List of Figures

Figure 19-1

Sample of Rating Plate (Son La HPP: Turbine-Generator Unit).................................

27

Figure 19- 2

Sample rating plate of generator..................................................................................

31

Figure 20-2

Dimensions of Color Band & Directional Arrow........................................................

40

Figure 21-1

Sample of record and indication of parameter for operation.......................................

47

Figure 21-2

Indication of Parameter for Control Boards (Fault indicator: 30F and Operation

 

 

indicator: 30S) .............................................................................................................

48

Figure 22-1

System configuration example of Load dispatch center..............................................

52

Figure 22-2

Example of installation of equipment with a record (Hydropower plant 1/3).............

53

Figure 22-3

Example of installation of equipment for record (Printer) (Hydropower plant

 

 

2/3)...............................................................................................................................

53

Figure 22-4

Example of installation of equipment for record (Monitoring system)

 

 

(Hydropower plant 3/3) ...............................................................................................

54

Figure 22-5

Example of installation of equipment for record (Thermal Power Plant) ...................

55

Figure 24-1

Process flow of registration of boiler and pressure vessel...........................................

57

Figure 25-1

Example of installation of equipment for Cameras system .........................................

59

Figure 33-1

Example of Installation of Fire Prevention Equipment ...............................................

65

Figure 33-2

Example of Principal Diagram of Fire Alarm Network...............................................

65

Figure 38-1

Powerhouse-Waste Water Disposal System in Hydro-power Plant.............................

68

Figure 93-1

Changeable Operation Rule.......................................................................................

113

Figure 95-1

Sequence Diagram of Protection System ..................................................................

114

Figure 98-1

Cross-section of Francis Turbine (An example of Turbine Pit of Hydraulic

 

 

Power Plant) ..............................................................................................................

115

Figure 114-1

Coal feeding system ..................................................................................................

131

Figure 116-1

Oil unloading and storage system..............................................................................

133

Figure 125-1

Measuring method of electrical potential of underground pipeline in terms of

 

 

ground........................................................................................................................

141

Figure 125-2

Measuring method of corrosion of underground pipeline .........................................

142

Figure 128-a1-1 LNG receiving terminal.............................................................................................

148

Figure 134-1

Process flow of no flow coal at bunker chute............................................................

158

Figure 134-2

Process flow of Lack of coal at coal feeder...............................................................

159

Figure 135-1

Configuration of measuring of flow velocity ............................................................

161

Figure 135-2

Configuration of sampling.........................................................................................

161

Figure 136-1

PAF system................................................................................................................

163

Figure 142-1

Classification of water treatment...............................................................................

176

Figure 142-2

Status of scale (Schematic view) ...............................................................................

177

Figure 143-1

Main process flow of furnace purge ..........................................................................

178

Figure 144-1

Water level.................................................................................................................

179

v

Figure 145-1

Sample of unit starting flow (cold mode)..................................................................

181

Figure 151-1

Main process flow of run back system at stopping FDF ...........................................

191

Figure 157-1

Sample of dual structure............................................................................................

202

Figure 159-1

Sample of unit stopping flow.....................................................................................

204

Figure 163-1

Sample behavior of steam turbine at load dump .......................................................

210

Figure 170-1

Sample countermeasure (Bypass of No.3 and 4 heater) ............................................

219

Figure 171-1

Sample countermeasure (Stopping of high pressure heater A (No.1) system) ..........

221

Figure 176-1

Countermeasure in case that left MSV is stuck .........................................................

229

Figure 176-2

Countermeasure in case that No.1 CV is stuck..........................................................

230

Figure 176-3

Countermeasure in case that operation of CV is fluctuated.......................................

231

Figure 176-4

Co untermeasure in case of boiler tube leak ..............................................................

232

Figure 178-1

Sample operation procedure at overload ...................................................................

234

Figure 182-1

Comparison between Unit-type and Not Unit-type power plant ...............................

239

Figure 186-1

Sample of fuel distribution of low NOx combustor ..................................................

244

Figure 197-1

Sample of purging procedure of gas turbine..............................................................

255

Figure 198-1

Sample of starting process flow of gas turbine..........................................................

256

Figure 200-1

Countermeasure in case that main fuel valve is stuck ...............................................

259

Figure 202-1

Process flow of purging fuel header by nitrogen.......................................................

261

Figure 208-1

Point to be checked when going up vibration of gas turbine.....................................

264

Figure 210

An example of electrical connection of a diesel generator........................................

265

Figure 214

An example of diesel generator start-up and shutdown.............................................

273

Figure 216

An example of fuel pipe line .....................................................................................

275

Figure 217-1

An example of check points of pneumatic control equipment ..................................

277

Figure 217-2

An example of front view of electronic automatic control equipment ......................

277

Figure 217-3

An example of redundant instrumentation ................................................................

278

Figure 217-4

An example of air flow failure ..................................................................................

279

Figure 218-1

An example of power supply using CVCF................................................................

280

Figure 218-2

An example of redundant system of DC and AC power supply................................

281

Figure 219

An example of insulation resistance measurement....................................................

283

Figure 222-1

Concept of operation, control, protection..................................................................

284

Figure 223

Examples of signal flow ............................................................................................

286

Figure 242-1

Measuring point of vibration of pump.......................................................................

297

Figure 242-a1-1 Countermeasure in case of rise in NOx concentration ..............................................

298

Figure 243-1

Countermeasure in case of rise in dust content .........................................................

299

Figure 245-1

Process flow of coal ash ............................................................................................

300

Figure 251-1

An example of brushless exciter................................................................................

307

Figure 251-2

An example of commutatorless exciter .....................................................................

