
- •Table of Contents
- •List of Tables
- •List of Figures
- •PART 1 DEFINITIONS
- •Chapter 1-2 Definitions of Transmission and Distribution Lines
- •Chapter 1-5 Definitions of Metering
- •Chapter 1-6 Definitions of Earthing
- •PART 2 GENERAL REQUIREMENTS
- •Chapter 2-2 Electrical Equipment
- •Chapter 2-2-1 The Selection of the Conductor Cross-Section Area
- •Chapter 2-2-2 The Selection of Electrical Equipment by Short Circuit Conditions
- •Chapter 2-3 Transmission and Distribution Lines
- •Chapter 2-3-1 House and Outside Wiring Systems with Voltage up to 35kV
- •Chapter 2-3-2 Power Cable Line Systems with voltage up to 220kV
- •Chapter 2-3-3 Overhead Power Line Systems with voltage up to 500kV
- •Chapter 2-4 Distribution Equipment up to 1kV
- •Chapter 2-5 Substations above 1kV
- •Chapter 2-6 Measure the electrical energy (Metering)
- •Chapter 2-6-1 Metering System
- •Chapter 2-6-2 Electrical Measurements
- •PART 3 TRANSMISSION AND DISTRIBUTION LINES
- •Chapter 3-1 House and Outside Wiring Systems with Voltage up to 35kV
- •Chapter 3-1-1 The Selection of Types of House and Outside Wirings with voltage up to 1kV and Installation Methods
- •Chapter 3-1-2 House Wirings with Voltage up to 1kV
- •Chapter 3-1-3 Outside Wirings with Voltage up to 1kV
- •Chapter 3-1-4 House and Outside Wirings with Voltages above 1kV up to 35kV
- •Chapter 3-2 Power Cable Line Systems with Voltage up to 220kV
- •Chapter 3-2-1 The Selection of Cables
- •Chapter 3-2-3 Special Requirements for Power Cable Lines
- •Chapter 3-2-4 Cables Installed Underground
- •Chapter 3-2-6 Installation of Cable Lines in Production Halls, Water or Special Structures
- •Chapter 3-3 Overhead Power Line Systems with Voltage up to 500kV
- •Chapter 3-3-1 Power Conductors and Lightning Conductors
- •Chapter 3-3-3 Insulators
- •Chapter 3-3-4 Power Line Accessories
- •Chapter 3-3-5 Overvoltage Protection
- •Chapter 3-3-6 Poles
- •Chapter 3-3-7 Particular Requirement
- •Chapter 3-3-8 Traversing Non-Populated Areas
- •Chapter 3-3-9 Traversing Populated Areas
- •Chapter 3-3-10 Traversing Areas with Water
- •Chapter 3-3-11 Crossing or Going Nearby Overhead Power Lines
- •Chapter 3-3-13 Crossing or Going Nearby Special Structures and/or Places
- •Chapter 4-1 Distribution Equipment up to 1kV
- •Chapter 4-1-1 Electric Equipment Installation
- •Chapter 4-1-2 Distribution Panel Boards
- •Chapter 4-2 Distribution Equipment and Substations above 1kV
- •Chapter 4-2-2 Indoor Distribution Equipment and Substations
- •Chapter 4-2-3 Workshop Substation
- •Chapter 4-2-4 Distribution Equipment and On-Pole Substation
- •Chapter 4-2-5 Lighting Protection
- •Chapter 4-2-6 Lightning Protection for Rotation Machine
- •Chapter 4-2-7 Internal Overvoltage Protection
- •Chapter 4-2-8 Installation of Power Transformers
- •Chapter 4-2-9 Battery Systems
- •PART 5 PROTECTIVE RELAYS AND CONTROL SYSTEMS
- •Chapter 5-1 Protective Relays up to 1kV
- •Chapter 5-2 Protective Relays above 1kV
- •Chapter 5-2-1 Common Protection Methods
- •Chapter 5-2-2 Protection of Generators
- •Chapter 5-2-3 Protection of Transformers and Shunt Reactors
- •Chapter 5-2-4 Protection of Transformer and Generator Blocks
- •Chapter 5-2-5 Protection of Overhead Lines and Cables with Isolated Neutral
- •Chapter 5-2-6 Protection of Overhead Lines and Cables with Efficient Earthed Neutral
- •Chapter 5-2-7 Protection of Compensating Capacitors
- •Chapter 5-2-8 Protection of Busbars
- •Chapter 5-2-9 Protection of Synchronous Compensators
- •Chapter 5-2-10 Protection of Underground Cable Lines
- •Chapter 5-3 Control Systems
- •Chapter 5-3-1 Control equipment and Auto-reclosers
- •Chapter 5-3-2 Auto Switching Power Supply Devices
- •Chapter 5-3-3 Auto-synchronization of Generators
- •Chapter 5-3-4 Auto-control Exciter Systems, Auto-control of Reactive Power, Auto-voltage Regulators
- •Chapter 5-3-5 Auto-control Frequency and Active Power
- •Chapter 5-3-6 Auto-prevention of Disturbances
- •Chapter 5-3-7 Auto-elimination of Asynchronous Mode
- •Chapter 5-3-8 Auto-prevention of Frequency Decrease
- •Chapter 5-3-9 Auto-prevention of Frequency Increase
- •Chapter 5-3-10 Auto-prevention of Voltage Decrease
- •Chapter 5-3-11 Auto-prevention of Voltage Increase
- •Chapter 5-3-13 Remote Telecontrol Systems
- •Chapter 5-4 Secondary Circuits
- •PART 6 EARTHING
- •Chapter 6-1 Purpose of earthing
- •Chapter 6-2 Components to be Earthed in Power Networks
- •Chapter 6-3 Components to be Earthed in Electrical Equipment
- •Chapter 6-4 Components Exempt from Earthing
- •Chapter 6-5 Protection against Earth Faults
- •Chapter 6-6 Earth Resistance Requirements of Earthing System
- •Chapter 6-7 Calculation of Earth Fault Current
