Setting Up the Enterprise Project Structure 89

Defining Enterprise Project Structure Details

Define project details and defaults used throughout a project using the Project Details tabs in the bottom portion of the Projects window. You can also define information specific to the EPS nodes in your hierarchy. To display Project Details, click the Display Options bar, then choose Show on Bottom, Project Details (the box next to Project Details should be marked).

Make sure Project Details are displayed so you can define properties.

To include/exclude tabs, right-click in the Details area, and choose Customize Project Details.

Open each tab to view and edit that type of information for the selected node or project.

Primavera - Project Management

90 Part 2: Structuring Projects

For details about the Budget Log, Spending Plan, Budget Summary, and Funding tabs, see “Defining Budgets” on page 151.

General information The General tab enables you to view and edit general information about the selected node or project. This information includes the ID, name, responsible manager, leveling priority, and risk level. You can also view or edit the project’s Web site address, if applicable.

Use status to identify active (Active) or (Inactive) projects. You can also select status for analysis before establishing permanent project schedule, or Planned for use during the project planning

The node’s/project’s assigned organizational breakdown structure (OBS) element. The Responsible Manager is a mandatory assignment for each level of the EPS.

The name of the user and the

 

The overall risk in performing the node/

 

 

 

Use this value to

 

 

 

 

 

 

 

 

date and time the user checked

 

project. Use the risk level to organize,

 

 

 

consider applicable

out the project. This field is blank

 

filter, and report project information.

 

 

 

external projects

when the Check Out Status is

 

 

 

 

 

(those not included in

Checked In.

 

 

 

 

 

the current window)

 

 

 

 

 

 

when deducting from

 

 

 

 

 

 

resource availability

 

 

 

 

 

 

immediately during

 

 

 

 

 

 

leveling.

Leveling Priority

You can include assignments from closed projects during leveling. Mark the Consider Assignments in Other Projects with Priority Equal/Higher Than checkbox in the Level Resources dialog box and indicate a Project Leveling Priority for those projects on the General tab in the Projects window. You can enter a value from 1 to 100, with 1 being the highest priority. To use the priority level as a tie breaker during leveling, include Project Leveling Priority under Leveling Priorities in the Level Resources dialog box.

Primavera - Project Management

Setting Up the Enterprise Project Structure 91

Dates The Dates tab enables you to edit schedule information for the selected project. This information includes the current data date, planned start date, and the scheduled finish date. If you have an EPS node selected, you can also enter the dates you anticipate the node will start and finish.

The latest early finish date calculated when the project was last scheduled

The start date of the project

The date used as the starting point to calculate the schedule

A date constraint placed on the project end date

The user-defined date the project is expected to start or finish

The actual finish date of the project, if the project has finished—all activities in the project have actual finish dates.

Anticipated Dates

Anticipated start and finish dates are used during the project planning stage, and can be set at the EPS, project, or WBS level. If the selected project has no activities, or the activities have not started, the Start date or Finish date (in columns) is set equal to the Anticipated Start or Anticipated Finish. Click the Browse button to select a new date.

Primavera - Project Management

92 Part 2: Structuring Projects

Notebook The Notebook tab enables you to assign notebook topics and details to the selected node or project. These topics are defined in the Notebook Topics tab of the Admin Categories dialog box.

Click to add a topic,

 

 

 

 

 

 

 

select a topic in the

 

 

 

 

 

 

 

Assign Notebook Topic

 

 

 

 

 

 

 

 

 

 

 

 

 

 

dialog box, then click

 

 

 

 

 

 

 

Assign.

 

 

 

 

Click in this area to type a

 

 

 

 

 

 

 

 

description of the selected topic.

 

 

 

 

 

 

 

 

 

 

 

 

 

For free-form, user-defined details, you can use HTML editing

 

 

 

 

 

 

 

 

 

 

features, which include formatting text, inserting pictures,

 

 

 

 

 

 

 

 

 

 

copying and pasting information from other document files

 

 

 

 

 

(while retaining formatting), and adding hyperlinks.

 

 

 

 

 

 

 

 

Project codes The Codes tab enables you to assign project code values to the selected project. You must first add project codes and values (choose Enterprise, Project Codes).

To sort the display, click the applicable column label.

Primavera - Project Management