Добавил:
Опубликованный материал нарушает ваши авторские права? Сообщите нам.
Вуз: Предмет: Файл:
0 Standard / 02 JICA.2013 / Guide / vol 2 / Vol2-Book12-Electrical Facility.pdf
Скачиваний:
0
Добавлен:
28.12.2023
Размер:
2.03 Mб
Скачать

SOCIALIST REPUBLIC OF VIETNAM

Ministry of Industry and Trade (MOIT)

Guideline for

Technical Regulation

Volume 2

Design of Thermal Power Facilities

Book 12/12

« Electrical Facility »

Final Draft

June 2013

Japan International Cooperation Agency

Electric Power Development Co., Ltd.

Shikoku Electric Power Co., Inc.

West Japan Engineering Consultants, Inc.

IL

CR(2)

13-092

 

Table of Contents

 

Chapter 1 Comparison between technical guideline and technical regulation of electrical facility

...1

Chapter 2 Each Items of Guideline.....................................................................................................

8

Section 1 General of the Electrical Facilities..................................................................

8

Section 2 Installation of the Electrical Facilities for the Power Supply........................

34

Section 3 Electrical Facilities in Demand Site..............................................................

60

Section 4

Measurement Equipment ..............................................................................

70

Section 5

Protection Equipment..................................................................................

123

Section 6

SCADA/EMS System.................................................................................

150

Chapter 3 Reference International Technical Standards .................................................................

184

 

List of Tables

 

Table- 1 Comparison between technical guideline and technical regulation of electrical facility ..................

1

Table- 2 Insulation of electric power line whose voltage is exceeding 1kV.................................................

10

Table- 3 Insulation of transformers................................................................................................................

11

Table- 4 Insulation of a rotating machine .....................................................................................................

12

Table- 5 Insulation of a switch and circuit-breaker.......................................................................................

13

Table- 6 Insulation of lightning-surge absorption type capacitors................................................................

13

Table- 7 Standards for cables whose voltages are less than 11kV ................................................................

14

Table- 8 Assumed weight on the wire...........................................................................................................

15

Table- 9 Safety factor....................................................................................................................................

 

16

Table10 Standards for extension and compensating cables........................................................................

16

Table11 Standards for optical fiber cables..................................................................................................

16

Table12 Standards for mineral insulated thermocouple cables...................................................................

17

Table13 Separation from wooden walls or ceilings or other inflammabilities ...........................................

20

Table14 Grounding of the metal stand and enclosure.................................................................................

21

Table15 Operating time of over-current breaker ........................................................................................

23

Table16 Installation of ground-fault shutdown device ...............................................................................

26

Table17 Separation between an overhead wire whose voltage is not less than 11kV and the supporting

 

......................................................................................................................................................

 

34

Table18 Sum of a height of a fence, wall, etc and a distance from a charging part to the fence, wall, etc.

 

......................................................................................................................................................

 

37

 

i

 

Table19 The height of an overhead wire whose voltage is not less than 11kV ..........................................

40

Table20 Separation between overhead wires and buildings whose voltages are not less than 11kV .........

42

Table21 Construction whose voltage is not less than 11kV for security ....................................................

43

Table22 Separation between over head wires whose voltages are not less than 11kV and over head

 

lines whose voltages are less than 11kV or and supporting equipment........................................

44

Table23 Separation between over head wires whose voltages are not less than 11kV...............................

45

Table24 Separation between over head wires whose voltages are not less than 11kV and other facilities

 

......................................................................................................................................................

46

Table25 Separation between underground cables and underground cables of weak current......................

47

Table26 Protection devices for the transformer whose voltage is not less than 11kV................................

54

Table27 Separation between the phase and separation from the ground of bare wires ..............................

54

Table28 Methods of protection...................................................................................................................

67

Table29 Hazardous areas classification ......................................................................................................

67

Table30 Measurement Equipment for Boiler (Recommendations) ............................................................

72

Table31 Automatic control systems for Boiler (Recommendations)..........................................................

85

Table32 Automatic control devices for Boiler (Recommendations)...........................................................

92

Table33 Measurement Equipment for steam turbine (Recommendations).................................................

99

Table34 Examples of EHC control function.............................................................................................

104

Table35 Measurement Equipment for Gas Turbine (Recommendations).................................................

108

Table36 Automatic control systems for combined cycle (Recommendations).........................................

109

Table37 Automatic control devices for combined cycle (Recommendations) ..........................................

