Добавил:
Upload Опубликованный материал нарушает ваши авторские права? Сообщите нам.
Вуз: Предмет: Файл:
I&C Safety Guide DRAFT 20110803.doc
Скачиваний:
13
Добавлен:
01.02.2015
Размер:
720.38 Кб
Скачать

6.58. The I&c architecture should be designed to fully satisfy the system requirements, including system interfaces and non-functional requirements (e.G., performance and reliability).

6.59. The design should be analyzed to ensure that requirements not essential for the functions important to safety do not impact these functions (see paragraph 6.41).

6.60. Design the overall I&C architecture is covered by the discussion of system architecture in chapter 4.

6.61. The HMI design of an I&C system should be justified by analyses with considerations for:

  1. Defining information needs (including considerations for defining a subset of indications and controls required to address accident and post accident conditions);

  2. Defining control needs and allocation;

  3. Including human error in safety analysis (i.e. Human Reliability Analysis);

  4. Defining user roles and responsibilities and other staffing requirements; and

  5. Task process, time constraints, flow of staff and information through analyses (i.e. task analysis).

6.62. The considerations in paragraph 6.62 are normally activities of the Human Factors Engineering life cycle. The output of these activities are inputs to the I&C life cycles as illustrated in Figure 2.

I&C system integration plan:

6.63. A documented traceability analysis should demonstrate that the system integration plan is complete with respect to the system design specification.

6.64. In particular, the traceability analysis should document that system integration activities cover: the full ranges of inputs and outputs (including out-of-range values for interface signals), exceptions handling, timing related requirements, and robustness tests to demonstrate that the system responds safely to all possible interface and load conditions.

6.65. The system integration plan should be verified to check that all integration interfaces (such as hardware–software or software module to module) will be challenged.

Detailed system design and implementation

6.66. Requirements should be met by the detailed system design.

System integration

6.67. System integration should check and document that the interface requirements between the various components of the system are satisfied, and that the components and subsystems operate as designed in the integrated system to enable the system to meet its specified requirements.

6.68. This is essentially a clear-box process (i.e., undertaken with an understanding of the structure and behaviour of the system and components).

6.69. Integration testing should be performed according to the provisions of a system integration plan.

6.70. Only the current version of verified modules (hardware and software) should be submitted to system integration.

6.71. It is advisable to use software tools to control issue of modules for assembly into system components and to control the build used for validation and for on-site use in operation so that traceability can be established between installed components and validated components.

6.72. For safety systems, the team designing and undertaking the system integration tests should be independent of the designers and developers.

6.73. Technical communication between the test team and the designers should be recorded.

6.74. All changes to approved test procedures should be recorded and subjected to re-approval.

System validation

6.75. Validation should demonstrate and document that the I&C system complies with its functional and non-functional requirements.

6.76. This is essentially a black-box process (i.e., undertaken solely on the basis of the system’s external behaviour).

6.77. Validation testing should be performed according to the provisions of a system validation plan.

6.78. Test documentation should be sufficient to enable the testing process to be repeated with confidence of achieving the same results.

6.79. The system operation and maintenance manuals should be validated, as far as possible, in this phase.

6.80. The system subjected to validation testing should be fully representative of the final configuration of the I&C system at the site and the software of the system should be identical.

6.81. The team designing the system validation tests should be independent of the designers and developers.

6.82. Technical communication between the test team and the designers should be recorded.

6.83. All changes to approved test procedures should be recorded and subjected to re-approval.

Installation and commissioning

6.84. The I&C system should be installed in the plant in accordance with the approved design.

6.85. Commissioning should be performed in accordance with the guidance of IAEA NS-G-2.9, Ref. [22].

6.86. The following paragraphs discuss considerations in implementing the guidance of NS-G-2.9, Ref. [22] for I&C systems.

6.87. Commissioning should progressively integrate the I&C system with the other components and other plant items, and verify that they are in accordance with design assumptions and that they meet the performance criteria.

6.88. Testing within the plant environment is an important part of the commissioning.

6.89. In particular, modes of operation and interaction between the I&C system and the plant which could not be readily tested at the validation stage should be tested then.

6.90. Equipment receipt inspection, pre-commissioning, or commissioning tests should verify that the system has not suffered damage during transportation.

6.91. Commissioning should give particular attention to verification of external system interfaces and to the confirmation of correct performance with the interfacing equipment.

6.92. During the commissioning period software-based I&C systems should be operated for an extended time under operation, testing and maintenance conditions that are as representative of the in-service conditions as possible.

6.93. The validation of operation and maintenance manuals should be completed in this phase.

6.94. The team designing the commissioning tests should be independent of the designers of the I&C system and those who specified the I&C system functions and performance.

Operation

6.95. Maintenance and surveillance of I&C systems should be performed in accordance with the guidance of IAEA NS-G-2.6, Ref. [20].

6.96. NS-G-2.6, Ref. [20] provides guidance on planning, organisational aspects, and implementation of maintenance and surveillance, including calibration, of I&C systems.

6.97. The following paragraphs discuss considerations in implementing the guidance of NS-G-2.6, Ref [20] for I&C systems.

6.98. Modification of parameters that might require variation during the operation of the plant (such as trip settings and calibration constants) should be undertaken using facilities that have been shown to be fit for the purpose.

6.99. Human performance monitoring of the operation and maintenance of the I&C system should be performed to document operating experience that may identify modifications to be considered for implementation.

Modifications

6.100. Upgrade and modification of I&C systems should be performed in accordance with the guidance of IAEA NS-G-2.3, Ref. [18].

6.101. NS-G-2.3, Ref. [18] provides guidance on planning, organisational aspects, implementation, training, and documentation of plant modifications.

6.102. Development of the modification or upgrade of I&C systems should follow a defined life cycle.

6.103. The complexity of the life cycle process needed for modifications is related to the complexity and safety significance of the modification.

6.104. The life cycle for even the simplest changes should include at least the phases of the individual system life cycle shown in Figure 2.

6.105. For a simple change, many of these elements will be simple. Normally, such life cycles are defined in plant modification procedures. For modifications that involve changes to overall I&C system architecture or interactions between individual systems it will be necessary to also implement elements of the overall I&C system life cycle.

6.106. When an I&C system is modified or is part of an upgrade, the level of rigour applied in justifying and executing the change should be established based upon its role and function in ensuring the safety of the nuclear power plant, in association with the existing systems and any of them that will remain in operation after the work. This also applies to changes to software tools.

6.107. Change control procedures should be in place, including appropriate procedures and organizational structures for the review and approval of the safety aspects of the modification.

6.108. The design of I&C upgrades and modification should consider:

  1. The limitations due to the physical characteristics of the installed plant, which effectively restrict the design options for I&C systems;

  2. The possible need to maintain consistency between the design of replacement equipment and existing I&C equipment to, for example, reduce the complexity of the overall operator interface and maintenance tasks of the plant; and

  3. Practical considerations with respect to the equipment or technology commercially available when required by the project programme, and the prospects for securing support of such equipment and technology by manufactures or third parties for the installed life of the equipment.

Соседние файлы в предмете [НЕСОРТИРОВАННОЕ]