
reading / British practice / Vol D - 1990 (ocr) ELECTRICAL SYSTEM & EQUIPMENT
.pdf
Earthing systems
.hiv svstems. Therefore, these types of electrodes
E |
oire considerable space and are difficult to accom- |
90mm DUCTS |
|
|
|
|
|
|
|
|
|
|
|
||||||
AS REQUIRED |
|
|
|
|
|
|
|
|
|
|
|
||||||||
rc |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
wdate at the locations where EHV system faults are |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|||
|
|
to occur, i.e., generator or station transformers. |
|
|
|
|
|
|
—--- |
- |
|
|
|
|
|
|
|||
.1, |
:therefore more convenient to use sheet or cylin- |
|
|
|
|
|
|
1 |
MC 1 |
|
|
|
|||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||
|
tcel piles which form a more compact electrode. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
|
|
type of steel pile used for the earth elec- |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
a new station will usually be selected from |
A |
|
|
|
|
|
|
|
|
|
|
|
A |
||||
|
Je |
4 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
|
that the civil contractor has on site for his own |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
|
Foil calculations to obtain the overall station re- |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
.;,:.ince and rise of earth potential are only corn- |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||
|
|
for steel piles to demonstrate the principles. The |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
parameters selected for all examples are as |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
100mm • I2mm |
|
1 |
|
|
- |
|
|
|
|
|
|
|
|||
:0 11 0v.s: |
|
|
200 mm 5 ..1,1 |
|
|||||||||||||||
|
ALuMifflu1,1 EARTH BAR |
|
|
|
|
|
|
|
|
|
|
|
|||||||
• |
\ i„,i m urn earth fault current to return to remote |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
|
ncuirals is 28 kA. It should be noted that this is |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
|
he |
current which has to return to the remote neu- |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
:rdl |
via the earth electrode and therefore 'on site' |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
:eneration |
is ignored. For earth electrode design |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
curposes, |
this earth fault current is assumed to have |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
.1 maximum duration of I second. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
• v.craa soil resistivity to a depth of 10 m at any rroposeci electrode location is 19.9 Sim.
ELECT CONTINUITY |
L_ |
11 |
STRAPS AT EACH |
|
|
FILE JOINT |
‘I 7 |
|
I 1 implicity, all calculations are carried out assum-
:'..z ihe |
top of the electrode is flush with the ground |
-tirlai:e. |
In practice, for steel piles, the top of the |
.•.....Arode is approximately 1 m below the surface as ,: ; ,m I) in Figs 6.124 and 6.125. The errors from this :; TroNimation are considered negligible, bearing in ihe limitations in the accuracy of soil resistivity
114,1 Sheet steel piles
LARSON NO 3 —I-4 |
|
|
|
|
|
|||
SHEET PILES |
li |
|
|
|
|
|
||
|
|
, I |
|
|
|
|
|
|
100mm 42mm |
|
|
|
|
|
|
|
|
STEEL STRAPS |
|
|
|
|
|
|
|
|
WELDED TO PILES |
|
|
|
|
|
|
|
|
WITH CONTINUOUS |
|
|
|
|
|
|
|
|
FILLET WELD |
-..44111411111Noil.:Orn |
|
|
|
|
|||
|
|
|
|
|||||
|
|
V\ |
4! . * |
|
|
|
||
247mm |
|
|
|
7--7- |
|
|
|
|
|
|
|
1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1200mm |
|
|
|
|
|
|
|
|
|
|
|
Li:, example is based on Larson No 3 piles as shown |
||
:. |
IL 6.124. This type of pile is trough -shaped, the |
|
|
being 145 mm long and the bottom 248 mm wide; |
|
|
:lliekness of the pile is 14 mm. |
|
I |
on,ider |
the station electrode arrangement shown |
6.122, |
where %ite measurements have shown the |
|
|
a%.erage soil resistivity for any proposed main |
