Добавил:
Опубликованный материал нарушает ваши авторские права? Сообщите нам.
Вуз: Предмет: Файл:
0 Standard / 03. IAEA / NP-T-2.7 Project Management in NPP Construction_Guidelines.pdf
Скачиваний:
0
Добавлен:
07.04.2025
Размер:
3.24 Mб
Скачать

If nuclear specific practices are not recognized and understood by the sub-contractors at the time of contract signature, difficulties are to be expected at a later stage. It has been noted that:

The real competence of manufacturers and sub-contractors is not easy to judge through auditing only;

Evaluation of the manufacturer’s ability at the shop/factory is important;

The vendor needs to ensure not only their sub-contractors uphold the nuclear quality standards but that its subcontractors in turn require the same nuclear quality standard throughout the entire supply chain.

The Owner/Operator needs to have means to ascertain that the issues specific to nuclear safety and quality management, and the respective controls are properly agreed upon in each contract between the vendor and its subcontractors, including the entire supply chain.

5.3.5.Commissioning and operation

The transfer of responsibility and knowledge from the construction teams to the commissioning teams and on to operational staff can be facilitated by appointing commissioning and operations teams early and actively encouraging collaboration. Making equipment suppliers and installers responsible for the work and having commissioning staff as members of their team ensures that the right expertise is made available in a timely way, experience is gained and knowledge transferred. Ensuring that foreign material is prevented from entering the process systems and taking measures, prior to nuclear power generation, to reduce the corrosion products that could circulate through the core, will reduce radiation fields and operator dose that arise from subsequent operation of the plant. A lack of cleanliness during commissioning of either circuit can result in problems several decades into operation.

6. CONCLUSIONS AND RECOMMENDATIONS

Experience has shown that nuclear projects have faced challenges similar to other complex mega projects with additional specific issues. The major conclusions and recommendations are as follows:

Assign high priority to safety and quality over cost and schedule;

A regulatory framework should be established before launching the nuclear power project and the regulatory process is rigorous for nuclear power plants;

First of a kind projects are more challenging, complex, and costly than follow on replica plant;

Establish a high qualified project management team;

The design must be mature, and licensing issues resolved prior to start of construction and sufficient project pre-planning done;

Ensure that sub-contractors are of high quality and experienced in nuclear construction or are taught the necessary special skills and requirements for quality, traceability and documentation;

Establish and maintain good communications with the public;

The QA programme for the nuclear power industry is more stringent than for other industries. The QA programme interfaces the design, procurement, construction, manufacturing, installation and commissioning functions;

The systematic generation, preservation, verification and administration of documentation is of a vital significance supporting the license configuration and traceability of the design and safety parameters for future modifications;

Nuclear reactor’s life time cost is concentrated upfront as capital cost, and therefore delays in construction may become intolerable in terms of both lost revenues and interest on the capital;

Security has a special significance at nuclear power plants and should be taken into consideration during the construction.

78

REFERENCES

[1]U.S. DEPARTMENT OF ENERGY, Nuclear Power 2010, MPR-2627, Construction Schedule Evaluation, Revision 2, MPR Associates, US DOE, Washington D.C. (2004).

[2]INTERNATIONAL ATOMIC ENERGY AGENCY, Nuclear Project Management: A guidebook, Technical Reports Series No. 279, IAEA, Vienna (1998).

[3]INTERNATIONAL ATOMIC ENERGY AGENCY, Site Evaluation for Nuclear Installations, IAEA Safety Standards Series No. NS R-3, IAEA, Vienna (2003).

[4]PROJECT MANAGEMENT INSTITUTE, A Guide to the Project Management Body of Knowledge — PMBOK® Fourth Edition, PMI, Newtown (2008).

[5]PROJECT MANAGEMENT INSTITUTE, Construction Extension to the PMBOK® Guide Third Edition, PMI, Newtown (2007).

[6]INTERNATIONAL ATOMIC ENERGY AGENCY, Managing the First Nuclear Power Plant Project, IAEA-TECDOC-1555, IAEA, Vienna (2007).

[7]INTERNATIONAL ATOMIC ENERGY AGENCY, Invitation and Evaluation of Bids for Nuclear Power Plants, IAEA Nuclear Energy Series, No. NG-T-3.9, IAEA, Vienna (2011).

