1. |
|
The waterfall model |
|
|
|
|
|
|
|
Correct answer is |
(d) |
|
|
Your score on this question is: |
0.00 |
|
|
Feedback: |
See section 1.1.2, page 15 in the textboo |
View Assessment Result: Exam 1 Multiple-Choice
Начало формы
|
|
|
|
Your performance was as follows: |
|
|
1. |
|
With modern software project management, if a project is behind schedule, managers can |
|
|
|
|
|
|
Correct answer is |
(b) |
|
|
Your score on this question is: |
10.00 |
|
|
Feedback: |
See section 1.2, page 18 in the textbook. |
|
|
|
2. |
|
Contemporary cost models |
|
|
|
|
|
|
Correct answer is |
(b) |
|
|
Your score on this question is: |
10.00 |
|
|
Feedback: |
See chapter 2, page 21, Key Points in the textbook. |
|
|
|
3. |
|
Universal function points |
|
|
|
|
|
|
Correct answer is |
(c) |
|
|
Your score on this question is: |
0.00 |
|
|
Feedback: |
See section 3.1.1, page 35 in the textbook. |
|
|
|
4. |
|
Model-based development |
|
|
|
|
|
|
Correct answer is |
(c) |
|
|
Your score on this question is: |
10.00 |
|
|
Feedback: |
See section 4.3, page 68 in the textbook. |
|
|
|
5. |
|
An architecture baseline |
|
|
|
|
|
|
Correct answer is |
(c) |
|
|
Your score on this question is: |
10.00 |
|
|
Feedback: |
See chapter 7, page 9, Key Points in the textbook. |
|
|
|
6. |
|
A design set |
|
|
|
|
|
|
Correct answer is |
(d) |
|
|
Your score on this question is: |
10.00 |
|
|
Feedback: |
See Glossary, page 392 in the textbook. |
|
|
|
7. |
|
For most iterations that last between one and six months, only two minor milestones are needed:
|
|
|
|
|
|
|
Correct answer is |
(a) |
|
|
Your score on this question is: |
10.00 |
|
|
Feedback: |
See section 9.2, page 132 in the textbook. |
|
|
|
8. |
|
The following are essential activities of which phase?
|
|
|
|
|
|
|
Correct answer is |
(c) |
|
|
Your score on this question is: |
0.00 |
|
|
Feedback: |
See section 5.5, pages 80-1 in the textbook. |
|
|
|
9. |
|
What activities are omitted in the modern process because they are considered a part of or by-products of the workflows? |
|
|
|
|
|
|
Correct answer is |
(a) |
|
|
Your score on this question is: |
10.00 |
|
|
Feedback: |
See section 8.1, page 119 in the textbook. |
|
|
|
10. |
|
What is considered in the environment workflow? |
|
|
|
|
|
|
Correct answer is |
(b) |
|
|
Your score on this question is: |
10.00 |
|
|
Feedback: |
See section 8.1, page 120, and Glossary, page 393 in the textbook. |
|
|
|
Go to top of assessment. |
|
|
Total score: 80.00 |
|
|
© Copyright 2008 iCarnegie, Inc. All rights reserved. |
Конец формы
Конец формы

(a) made
project managers look successful at the end of a project
(b) was
very cost effective
(c) incorporated
reviews to make stakeholders feel secure
(d) created
stakeholder suspicion and distrust
(a) add
as many programmers as necessary to speed the project up
(b) add
programmers to compress the schedule by about a quarter of the
estimate
(c) make
everyone work overtime
(d) hurt
the project by extending the target date
(a) are
currently difficult to use successfully
(b) are
based mostly on historical project databases using older
processes
(c) allow
estimates to be obtained easily
(d) reflect
a more production-intensive approach than they once did
(a) are
inferior to source lines of code for cost estimation at the
beginning of a project
(b) allow
the implementation of commercial components
(c) describe
the size of a problem instead of it's language-based
solution
(d) usually
indicate Java as the preferred language
(a) requires
visual modeling and risk control
(b) requires
complementary tools and integrated environments
(c) requires
object-oriented methods and rigorous notation
(d) requires
visual modeling and round-trip engineering
(a) is
a paper document
(b) is
extracted from requirements models
(c) is
a collection of information across all the engineering
sets
(d) is
the ultimate goal of the construction phase
(a) contains
more text than visual models
(b) is
in the language of the user
(c) is
linearly traceable from the requirements set
(d) includes
models of the solution space
(a) I
and III only
(b) I
and II only
(c) II
and III only
(d) I,
II, and III
(a) the
elaboration phase
(b) the
construction phase
(c) the
transition phase
(d) the
inception phase
(a) Documentation
and quality assurance
(b) Testing
and quality assurance
(c) Documentation
and maintenance
(d) Testing
and maintenance
(a) Installation
of the programming environment
(b) Evolution
of the maintenance environment and automation of the production of
the artifact sets
(c) Definition
of the architecture objectives
(d) Planning
and control of the external conditions that could affect the
project