113

Table38 Measurement Equipment for Generator (Recommendations) .....................................................

114

Table39 Automatic control systems for generator (Recommendations)....................................................

119

Table40 Measurement Equipment for Transformers (Recommendations)...............................................

121

Table41 Protection for boiler (Mandatory)...............................................................................................

124

Table42 Protection for boiler (Recommendation) ....................................................................................

127

Table43 Protection for Steam Turbine (Mandatory).................................................................................

129

Table44 Protection for Steam Turbine (Recommendations).....................................................................

130

Table45 Protection for Gas Turbine (Mandatory).....................................................................................

131

ii

Table46 Protection for Gas Turbine(Recommendation)...........................................................................

132

Table47 Protection for Generator and Major Transformers (Mandatory).................................................

133

Table48 Protection for Generator and Major Transformers (Recommendations) ....................................

135

Table49 Protections of auxiliary machines (pump) ..................................................................................

141

Table50 Protections of auxiliary machines (Axial flow type fan) ............................................................

141

Table51 Protections of auxiliary machines (Centrifugal type fan) ...........................................................

142

Table52 Protections of auxiliary machines (Axial flow type fan) ............................................................

142

Table53 Examples of SCADA functions ..................................................................................................

159

Table54 Examples of control network standards (Real time Ethernet) ....................................................

177

Table55 An example of SIL and hardware structures...............................................................................

178

Table56 Difference between DCS and SCADA.......................................................................................

180

Table57 Reference International Technical Standards (including national and industrial associations) ..

184

Table58 Reference Vietnamese Technical Regulations ............................................................................

203

Table59 Reference Vietnamese Technical Standards................................................................................

204

Table60 Reference Japanese Technical Standards....................................................................................

207

List of Figures

 

Fig- 1 Separation from wooden walls or ceilings or other inflammabilities.................................................

20

Fig- 2 Grounding of the second of an instrument transformer......................................................................

21

Fig- 3 An example of installation of discharging unit...................................................................................

22

Fig- 4 An example of installation of ground-fault shutdown devices...........................................................

27

Fig- 5 Grounding methods of cable shield....................................................................................................

30

Fig- 6 Ground loop current ...........................................................................................................................

30

Fig- 7 An example of appropriate installation ..............................................................................................

31

Fig- 8 Twisted pair cables .............................................................................................................................

31

Fig- 9 An example of circuit with the function of noise reduction ...............................................................

32

Fig10 Measuring circuit of power line carrier equipment ..........................................................................

33

Fig11 Distance from a charging part to a fence, wall, etc. .........................................................................

37

Fig12 Installation of machinery or equipment or buses installed outdoors................................................

39

iii

Fig13 Identifications of phase ....................................................................................................................

42

Fig14 An example of approach...................................................................................................................

43

Fig15 An example of cross.........................................................................................................................

44

Fig16 Separation between underground cables ..........................................................................................

47

Fig17 Separation between underground cables and weak current cables...................................................

47

Fig18 An example of arrester installations .................................................................................................

56

Fig19 Examples of cable installation underground ....................................................................................

58

Fig20 An example of installation in an area with much dust......................................................................

66

Fig21 Concept of operation, control and protection...................................................................................

70

Fig22 Resistance thermometer sensors.......................................................................................................

75

Fig23 Type of orifice ..................................................................................................................................

77

Fig24 ISA 1932 flow nozzle.......................................................................................................................

78

Fig25 The Venturi tube ...............................................................................................................................

78

Fig26 Transmitter and restrictor .................................................................................................................

79

Fig27 Oval gear type meter ........................................................................................................................

80

Fig28 Area type flow meter (Float type) ....................................................................................................

80

Fig29 Principle and configuration of the zirconia ......................................................................................

82

Fig30 Principle of the infrared analyzers....................................................................................................

83

Fig31 Principle and configuration of chemiluminescence type analyzers..................................................

84

Fig32 Configuration of boiler control ........................................................................................................

86

Fig33 Relationship between boiler control and process values (Drum boiler)...........................................

87

Fig34 Relationship between boiler control and process values (Once –through boiler) ............................

87

Fig35 An example of Automatic Plant Control (abstract) ..........................................................................

89

Fig36 An example of a turbine speed measurement...................................................................................

97

Fig37 An example configuration of control valves and sensors...............................................................

101

Fig38 An example of turbine supervisory instruments around the turbine shaft......................................