[8]INTERNATIONAL ATOMIC ENERGY AGENCY, Risk Management: A Tool for Improving NPP Performance, IAEA-TECDOC-1209, IAEA, Vienna (2001).

[9]PROJECT MANAGEMENT INSTITUTE, Project and Program Risk Management: A Guide to Managing Project Risks and Opportunities, PMI, Newtown (1992).

[10]INTERNATIONAL ATOMIC ENERGY AGENCY, Nuclear Security Recommendations on Physical Protection of Nuclear Material and Nuclear Facilities (INFCIRC/225/Revision 5), IAEA Nuclear Security Series No. 13, IAEA, Vienna (2011).

[11]PROJECT MANAGEMENT INSTITUTE, Practice Standard for Earned Value Management, PMI, Newtown (2005).

[12]PROJECT MANAGEMENT INSTITUTE, Practice Standard for Work Breakdown Structures, PMI, Newtown (2001).

[13]RADIATION AND NUCLEAR SAFETY AUTHORITY, Construction Inspection Programme, Licensing and Regulatory Oversight of new Nuclear Build Workshop in Helsinki and Olkiluoto, Petteri Tiippana, STUK, Helsinki (2008).

[14]INTERNATIONAL ATOMIC ENERGY AGENCY, Safety Culture in Nuclear Installations, IAEA-TECDOC-1329, IAEA, Vienna (2004).

[15]PROJECT MANAGEMENT INSTITUTE, Construction Extension to the PMBOK® Guide Third Edition, PMI, Newtown (2007).

[16]INTERNATIONAL ATOMIC ENERGY AGENCY, The Management Systems for Facilities and Activities, IAEA Safety Standards Series No. GS-R-3, IAEA, Vienna (2006).

[17]PROJECT MANAGEMENT INSTITUTE, A Guide to the Project Management Body of Knowledge — PMBOK® Fourth Edition, PMI, Newtown (2008).

[18]TVO Press Release 21/04/2010 http://www.tvo.fi/www/page/3405/

[19]Fennovoima Press Release 06/05/2010, http://www.fennovoima.com/en/pressreleases/

[20]LAAKSONEN, J., Regulatory oversight of Olkiluoto 3 (EPR) construction lessons learned, 20th International Conference on Structural Mechanics in Reactor Technology, Espoo (2009).

[21]THE ROYAL ACADEMY OF ENGINEERING, Engineering the future, Nuclear Lessons Learned, published by the Royal Academy of Engineering on behalf of Engineering the future, ISBN 1-903496-60-8, London (2010).

79

 

ABBREVIATIONS

ABWR

Advanced Boiling Water Reactor

CAR

Construction Assurance Report

AE

Architect Engineer

ATP

Authorization to Proceed

BBS

Budget Breakdown Structure

BOP

Balance of Plant

CAT

Construction Acceptance Test

CHT

Cold Hydro Test

COD

Commercial Operation Date

COTS

Commercial of the Shelf

EPC

Engineering Procurement Construction

EPR

European Pressurized Water Reactor

FSAR

Final Safety Analysis Report

HFT

Hot Functional Test

I&C

Instrumentation and Control

ILRT

Integrated Leak Rate Test

INIR

Integrated Nuclear Infrastructure Review

IRSS

Integrated Regulatory Review Service

MDEP

Mutual Design Evaluation Process

NCR

Non-Conformance report

NSSS

Nuclear Steam Supply System

OSART

Operational Safety Review Team

PAT

Power Ascension Test

PC

Procurement and Construction

PIP

Project Implementation Plan

PNSC

Plant Nuclear Safety Committee

PSAR

Preliminary Safety Analysis Report

QA

Quality Assurance

QC

Quality Control

RCS

Reactor Coolant System

SAT

Standby Auxiliary Transformers

SIT

Structure Integrity Test

SG

Steam Generator

STUK

Radiation and Nuclear Safety Authority from Finland

TG

Turbo Generator

TWG

Test Working Group

WBS

Work Breakdown Structure

CSA

Canadian Standards Association

ASME

America Society Mechanical Engineers

AEC

Architecture, Engineering, Construction

INCOSE

International Council Of Systems Engineering

P&ID

Process and Instrumentation Diagrams

81