....!rode location to he 19.9 Sim. This figure can be to determine the smallest electrode area capable
' dmipaiing the assumed 28 kA earth fault current |
|||
. , |
e.ated with the 400 kV system. |
||
Hl |
,, |
discussed in CP1013: 1965, the little experimen- |
|
|
, |
||
|
ork % .hich has been carried out on current loading |
||
|
|
been |
confined to model tests with spherical elec- |
|
|
in clay or loam of low resistivity. One of the |
--'1',uRe conclusions from this work is that the time |
|
- tliture on short-term overload is inversely pro- |
|
|
t;onal to the specific loading, which is given by |
|
%there i is the current density at the electrode |
•,, |
and Q the resistivity of the soil. For soils in- |
ated the maximum permissible current density is |
•
SECTION B-B
FIG. 6.124 Arrangement of sheet steel pile electrode
i = |
\II 57.66 x 10 6 |
A/m 2 |
|
|
Qt |
where: Q = soil resisitivity, Sim
t = duration of fault, s
For the given conditions:
=57.66 x 10 6 A/m 2
19.9x 1
i = 0.17 x 10 4 |
A/m 2 |
557

Cabling |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Chapter 6 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1SOmm MIN |
||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
90m, CABLE DUCTS |
||||||||||||||||
|
AS REOLAPEO |
||||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1000mm SO |
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
41:11) mm |
|
|
|
|
|
|
|
|
|
|
I |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|||
|
|
|
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
|
|
|
100mm 12m1n |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
ALUMINIUM |
|
701)mm |
|
|
|
|
|
|
|
|
|
|
|
|
EARTH BAR |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
BOLTED
I GOITrri 12mrn ALUMINIUM
BRACKET SEMCNABLE FOR
TEST PURPOSES
STEEL BARS WELDED
1 04,1rorn r 12rr.rn STEEL EXTENSIONS WELDED TO PILE LINER
TOP OF CYLINDRICAL
STEEL ELECTRODE
65Ernm MIN LENGTH OF roew
LL
SECTION A-A
FIG. 6.125 Arrangement of cylindrical steel pile electrode
Minimum length of single pile required:
1
L
i x (2w 4s)
where 1 = earth fault current, A
= maximum permissible current density, A/m 2
w = width of base of pile, m s = length of side of pile, m
28 000
0.17 x 10 4 x ((2 x 0.248) + (4 x 0.145)) L = 15,3 m
558

|
|
|
|
|
|
|
|
|
|
|
|
|
Earthing systems |
|
|
|
|
|
|
|
|||||||
'co" for the pile electrode under consideration, the |
For an earth fault duration of 1 second and a soil |
||||||||||||
|
|
the equivalent hemisphere is: |
resistivity of 19.9 fl m, the maxirnurn permissible rod |
||||||||||
|
01 |
loading is: |
|
|
|
|
|||||||
|
|
|
|
|
|
10 |
= 3.0 m |
|
380 |
|
|
||
|
|
|
|
|
|
|
i |
|
-85 A/m |
||||
|
|
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
I0gn |
|
|
|
|
\(19.9 x 1) |
||||
|
|
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
The total length of earth rod required for a fault current |
||||
|
|
L |
|
10 in |
|
|
|
|
of 28 kA is: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
|
|
3.0 |
|
|
L - |
28 000 |
- 329 m |
||
|
|
|
|
|
|
- = 0.3 |
|
|
|
||||
|
|
|
|
|
|
|
85 |
||||||
|
|
|
|
|
|
10 |
|
|
|
|
|
||
%.fore, for two pile electrodes in parallel: |
Assuming that the maximum depth to which an earth |
||||||||||||
|
|
|
|
|
|
|
|
|
rod can be driven is 5 m, the total number of rods |
||||
|
,_ |
|
1 + a |
|
x (resistance of a single pile) |
required is 66. In order to obtain reasonable current |
|||||||
[Z2 |
|
( --. |
|
dissipation and overall resistance from the electrode |
|||||||||
|
|
|
|
|
|
|
|
array, the rods should be spaced on 3 m centres. Using |
|||||
|
|
|
|
|
|
|
|
|
|||||
|
|
|
I + 0.3 ) |
|
|
|
this spacing, an area of some 600 m 2 is required for |
||||||
|
|
|
x 1.06 |
|
|
the electrode array. |
|
|
|
|
|||
|
= |
|
( |
|
1 |
|
|
In view of the need to place the electrode close to |
|||||
|
|
2 |
|
|
|
||||||||
|
|
|
-- |
|
|
|
|
||||||
|
|
|
|
|
|
|
|
|