102

Fig39 An example of Electric Hydraulic Control flow.............................................................................

104

Fig40 An example of turbine control system............................................................................................

105

Fig41 The concept of automatic control systems for combined cycle (Single axis) .................................

110

iv

Fig42 The concept of automatic control systems for combined cycle (Multi axes) ..................................

111

Fig43 Principle of hydrogen concentration detection................................................................................

118

Fig44 Preferred way to provide ground-fault protection ..........................................................................

135

Fig45 An example of protecting relays in the electric power line for thermal power ..............................

140

Fig46 An example of 2 out of 3 logic.......................................................................................................

145

Fig47 An example of unit interlocks for conventional plants...................................................................

146

Fig48 An example of unit interlocks for gas turbine plants......................................................................

147

Fig49 An example of unit interlocks for single-shaft combined cycle power plant .................................

148

Fig50 An example of unit interlocks for multi-shaft combined cycle power plant ..................................

150

Fig51 An example of SCADA/EMS system and control system .............................................................

153

Fig52 Examples of redundant system.......................................................................................................

156

Fig53 Configuration of alarm unit............................................................................................................

163

Fig54 An example of alarming .................................................................................................................

165

Fig55 Concept of EMS.............................................................................................................................

166

Fig56 An example of system configuration for EMS at the power station...............................................

168

Fig57 An example of functions for EMS at the power station .................................................................

169

Fig58 An example of DCS system ...........................................................................................................

171

Fig59 An example of DCS module...........................................................................................................

172

Fig60 An example of DCS configuration .................................................................................................

173

Fig61 An example of data transmission between DCS.............................................................................

176

Fig62 An example of methodology for protection and control.................................................................

182

v

 

List of Acronyms/Abbreviations

 

 

AC

Alternating Current

 

 

ANSI

American National Standards Institute

 

 

APC

Automatic Plant Control

 

 

AVQR

Automatic Voltage & Q Regulator

 

 

AVR

Automatic Voltage Regulator

 

 

BFP

Boiler Feed water Pump

 

 

CRT

Cathode Ray Tube

 

 

CO

Carbon monOxide

 

 

CO2

Carbon diOxide

CV

Control Valve or governing valve

 

 

CT

Current Transformer

 

 

CVCF

Constant Voltage Constant Frequency

 

 

DB

Data Base

 

 

DC

Direct Current

 

 

DCS

Distributed Control System

 

 

DS

Disconnecting Switch

 

 

EHC

Electric Hydraulic Control

 

 

EMC

ElectroMagnetic Compatibility

 

 

EMS

Energy Management System

 

 

ETD

Embedded Temperature Detector

 

 

FA

Full arc Admission

 

 

FBC

Fluidized bed combustion boiler

 

 

FCB

Fast Cut Back

 

 

FDF

Forced Draft Fan

 

 

FW

Fire Wall

 

 

GW

Gate Way

 

 

HMI

Human Machine Interface

 

 

ICV

InterCept valve

 

 

IDF

Induced Draft Fan

 

 

IEC

International Electro-technical Commission

 

 

IEEE

Institute of Electrical and Electronics Engineers

 

 

IP code

International Protection code

 

 

ISO

International Organization for Standardization

 

 

JEC

Japanese Electrotechnical Committee

 

 

JEM

Japan Electrical Manufacturer

 

 

JIS

Japan Industrial Standards

 

 

vi

HRSG

Heat Recovery Steam Generator

 

 

LTB

Low pressure Turbine Bypass valve

 

 

MFT

Master Fuel Trip

 

 

MSV

Main steam Stop Valve

 

 

NFPA

National Fire Protection Association

 

 

NH3

Ammonia

NO

Nitrogen monOxide

 

 

NOx

Nitrogen Oxides

 

 

OA

Office Automation

 

 

PA

Partial arc Admission

 

 

PAF

Primary Air Fan

 

 

PCB

Polychlorinated Biphenyl

 

 

PLC

Programmable Logic Controller

 

 

PSS

Power System Stabilizer

 

 

SIL

Safety Integrity Level

 

 

SOx

Sulfur Oxides

 

 

SCADA

Supervisory Control And Data Acquisition

 

 

SSO

Single Sign On

 

 

TCVN

Vietnamese National Standard

 

 

VT

Voltage Transformer

 

 

VDT

Visual Display Terminal

 

 

WDT

Watch Dog Timer

 

 

vii

Соседние файлы в папке vol 2