- •Chapter 6-8 Earthing Conductors
- •Chapter 6-9 Installation Method of Earthing Systems
- •Chapter 6-10 Alternatives to Earthing Conductors
- •Chapter 6-11 Earthing of Mobile Electrical Equipment
- •Annex II.2.1 (I.3A)
- •Annex II.2.2 (I.3B)
- •Annex II.2.3 (I.3C)
- •Annex III.1 (II.1)
- •Annex III.3 (II.4)

|
List of Figures |
|
|
Figure 7-1 |
(Reference) Cable structures .......................................................................................... |
|
7 |
Figure 7-2 |
The sample of cable arrangement................................................................................... |
|
8 |
Figure 7-3 |
Safety corridor of power cable line ................................................................................ |
|
9 |
Figure 8-1 |
Safety corridor of overhead power line........................................................................ |
|
10 |
Figure 8-2 |
Safety corridor of tree .................................................................................................. |
|
10 |
Figure 72-1 |
Cross section of square busbar ..................................................................................... |
|
44 |
Figure 72-2 |
Cross section of box busbar ......................................................................................... |
|
45 |
Figure 81-1 |
Electromagnetic force between conductors.................................................................. |
|
49 |
Figure 81-2 |
Bus arrangement........................................................................................................... |
|
49 |
Figure 84 |
Breaking performance of fuses .................................................................................... |
|
51 |
Figure 113 |
(Sample) Map of the route ........................................................................................... |
|
61 |
Figure 122 |
Pole sign ....................................................................................................................... |
|
64 |
Figure 124 |
Painted signs and signal lamps..................................................................................... |
|
65 |
Figure 137-1 Determination of short-circuit breaking currents and of percentage |
D.C. |
|
|
|
component .................................................................................................................... |
|
72 |
Figure 137-2 |
Percentage DC component in relation to the time interval |
from |
the |
|
initiation of the short circuit for the standard time constant and for the |
|
|
|
special case time constants........................................................................................... |
|
73 |
Figure 142 |
Altitude correction factor ............................................................................................. |
|
75 |
Figure 145-1 Mechanical interlock between line disconnector and earthing switch ......................... |
|
76 |
|
Figure 145-2 Electrical interlock for line disconnector and earthing switch ..................................... |
|
77 |
|
Figure 146 |
(Reference) Earthing Terminal ..................................................................................... |
|
77 |
Figure 148 |
Necessary length of lead wire which connects between two equipment...................... |
|
79 |
Figure 157-1 Sump with integrated catchment tank .......................................................................... |
|
82 |
|
Figure 157-2 Sump with separated catchment tank ........................................................................... |
|
82 |
|
Figure 157-3 Sump with integrated common catchment tank ........................................................... |
|
82 |
|
Figure 159 |
The outlet layout example of hospital grade (Connected to isolating TR) |
|
|
|
and normal grade.......................................................................................................... |
|
83 |
Figure 287 |
Distance for induction ................................................................................................ |
|
145 |
Figure 305 |
The example of secondary fault due to the shortage of arc space.............................. |
|
155 |
Figure 306 |
Connection diagram of knife switch .......................................................................... |
|
156 |
Figure 310 |
The Example of screw-in fuse and fuse base ............................................................. |
|
157 |
viii

Figure 321 |
Measurement of resistance of compression part using the voltage-drop |
|
|||
|
method........................................................................................................................ |