the location where an EHV earth fault may occur, |
||||
|
= |
|
0.69 C2 |
|
|
|
|
e.g., generator transformer, it is likely to be difficult |
|||||
|
|
|
|
|
|
to find such an area of free space available. A further |
|||||||
|
|
|
|
|
|
|
|
|
|||||
1 three |
pile electrodes, arranged in a triangle: |
complication with this type of electrode is the diffi- |
|||||||||||
culty of interconnecting the large number of rods with |
|||||||||||||
|
|
|
( 1 + 2a, |
|
|
|
|
buried cable or strip. This type of electrode is not |
|||||
|
|
|
|
x (resistance of a single pile) |
therefore recommended for power station applications. |
||||||||
|
|
|
|
|
|
|
|
|
|
|
|||
|
|
|
3 |
|
|
|
|
|
|
|
|
|
11.4.4 Earth strip
|
( + 0.6 ) |
||
|
|
3 |
x 1.06 |
|
|
||
R; |
= 0.56 C2 |
||
rii |
(his it can be seen that only a relatively small |
:t rrmement in resistance is |
obtained by adding the |
electrode. Therefore, if ground conditions permit, |
|
• 1;,1 ■,- be more beneficial to |
drive two electrodes to |
ater depth than to add further electrodes.
ftc o‘erall station earth resistance and rise of earth are then determined in the same manner as
11.4.1of this chapter.
11.4.3Earth rods
, ection is based on the use of 16 mm diameter
.vensible steel-cored copper earth rods complying with Standard 43-94.
ihe general formula for permissible current loading al he transformed by using the surface area of a
16 min earth rod to yield the following:
|
380 |
= |
A/m of earth rod |
|
./(Qt) |
This section is based on the use of 50 x 6 mm copper strip. For an earth fault duration of 1 second and a soil resistivity of 19.9 12m, the permissible current rating is once again:
|
= V 57.66 x 10 6 |
• |
- 0.17 x 10 4 A/m 2 |
|
19.9 x 1 |
Total length of strip required is:
fault current
L -
current density x circumference
28 000
0.17x 10 4 x [(2 x 0.05) + (2 x 0.006)]
=147 m
In order to obtain reasonable current dissipation and obtain the required order of resistance, this tape would need to be buried over an area in excess of 300 m 2 . As discussed for earth rods, this amount of free space is not normally available at the required location. An alternative would be to install the electrode in contact with the earth under the foundation slab concrete.
561

Cabling |
Chapter 6 |
|
However, this would require accurate planning so as not to delay the civil contractor and if any damage
occurred during concrete pouring this could not be detected. An added complication is the time involved in making an electrical connection between the strips
at each mesh intersection. NOMiNAL iNSULATICN TO PREVENT ELECTRICAL CONTACT ANO CORROSION
11.5 Earth network construction and plant |
|
|
|
|
|
bonding |
|
|
|
_ |
|
|
|
0 0 0 0 |
|||
|
|
|
|
|
Earth networks are formed and bonding of plant is carried out using PVC insulated cables. Earth cables run on the power cable supporting steelwork are considered to give a more economic installation than copper or aluminium bar clipped to the building surface. The use of earth cables allows the same installation and termination techniques as for power cables, giving a unified approach to labour requirements and the use of standard tools and equipment.
All cables used for earthing and bonding comply with the insulation, construction and testing requirements given in 3S6004: 1975. The cables may have either green or green/yellow insulation and the following rationalised range of sizes is used:
Size, 111171 2 |
Type of construction |
2.5Stranded copper/PVC
4 |
Stranded copper/PVC |
6 |
Stranded copper/PVC |
10 |
Stranded copper/PVC |
16 |
Solid aluminium/PVC |
35 |
Solid aluminium/PVC |
95 |
Solid aluminium/PVC |
150 |
Solid aluminium/PVC |
300 |
Solid aluminium/PVC |
500 |
Stranded aluminium/PVC |
All earth cables are terminated, bolted to equipment and where necessary protected from corrosion using the techniques given in Section 9.2 of this chapter.
