9.2 Budget and financial calculations

Budget and financial calculation consists of information and scope of work of the estimate (Table 9.2). Statement of scope of work is presented in Table. 9.1.

Table 9.2 - Estimates for linear structures FOCL

Name of work

Units of measurement

Quantity

Cost of unit, грн.

Total price,

грн.

1

2

3

4

5

6

Construction

Construction work at the suburban area

1

Development of trenches for laying cable by hand in soils

2 - 3 groups

100

3470

2

Development of trenches for laying cable excavator in soil 2 - 3 groups

100

5404

3

Development pits for socket manually in soil 2 - 3 groups

100

4773

4

Development pits for measurement instrumentation columns manually in soils

2 - 4 groups

100

5412

5

Filling trenches and pits by hand soil 1 - 3 groups

100

1647

6

Filling trenches and pits bulldozer soil 1 - 3 groups

100

898

7

Cable crossings and / roads and s / road punctures

10м

1460

8

Cable crossings and / roads and s / road directional drilling

10м

5234

9

Cable crossings over water obstacles directional drilling

10м

5234

Installation work

10

Laying cable (tube) a cable in soil 2 - 3 groups

км.каб

9307

1

2

3

4

5

6

11

Laying cable (tube) into the prepared trench

км.каб

1200

12

Laying cables in existing cable ducts and projecting

км.каб

3900

13

Blown optical cable in the tube

км.каб

4500

14

Establishing measurement instrumentation columns

шт.

248

15

Installation of couplings in cable wells and pits

шт.

2636

INSTALLATION and test workof OF

16

Measuring 8-optic cable reflectometer for cable ground before laying

барабан

1327

1

2

3

4

5

6

17

Measuring 8-optic cable Reflectometer for laying of each

building length

стр. длина

1682

18

Installation of joints and measuring the damping joints reflectometer in two directions

муфта

2637

19

Measurement of optical parameters, 8-fiber OF with optical testers in two directions mounted station

рег. дільн.

1400

20

Cable ОКЛБг з 8 ОВ

км

9100

Total

Planned savings

%

8

Total

Determine the cost of construction of 100 km of the route:

, (9.1)

where С – estimated cost of cable lines;

– length of the cable line, km.

Define the cost of a PTSP to 1 km route:

. (9.2)