|
|
|
160 |
Figure 358 |
Example of protection by enclosure for the conductor of the transformer................. |
170 |
|||
Figure 365 |
(Reference) Japanese installation example of drive engine |
with |
lock |
||
|
system of the disconnecting switch in one pole ......................................................... |
|
|
|
173 |
Figure 369 |
PVC conduit (with a weather resistant |
and a |
self |
extinguishing |
|
|
performance) .............................................................................................................. |
|
|
|
174 |
Figure 377-1 Schematic diagram of atmospheric over-voltage protection of substations |
|
||||
|
connected to overhead line via branches with a) length up to 150m b) |
||||
|
length over 150m to 500m ......................................................................................... |
|
|
|
180 |
Figure 377-2 Schematic diagram of atmospheric over-voltage protection of substations |
|
||||
|
connected to overhead line via branches with (a) length up to 150m and |
||||
|
(b) over 150m............................................................................................................. |
|
|
|
180 |
Figure 382 |
Atmospheric overvoltage protection diagram for electric rotation machine |
..............184 |
|||
Figure 389 |
Installation example of oil level gauge....................................................................... |
|
|
|
189 |
Figure 390-1 Installation example of Buchholz Relay (Japanese case)........................................... |
|
|
190 |
||
Figure 390-2 Installation example of maintenance ladder (Japanese case) ..................................... |
|
|
190 |
||
Figure 395 |
Installation example of bursting tube and catchment tank ......................................... |
|
|
191 |
|
Figure 420-1 |
Protection Zones......................................................................................................... |
|
|
|
200 |
Figure 420-2 |
Protection Zone and the arrangement of circuit breaker and |
current |
|||
|
transformer ................................................................................................................. |
|
|
|
200 |
Figure 426 |
Impedance locus during transient power swing ......................................................... |
|
|
|
202 |
Figure 548 |
Permissible touch voltage UT ..................................................................................... |
|
|
|
257 |
Figure 549 |
Grounding method of neutral conductor .................................................................... |
|
|
|
259 |
Figure 566-1 |
Grounding method of neutral conductor |
of-voltagelow |
electrical |
||
|
equipment................................................................................................................... |
|
|
|
268 |
Figure 566-2 |
Grounding method of neutral conductor |
of-voltagelow |
electrical |
||
|
equipment................................................................................................................... |
|
|
|
268 |
Figure 566-3 |
Grounding method of neutral conductor |
of-voltagelow |
electrical |
||
|
equipment................................................................................................................... |
|
|
|
269 |
Figure 566-4 |
Grounding method of neutral conductor |
of-voltagelow |
electrical |
||
|
equipment................................................................................................................... |
|
|
|
270 |
Figure 567 |
Touch voltage and step voltage .................................................................................. |
|
|
|
272 |
Figure 568-1 |
Two-layer land............................................................................................................ |
|
|
|
273 |
Figure 568-2 Two coefficients k1 and k2 ........................................................................................ |
|
|
|
277 |
|
Figure 569-1 Earth fault outside substation ..................................................................................... |
|
|
|
281 |
|
Figure 569-2 Earth fault inside substation....................................................................................... |
|
|
|
281 |
|
|
ix |
|
|
|
|

Figure 570 |
Earth fault at two points distant from each other in different phases......................... |
285 |
Figure 589 |
Connecting method of grounding conductor.............................................................. |
293 |
Figure 591 |
Connection between metal enclosure and metal base ................................................ |
293 |
x