11.5.1 Main earth network
The main earth network is formed by interconnecting the earth electrodes and forming rings around main plant areas as shown in Fig 6.122. These rings are extended into all levels of the building where major plant is located. Interconnections are made using 'teeoff' bars of the type shown in Fig 6.126. These `tee-off" bars are also inserted in the ring at strategic locations to enable connections to be made to electrical plant.
As discussed in Section 11.3 of this chapter, the largest current that the station earth network will normally have to carry is the 43.1 kA associated with the 415 V system. Major plant such as switchgear is
FIG. 6.126 Arrangement of tee-off connections
given a 3 -second rating and it is considered appr o , priate to give this rating to the main earth network. However, this fault duration is considerably in excess of that associated with back-up protection and such faults must be considered extremely rare. Under these circumstances it is considered acceptable to allow the earth cable to reach a final temperature of 325 ° C, as allowed by Engineering Recommendation S5/1 for aluminium bar. Whilst this ensures mechanical integrity of the earth system, it will be appreciated that the PVC cable sheathing will disintegrate and any affected cables would have to be replaced. However, for fault durations appropriate to back-up protection, the earth network should not be damaged and therefore the final conductor temperature of earth cables is limited to 160° C.
The required cable size is calculated using the formula given in Section 4.3.1 of this chapter:
1
S = _ |
|
|||
K V log r, ROr |
,3)/(0; f3)] |
|||
|
|
|
|
|
43 |
100 |
V |
3 |
148log s [(325 + 228)/(25 + 228)]
=570 mm 2
The use of 500 mm 2 cable is accepted as being adequate for forming the station earth network because of the extremely low probability of a 3-second fault and also, since the network is a ring, there will be a degree of current sharing between cables. For a cable temperature limit of 160 ° C the maximum allowable fault duration is 1.26 seconds which is adequate to cater for back-up protection.
11.5.2 Instrument earth network
To reduce the risk of interference on control and instrumentation equipment, a 'clean' earth termed the station instrument earth is provided. This instrumegt
562

|
|
|
|
|
Earthing systems |
|
|
|
|
||||
discussed in Section 11.6.1 of this chapter, the |
csa = 4 (9 x 97) = 3492 mm 2 |
|||||
jcl, t h |
which a pile may economically be driven is |
|
|
|||
w |
This allows a significant factor of safety on the mini- |
|||||
Jwcricient on the ground conditions. For this example, |
||||||
|
um economic length of pile is assumed to |
mum requirement of 372 mm 2 . |
|
|||
1 0 |
. Therefore Nvo interlocked steel piles will be |
Now the electrode resistance can be determined |
||||
m |
|
|
||||
ujred to dissipate the current. |
using the formula given in CP 1013: 1965 for plate |
|||||
iie |
,4age is to assess the current carrying ca- |
electrodes: |
|
|||
1e1 |
|
|
||||
-„.H11; |
of ihe electrode material itself and the con- |
|
|
|||
to it. Using the short-circuit formula given |
R = — x |
— |
||||
|
||||||
'-;ection 4.3 l of this chapter, the minimum cross- |
4 |
A |
||||
|
area of steel to carry the earth fault current is |
|
|
,,ieu hated as follows: where Q = soil resistivity, Om
A = surface area of electrode, m 2
S |
|
|
( Of |
+ ) |
|
|
||
|
|
Iogn |
+ |
|
|
|
||
|
|
|
|
|
|
|
||
FOr eel: K = 78 and /3 = 202 |
|
375 ° C and |
||||||
for 1 = |
28 000 A, t = 1 s, |
Of |
||||||
25°C; |
|
|
|
|
|
|
|
|
|
28 000 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5= |
( |
375 |
+ 202 ) |
|
||||
|
|
|||||||
|
78 |
|
log, |
|
|
|
|
|
|
|
25 + 202 |
|
|
||||
|
|
|
|
|
|
S = 372 mm 2
considering the electrode itself, the total cross- -,: uional area for two steel piles is:
= 2 x 14 x [248 + (2 x 145)] = 15 064 mm 2
llov,e\.er, allowance has to be made for surface corro,ion of the electrode over the life of the station. 1:1:‘, will depend on a number of factors of which the ,,ignificant is the soil pH which should be es- :,,h1Hhed from soil surveys. For this example, it is as- •11111Cd that the corrosion reduces the electrode thickness h, 3 mm (1.5 mm per surface) over the station life.
