138 Part 2: Structuring Projects

Grouping by WBS Path

You can organize multiple projects that use the same work breakdown structure (WBS) by grouping their identical WBS levels. The WBS path lists activities grouped by WBS levels, without displaying the project level node. Group by WBS path in the Activities and WBS windows. You can also filter or display the WBS path as a column in projects and reports. Further organize a layout by sorting to arrange the order of activities. If you use both grouping and sorting to organize a layout, the items are grouped first, then sorted.

Organize multiple projects that follow the same work breakdown structure path.

Group activities by WBS path Choose Project, Activities, then choose View, Group and Sort. In the Group By section, click the cell, then select WBS Path. Click Sort, then select a sort order for the WBS path. Click OK. Click Sort, then select a sort order for the WBS path. Click OK.

To view the WBS path in the WBS window, choose Project,

WBS, then View, Group and Sort by, WBS Path.