- •1.5 Earth Work
- •2.1 Excavation:
- •2.2 Excavation Operation
- •2.5 Structural Elements
- •2.5.1 Foundation
- •2.5.1.1 Condition That Effect Foundation
- •2.5.1.2 Foundation Types
- •2.5.2 Walls
- •2.5.2.1 Types of Walls
- •2.5.2.2 Building Materials for Wall
- •2.5.2.3 Wall Characteristics
- •2.5.3 Column
- •2.5.3.1 Types of Column
- •2.5.5 Slabs
- •2.5.6 Beams
- •2.5.6.1 Types of Beams
- •2.5.7 Stairs
- •2.5.7.1 Stair Case Materials
- •2.5.8 Roof
- •2.5.8.1 Roof Types
- •2.5.8.2 Roof Connection
- •2.5.8.3 Roof Function
- •2.5.8.4 Roof Materials
- •2.6 Finishing Works
- •2.6.1 Doors and windows
- •2.6.1.1 Standard performance of door and window
- •2.6.1.2 Type of door
- •2.6.2 Plastering
- •2.6.2.1 Type of mortar used for plastering
- •2.6.2.2 Types of Plaster Finishes
- •2.6.2.3 Plastering Materials
- •2.6.2.4 Tools for the Plaster
- •2.6.2.5 Defect in Plastering
- •2.6.4.1 Types of flooring
- •2.6.5 Painting
- •2.6.6 Ceiling
- •2.6.7 Sanitary Installation
- •2.6.8 Plumbing
- •2.6.8.1 Plumbing Materials
- •2.6.8.2 Pipe Connection (Joints)
- •2.6.9 Electrical Installation
- •Introduction
- •3.1.5 Setting out the building
- •3.5 Beam
- •3.5 Slabs
- •3.5.1 Slab Materials
- •3.5.2 Number of Slab of Motels
- •3.7 Finishing Work
- •3.7.1 Plastering
- •3.7.2 Pavement
- •3.7.3 Doors and Windows
- •3.7.4 Drainage
- •3.7.4.1 Sanitary fitting
- •3.7.4.2 Septic Tank
- •3.7.4.3 Water supply
- •3.7.4.4 Painting
- •3.7.4.5 Electrical installation
- •3.8 Bill of Quantity
- •Appendix
3.1.5 Setting out the building
Steps carried out 24.5
Establishment of base line 7.1 17.4
14.5
24.5 24.5
Setting out the right angle at the correct laugh and offer we checked the diagonals.
13.5
23.5
Figure 9: setting out operation
3. Setting the profiles boards of the trench foundation wall.
4. Establishment of profiles
5. Making of position of portion walls on the profile with lither mails and sow cuts
6. The stretched of building line through the nails and cornet pegs mark.
All setting out work have been carried manually for giving jobs Ngoma populations.
3.2 Foundations
3.2.1 Foundation Sizes
Consolidation: 20x80 cm
Footing size: 60x 100 cm
Foundation: 40x 100 cm
Projection: 10cm= light and left
3.2.2 Foundation Materials
Stone for foundation between the columns
Concrete for consolidation
Timber for form work
3.2.3 Foundation Types
Our foundation types is ‘’deep Foundation’’ because of its dimensions.
3.3 Elevations
3.3.1 Columns
The size of our column should be 30x30 cm and height is 320 cm
Colum materials
Reinforced concrete its means concrete and embedded steel bars
Column type
According to the slenderness ratio which is less than 14.3 for square or rectangular column our column types is ‘’ Short Column, which has lateral ties with longitudinal bars
3.4 Walls
Walls sizes
Thickness is 20 cm
Height = 300 cm
Walls materials
Cement based blocks
mortar
Bricks for internal portion walls
Glaze for cyber coffee portion
Steps for Wall Construction
The fixing of profile lines to locate on external corner or strip foundations
Using the builders level held vertically and or plumb
Stretcher line between the corners to provide position for the first course of block securing line by wrapping it around blocks.
Removing of line after the first course of blocks
Laying blocks in arrow adjust their position
Checking horizontal and vertical level
Forming the joints while the mortar is soft
Tools used for Wall Construction
Trowels
Building level
Float
Strings
Plumb
Mortar pan
Pegs
Pinch
3.5 Beam
Cross beams size
Thickness 30cmx13,5cmx23,5c
Horizontal beam sizes
Have 30cmx23,5cm long
30cmx13,5cm long
Beam materials
Reinforced concrete
Timber for formwork
Steps for Beam Construction
Our beam should be cast in situ
Election of timber formwork
Sealing all the joint with mastic between the timber formwork and block work to stop the cement and water leaking out
Painting inside the formwork with realizing oil
Placement of reinforced in the formwork and check that the bars 50cm from each end of the box and supported by spacers
Pour the concrete into the timber box and making sure that it floors down around and under the rods