I here rore after corrosion the cross-sectional area of ,N o piles is:
---- 2 x 11 x [248 + (2 x 145)] = 11 836 mm 2
19.9
R –
4V [(2 x 0.248) + (4 x 0.145)1 x 10 x 2
=1.90
To avoid an excessive rise of earth potential, an overall station resistance typically of less than 0.1 0 is required. Therefore, even with the eight proposed electrodes in parallel, an individual electrode resistance of 1.9 0 is not acceptable and the number of pile sections must be increased. Increasing the number of pile sections to 25 would result in an electrode 10 m long having a resistance of:
19.9 |
7r |
|
R = |
|
|
|
|
|
4 |
V [(2 x 0.248) + (4 x 0.145)1 x 10 x 25 |
|
= 0.54 |
|
|
The resistance of the remaining electrodes is then calculated assuming the same number of pile sections but using the soil resistivity appropriate to the location. For the purpose of this example let us assume that the remaining primary electrodes have resistances of 0.41, 0.51 and 0.49 0, and the secondary electrodes have resistances of 0.50, 0.58, 0.45 and 0.62 0. The overall station resistance is given by:
( 1 |
1 |
1 |
It can be seen that this is considerably in excess of !Ile required 372 mm 2 .
With respect to the connections from the earth cable , Litmection bar down to the earth electrode, it is nor- ,mal practice to use four 100 x 12 mm steel bars (as , hom,ri in Fig 6.124) to provide adequate mechanical trength. Again assuming 1.5 mm of surface corrosion
L)N•er the station life, the final cross-sectional area will he:
R1 |
R2 |
Rn |
|
|
|
|
( 1 |
1 |
1 |
1 |
1 |
||
R = |
|
|
|
|
|
|
0.41 |
0.51 |
0.49 |
0.50 |
|||
0.54 |
||||||
1 |
1 |
1 |
y |
|
||
|
|
|
|
|
|
|
0.58 |
0.45 |
0.62 |
|
|
|
|
R = 0.063 0 |
|
|
|
|
|
559

Cabling |
|
|
Chapter 6 |
|
|
|
|
||
|
|
|
|
|
Now assuming that the power station under consi- |
previously in Section 11.4.1. With respect |
to the c on, |
||
deration is some 3 km from the 400 kV substation, as |
nections to the pile, four 100 x 12 mm steel bars are |
|||
mentioned in Section 11.3.1 of this chapter, it should |
used as shown in Fig 6.125, these being shown t o be |
|||
be assumed that 30wo of the earth fault current returns |
of adequate size in Section 11.4.1. |
|
|
|
via the ground. The rise of earth potential (REP) at |
The resistance of a vertical rod type electrode can |
|||
the power station will therefore be: |
be obtained using the following formula given by Tagg |
|||
|
[29]: |
|
|
|
REP = 28 000 x 0.3 x 0.063 = 529 V |
R |
fc)/27r1_,] x [log, (8L/d) |
1] |
|
|
|
|||
This figure of 529 V is lower than the acceptance |
where Q = soil resistivity, Qm |
|
|
|
criteria of 650 V and gives a reasonable factor of |
|
|
safety. |
L = length of rod, m |
|
|
11.4.2 Cylindrical steel piles |
d = diameter of rod, m |
|
This example is based on a typical cylindrical pile having an external diameter of 1.05 m and a radial thickness of 6 mm. A typical arrangement is shown in Fig 6.125.
