

 

Defining General Activity Information

 

 

 

Defining Schedule Information

activities into steps, an activity’s primary

 

Establishing Relationships

resource is typically responsible for managing

 

Displaying Activity Details for Assign-

and tracking the progress of the steps, while

 

ments

the project manager is typically responsible for

 

Assigning Resources and Roles

 

managing and tracking the progress of the

 

Assigning Resource Curves to

 

 

 

Resource or Role Assignments

overall activity.

 

Manually Planning Future Period

 

 

Assignments

This chapter describes how to add activities

 

Assigning Activity Codes and Adding

and their properties.

 

Expenses

 

 

 

Viewing Activity Feedback and

 

 

Posting Resource Notes

 

 

Assigning Work Products and

 

 

Documents

 

 

Adding Steps

 

 

Creating and Assigning Activity Step

 

 

Templates

 

 

Viewing Activity Summaries

 

 

Viewing Contract Manager

 

 

Documents

 

 

Using Global Change

 

 

 

 

 

 

 

 

 

 

Primavera - Project Management

 

 

 

 

 

202 Part 3: Implementing the Schedule

Activities Overview

Activities represent work that must take place in a determined amount of time. Use the Activity Table or Activity Network layouts to add activities and build your projects. Within these layouts, you can define the following activity information:

Activity ID and name – to uniquely identify and describe the activity

Predecessor and successor relationships – to define relationships with other activities in the same project or in different projects in the enterprise project structure (EPS)

Activity start and finish dates

Activity calendar

Activity type, duration type, and percent complete type; whether an activity is a start or finish milestone; how to keep an activity’s unit values, duration values, and resource units/time values synchronized; and how to calculate an activity’s percent complete

WBS element

Activity codes and values – to categorize activities

Constraints on the activity’s scheduled start and finish dates

Expenses

Work products and documents, standards, and deliverables

Resources

Roles – to identify skill requirements for staffing the activity

Notes and feedback – to communicate with the resource working on an activity

Notes about performing the activity

Steps – to divide the activity into smaller units

Activity Step Templates – to define sets of reusable steps common to many activities in a project or across projects

Primavera - Project Management

Working with Activities 203

Adding Activities

Use the Activities window to create, view, and modify activities for the open project. The Activities window can be divided into upper and lower layouts. For example, show an Activity Table, Gantt Chart, Activity Usage Spreadsheet, or Activity Network in the top layout, and/or show Activity Details, an Activity Table, Gantt Chart, Activity or Resource Usage Spreadsheet or Profile, or Trace Logic in the bottom layout. Customize the layouts to suit your requirements.

Choose Project, Activities, to display the Activities window.

To open a layout, click the Layout Options bar and choose Show on Top/ Show on Bottom, then select the layout type.

To add an activity to a project, use the Activity Table and Gantt Chart, or Activity Network. Depending on your user preferences, the New Activity wizard may start to help you add an activity.

Add activities in the Activity Table Select an activity within the group to which you want to add a new activity, then click Add. The new activity is placed according to the sorting options selected for the layout.

Primavera - Project Management

204 Part 3: Implementing the Schedule

Include the Gantt Chart to see a timescaled version of your schedule as you add activities.

Type information directly in the column cells for the new activity...

...or use Activity Details to complete activity information.

Add activities in Activity Network In Activity Network, select the group band or an activity box within the group band into which you want to add the new activity, then click Add.

The new activity was added to this second-level WBS group band.

If no groups have been set up in Activity Network, the activity will be added to the bottom of the layout.