164 Part 2: Structuring Projects

Tracking and Analyzing Budgets

The resource and cost spreadsheets provide an overall picture of unit and cost budget distributions, along with the variance amounts resulting from current use versus original estimates at the activity level. At the EPS level, you can customize columns and produce reports to display original budget amounts per project, along with the current variance amounts. This is beneficial in the early stages of your projects when you may not have all resources and estimates in place to cover the scope and goals set forth by upper management.

Create a layout for budget and variance comparison Open the Projects window, then click the Display Options bar and choose Columns, Customize. You can select any budget-related columns from the list of choices. The following example compares the original budget amounts assigned to the projects and the current variance resulting from budget spending on those projects to date.

For information about assigning and analyzing budgets at the WBS, activity, and cost account levels, see “Reviewing Work Breakdown Structures” on page 133, “Working with Activities” on page 201, and “Working with Cost Accounts and Project Expenses” on page 247, respectively.

For information about running reports, see “Printing Layouts and Reports” on page 491.

When current spending differs from original budget estimates, a variance results. A variance amount shown in parentheses indicates a negative variance amount for the project.