Reference should be made to Section 11.4.1 of this chapter for explanation of formulae and definitions where they are not given in this section.
Maximum allowable current density:
57.66 x 10 6 |
57.66 x 106 |
= |
V19.9 x 1 |
Q t |
= 0.17 x 104 A/m 2
Minimum length of pile required:
L
i xrxd
where d = external diameter of pile
L — |
|
28 000 |
— 5.0 rri |
|
|
||
0.17 |
x 104 x r x 1.05 |
Although the minimum length required for current dissipation is 5 m, it is proposed that a 10 m length be used to obtain a lower value of resistance.
Now considering the current carrying capability of the electrode material itself and the connections to
R |
19.9 |
x [log, (8 x 10/1.05) — 1] |
|
|
2 x r X 10 |
|
= 1 06 0 |
As discussed previously in Section 11.4.1, a value of resistance of 1.06 0 is considered too large for a mai n electrode. It will therefore be necessary to incredse the electrode length or put a number of electrodes in parallel.
The following method of dealing with electrodes in parallel is given by Tagg [291 The method uses the 'equivalent hemisphere' principle where the rod electrode is replaced by a hemisphere having the same resistance. The radius of this equivalent hemisphere is given by:
r = Li[log n (8L/d) — 11
where L = length of rod, m
d = diameter of rod, m
For two rods in parallel:
Resistance of rods in parallel |
1 + a |
|
|
|
|
Resistance of one rod |
2 |
where a = r/S and S = spacing of electrodes, m
And for three rods in parallel, arranged in a triangle:
Resistance of rods in parallel |
1 + 2a |
Maximum csa of pile = r(R 2 — r 2 ) r(525 2 — 519 2 )
= 19 679 mm 2
After corrosion csa of pile = r(523.5 2 — 520.5 2 ) = 9839 mm 2
This can be seen to be considerably in excess of the minimum requirement of 372 mm 2 that was derived
Resistance of one rod |
3 |
From the above formulae it can be seen that spacing S increases, a will tend to zero and
value of 0.5 for the ratio will be approached. However
whilst initial increases in the spacing give a |
good |
improvement in the ratio, very large spacings |
would |
be required to approach the ideal value. For practical purposes, setting the spacing equal to the rod length normally gives an acceptable design.
560

|
|
|
|
|
|
Earthing systems |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
ork is normally installed in the main control |
and other major plant are sized for a 3-second rating |
|
L'arth |
|
area where the bulk of C and I equipment is |
with a final conductor temperature of 325 ° C. |
||||
Ifil'ated. The instrument earth network is connected, |
The bonds for all other power plant are sized for |
||||||
|
|
c in |
, le point, to a relatively noise-free part of |
back-up protection which is typically up to 1-second |
|||
|
|
|
earth system. The reason for using a single |
rating. For 11 kV and 3.3 kV systems, the earth fault |
|||
|
|
aioii |
|||||
|
|
is [o a \.. oid circulating earth currents or |
current is normally restricted to 1000 A per infeed which |
||||
|
|
|
|
|
|||
|
|
earth fault currents flowing in the system which |
would result in a relatively small bond size. However, |
||||
|
|
result in interference. |
it is considered prudent to ensure mechanical integrity |
||||
[Iii |
instrument earth is distributed to all C and I |
in the event of a neutral earthing resistor itself haying |
|||||
equirmient, marshalling cubicles, local adapter |
a short-circuit. Under these circumstances of a double- |
||||||
|
|
|
|
|
using a combination of earth cables and the |
fault, i.e., both main protection and neutral earthing |
|
|
|
ek2..tnultipair cables. A general arrangement of |
resistor failing, some damage to the PVC cable sheath |
||||
|
|
|
|
|
is shown in Fig 6.127. It can be seen from |
is accepted and the cables are sized for 1-second rating |
|
, H figure that the screens of multipair cables are |
with a final temperature of 325 ° C. On the 415 V |
