Working with Layouts 407

Working with Layouts

In this chapter

Layout Types

Creating, Opening, and Saving

Layouts

Exporting and Importing Layouts

Copying and Pasting Resource Spreadsheet Data to Microsoft Excel

You can create layouts that display the data you need to see, in the format you need to see them. Customize the top and bottom areas of the layout to include tables, graphs, charts, Activity or Project Details, and more. Once you are satisfied with your layout, you can save it so you or other team members can use it again.

This chapter describes the different layout types and explains how to create, open, save, export, and import layouts.

Primavera - Project Management

408 Part 5: Customizing Projects

Layout Types

You can open WBS, projects, and resource assignment layouts, and the following types of activity layouts: Activity Tables, Activity and Resource Usage Spreadsheets and Profiles, Gantt Charts, Activity Networks, Activity Details, and Trace Logic. Split the Activities window into top and bottom panes to display different types of layouts at the same time. For example, show an Activity Table in the top pane and a Resource Usage Profile in the bottom pane.

Click the Layout Options bar to display a menu of options that you can use to customize the top and bottom panes of the Activities window.

Click Show on Top and Show on Bottom to select the layout type displayed in each area of the Activities window.

For additional information

Refer to the following examples:

about layout types and

 

examples of sample layouts,

 

see “Quick Tour” on page 13.

 

Primavera - Project Management

Working with Layouts 409

Click the Show/Hide Bottom Layout button to display the top layout in an expanded view.

Activity Table

Displays activity information in spreadsheet format. Use this type of layout to quickly update a project.

You can use filters and data grouping to see only those activities that occur in your current status cycle.

Activity Usage

Spreadsheet

Displays units, costs, or earned value data by activity over time. Use this type of layout to review per period and rolled up activity resource/cost data.

Primavera - Project Management

410 Part 5: Customizing Projects

Click the Relationship Lines button to view relationships in the Gantt Chart.

To quickly zoom in on an Activity Network box, hold down the Alt key, then click and drag your mouse in the Activity Network section.

Gantt Chart

Provides a graphical display of activity progress over the course of the project. Use this layout to review or analyze the schedule.

Activity Network

Provides a graphical display of activities, including logical relationships. Activity Network can be displayed in the top layout only. The left side of this example displays the WBS hierarchy, while the right side shows the activity flow in graphical format. Use this layout to change the sequence of activities as your project evolves.

Primavera - Project Management

Working with Layouts 411

Activity Details

Displays and enables you to modify detailed information for an activity you select in either the Activity Table or Activity Network. This type of layout can be displayed in the bottom layout only. Use this layout type to add and update activities.

To show or hide any of the Detail tabs, right-click on a tab title and choose Customize Activity Details.

Activity Usage Profile

Displays a time distribution of activity units and costs in a Bar Chart format. This profile can be displayed in the bottom layout only. Use this layout type to review the labor use for activities in a specific timeperiod.

You can display usage for all activities, or choose Selected Activities to display usage for only the highlighted activities.

Primavera - Project Management

412 Part 5: Customizing Projects

Resource Usage Spreadsheet

Displays resource data in spreadsheet format. This spreadsheet can be displayed in the bottom layout only. Use this layout type to view resource allocation over time, according to a timescale you specify.

You can display activities by selected resource or assignment.

Resource Usage Profile

Displays a time distribution of resource units and costs in relation to activities in a Bar Chart format. This profile can be displayed in the bottom layout only. Use this layout type to analyze resource levels with the schedule.

To display a pop-up box containing totals for a specific month, double-click that month’s bar in the graph.

You can also display the profile as a histogram using different colors and patterns for multiple resources. Click the Display Options Bar and choose Stacked Histogram.

Primavera - Project Management

Working with Layouts 413

Trace Logic

Provides a graphical display of dependency relationships for an activity you select in either the Activity Table or Activity Network. Trace Logic can be displayed in the bottom layout only. Use this layout type to easily move forward and backward through the plan to view the critical path.

To quickly zoom in on a box, hold down the Alt key, then click and drag your mouse in the Trace Logic layout.