307

 

vi

 

Figure 251-3

An example of static exciter ......................................................................................

308

Figure 252

An example of nitrogen seal system..........................................................................

311

Figure 253

An example of hydrogen cooled generator................................................................

312

Figure 256

An example of hydrogen supply system....................................................................

314

Figure 257

An example of seal oil system...................................................................................

315

Figure 260

An example of current on the rotor surface caused by negative-sequence

 

 

current........................................................................................................................

316

Figure 261

An example of thyristor starting system....................................................................

318

Figure 262-1

An example of generator capability curve.................................................................

319

Figure 262-2

An example of magnetic flux at generator stator core end........................................

320

Figure 264-1

An example of H2 supply unit ...................................................................................

323

Figure 264-2

An example of hydrogen replacement.......................................................................

324

Figure 279-1

Structural drawing of Rubber bag type conservator ..................................................

334

Figure 279-2

Structural drawing of diaphragm type conservator....................................................

334

Figure 287

Safety range of OPL for tree......................................................................................

337

Figure 288

Drainage Pump and leakage oil detectors..................................................................

338

Figure 290

Abnormal Image of overheat of connection point (by Infrared camera)...................

338

Figure 291

Example of interlock system .....................................................................................

339

Figure 294

Image of the indicators of switch gear.......................................................................

340

Figure 311

Sample Image of Protective ropes.............................................................................

347

Figure 312

Sample of warning plate............................................................................................

348

Figure 335

Excavation Area needs Engineer's Presence from management unit ........................

356

Figure 376-1

An Example of process flow diagram of electrolytic hydrogen production

 

 

system........................................................................................................................

372

Figure 379-1

An Example of valves installation.............................................................................

375

Figure 410-1

Attachment example to various switches ..................................................................

401

Figure 410-2

Attachment example to equipment state and fault indicator .....................................

401

vii

 

List of Photos

 

Photo 20-1

Sample numbering busduct and control panel.............................................................

32

Photo 20-2

Example of Directional Arrow1 ..................................................................................

40

Photo 109-1

Stacker .......................................................................................................................

126

Photo 109-2

Reclaimer...................................................................................................................

126

Photo 109-3

Belt conveyor.............................................................................................................

127

Photo 110-1

Unloader ....................................................................................................................

128

Photo 111-1

Coal stock yard..........................................................................................................

129

Photo 116-1

Heavy oil tank............................................................................................................

132

Photo 117-1

Temperature gauge ....................................................................................................

133

Photo 121-1

Foam fire extinguishing system.................................................................................

138

Photo 121-2

Dry chemical extinguishing system...........................................................................

138

Photo 127-1

Contact combustion type sensor................................................................................

144

Photo 127-2

Semiconductor type sensor........................................................................................

145

Photo 127-3

Hot-wire semiconductor type sensor .........................................................................

145

Photo 127-4

Gas heat conduction type sensor ...............................................................................

145

Photo 128-a1-1

LNG storage tank ......................................................................................................

148

Photo 128-a2-1

Vaporizer....................................................................................................................

149

Photo 128-a3-1

Gas compressor .........................................................................................................

151

Photo 128-a4-1 Liquefied gas pump ...................................................................................................

151

Photo 131-1

Coal pulverizer ..........................................................................................................

156

Photo 135-3

Pump unit...................................................................................................................

161

Photo 140-1

Effect of cleaning of boiler........................................................................................

167

Photo 149-1

Creep damage ............................................................................................................

185

Photo 149-2

Fatigue damage..........................................................................................................

185

Photo 150-1

Soot blower................................................................................................................

188

Photo 151-1

FDF and IDF..............................................................................................................

190

Photo 152-1

De-NOx equipment ...................................................................................................

193

Photo 152-2

Catalyst......................................................................................................................

193

Photo 152-3

Electric precipitator ...................................................................................................

194

Photo 152-4

Electric precipitator (inner and outer structure).........................................................

195

Photo 152-5

De-SOx equipment (Absorber)..................................................................................

197

Photo 153-1

Oil burner...................................................................................................................

198

Photo 154-1

Non-water absorbing property of thermal insulation.................................................

199

Photo 165-1

Main stop valve .........................................................................................................

211

Photo 165-2

Re-heat stop valve .....................................................................................................

211

Photo 165-3

Control valve .............................................................................................................

212

 

viii

 

Photo 167-1

Extraction non-return valve.......................................................................................

215

Photo 168-1

Turbine oil feeding system ........................................................................................

215

Photo 170-1

Heat exchanger system ..............................................................................................

220

Photo 180-1

Circulating water pump .............................................................................................

237

Photo 180-2

Rotary screen.............................................................................................................

237

Photo 180-3

Seawater booster pump..............................................................................................

237

Photo 181-1

Cooling tower ............................................................................................................

239

Photo 188-1

Thermocouple............................................................................................................

245

Photo 191-1

Air intake room..........................................................................................................

248

Photo 191-2

HEPA filter ................................................................................................................

248

Photo 225- 1

Feed-water treatment system.....................................................................................

288

Photo 225-2

Condensate demineralizer..........................................................................................

288

Photo 225-3

Chemical pump..........................................................................................................

289

Photo 228-1

Wastewater treatment equipment...............................................................................

291

Photo 236-1

Steam turbine.............................................................................................................

295

Photo 236-2

LNG piping................................................................................................................

295

Photo 245-1

Slag disposal system (Chain conveyor type).............................................................

300

Photo 245-2

Fly ash disposal system (Vacuum transportation system) .........................................

301

Photo 247-1

Ash pond....................................................................................................................

303

ix

Соседние файлы в папке Guide