||||||
..vonected to the instrument earth at a single point. To |
system, the earth fault current is not restricted and |
||||||
ep |
interference to a minimum, it is preferred that |
therefore the earth cables are sized for 1-second rating |
|||||
|
|
|
|
|
with a final conductor temperature of 160 ° C, to ensure |
||
•he oN,olt rail(s) of internally-generated power supplies |
|||||||
connected to the instrument earth. The PAX and |
they are not damaged for faults cleared by back-up |
||||||
jp,v (direct wire) telephone systems should also be |
protection. |
||||||
_onnected to the instrument earth network. |
For fuse-protected circuits it is traditional to use |
||||||
It should be noted that the armours of rnultipair and |
an earth bond size of not less than half the phase |
||||||
.nIticore cables are not connected to the instrument |
conductor size. In all cases the minimum bond size |
||||||
|
network, but single-point bonded to the station |
allowed is 4 mm 2 to ensure mechanical integrity. |
|||||
c ,trth network. The reasons for this are twofold. Firstly, |
The bond sizes for these conditions are calculated |
||||||
'here is a risk of cable armours becoming accidentally |
as follows, using the formula given in Section 4.3.1 of |
||||||
,hortecl to equipment cases and if the armour were |
this chapter. It should be noted that, for economic |
||||||
„innected to the instrument earth this would defeat |
reasons, the calculated value has been reduced down to |
||||||
he single earth point connection policy for that system. |
the nearest cable size. This is particularly the case for |
||||||
'.‘2,..ondly, many multicore cables emanate from switch- |
3-second ratings because in practice this fault duration |
||||||
ter |
|
local panels where an instrument earth will not |
is unlikely ever to be reached. |
||||
readily available and therefore it is more convenient |
(a) II kV, 750 MVA system |
||||||
11,1 cheaper to use station earth. |
|||||||
|
|
|
|
|
|
For aluminium cables, constant K = 148 and 13 |
|
115.3 Earth bond cable sizes |
= 228 |
||||||
mn the same basis as that already discussed for the |
Therefore, for a short-circuit duration of 3 |
||||||
.11,iin network earth cables, the bonds to switchgear |
|||||||
seconds: |
Flo. 6.127 Single-point earthing system for C and I cables
563

Cabling |
Chapter 6 |
|
|
|
|
S — |
|
|
|
|
K |
lov r, [(Or + 0)/(0, + i3)] |
|||
39 400 |
|
|
|
|
3 |
|
|
||
|
|
|
|
|
148log„ 0325 + 228025 + 228)]
=521 mm 2
For a short-circuit duration of 1-second:
39 400 .\/ |
1 |
S —
148V log o [(325 + 228)/(25 + 228)]
=301 mm 2
For the 3-second rating, the nearest rationalised cable size of 500 mm 2 is selected to bond plant. For switchgear the 3-second rating is met by using two 300 mm 2 cables, one connected to each end of the switchgear earth bar.
For motors, other plant and cable gland bonds where a I-second rating is required, a 300 mm 2 earth cable is used. Alternatively, for cable gland bonds, aluminium bar having the same cross- sectional area may be used.
(b) 3.3 kV, 250 MVA system |
|
|
||
For aluminium cables, constant I< = 148 and 0 |
= |
|||
228 |
|
|
|
|
Therefore, for a short-circuit duration of |
3 |
|||
seconds: |
|
|
||
|
|
|
|
|
43 700 \i/ |
|
3 |
|
|
|
|
—
148log o [(325 + 228)/(25 + 228)]
=578 mm 2
For a short - circuit duration of 1 -second:
43 700 \I
148log e [(325 + 228)/(25 + 228)]
=334 mm 2
For the 3-second rating, the nearest rationalised cable size of 500 mm 2 is selected to bond plant. For switchgear, the 3 - second rating is met by using two 300 mm 2 cables, one connected to each end of the switchgear earth bar.
For motors, other plant and cable gland bo nds where a 1-second rating is required, a 300 rn ni z cable is used. Alternatively, for cable gland bond s, aluminium bar having the same cross-sectional area may be used.
(c)415 V, 31 MVA system
For aluminium cables, constant K -= 148 and 3
=228
Therefore, for a short-circuit duration of 3 seconds and a final conductor temperature of 325 ° C:
43 100 ,\,/ 3
S
148log i, [(325 + 228)/(25 + 228)]
=570 mm 2
For a short-circuit duration of 1-second and a final conductor temperature of 160 ° C:
43 100 V |
1 |
S —
148log, [(160 + 228)/(25 + 228)1
=445 mm 2
For a short-circuit duration of 1-second and a final conductor temperature of 325 ° C:
43 100 V
s=
148log o [(325 + 228)/(25 + 228)1
=329 mm 2
For the 3-second rating, the nearest rationalised cable size of 500 mm 2 is selected to bond plant. switchgear the 3-second rating is met by using two mm 2 earth cables, one connected to each end of switchgear earth bar.
For motors and other plant where a 1 -second rating is required, a 500 mm 2 earth cable is used. For cable gland bonds, aluminium bar should be used and since this can be operated at 325 ° C without harm, the crosssectional area required is 300 mm 2 .
11.5.4 Plant bonding arrangements
This section gives specific plant bonding arrangements which are based, where appropriate, on the fault levels and calculated cable sizes given in the previous Sub- section.
Plant bonding arrangements for electrical |
system |
|
|
neutral earthing are as follows: |
|
564

|
Generator transformer neutral earthing The gen- |
||
• |
m transformer HV neutral connection should |
||
cra |
E of an earth cable connected from the earthy |
||
|
,: ori ,is |
||
|
of the neutral CT direct to the adjacent generator |
||
|
:Faw,fortner earth electrode. The cable size is to be |
||
|
_11,:ulaJed using the full 400 kV earth fault current |
||
|
L.r ,: i„ding, on-site generation) for a fault duration |
||
• |
|
and unit transformer neutral earthing The |
|
|
and |
unit transformer LV neutral earthing |
|
|
,. onneL:tions |
shall be a 500 mm 2 earth cable, con- |
|
|
the transformer neutral earthing re- |
||
|
rs:c[ed |
from |
|
|
.1,tors |
onto |
the local earth network. |
Atransformer neutral earthing The 3.3 kV
•:-.insformer neutral earth connections should be by
means of a 500 mm 2 earth cable connected from the [rar4ormer neutral earthing resistors, either direct to an adjacent earth electrode or to the station earth
uetwork, v,hichever is the nearer.
• 4i5 V transformer neutral earthing |
The 415 V |
|
|
;r ansformer neutrals should be connected to earth |
|
he 415 V switchgear, a connection being made |
, ,:: -ect) the switchgear neutral and earth bars via a !i nk.
i'lint bonding arrangements for earth connections to plant are as follows:
• |
Generator earth bond network |
The generator earth |
|||
|
bond network |
consists of an earth bar mounted |
|||
|
;II parallel with the main generator connections to |
||||
|
miich all items of plant operating at generator |
||||
|
‘oltage are bonded. This earth bar is connected to |
||||
|
arth at the generator |
transformer earth electrode |
|||
|
Li•i u two 500 mm 2 earth cables. |
||||
• |
Sration transformers The earth terminals of these |
||||
|
iransformers are connected to the station earth net- |
||||
|
'ark by means of a 500 mm 2 earth cable. |
||||
• |
II 3.3 kV ancillary transformers The earth ter- |
||||
|
iiinals of the ancillary transformers are connected to |
||||
|
!he station earth network by |
means of a 500 mm 2 |
|||
|
earth cable. |
|
|
|
|
• |
Gas turbine generator stator, |
VT cubicle and liquid |
|||
|
wurral earthing resistor |
These items of plant are |
|||
|
onnected direct to the station earth network by |
||||
|
means of a 500 mm 2 earth cable. |
||||
• |
likV switchgear |
The earth |
bar of 11 kV switch- |
||
|
fear is connected to the |
main station earth network |
|||
|
l)!, means of two 300 mm 2 earth cables, one cable |
||||
|
1,emg connected to |
each end of the bar. |
|||
• |
1 I kl / motors |
The earth terminals of 11 kV motors |
|||
|
|
||||
|
are connected to the 11 |
kV switchgear earth bar by |
|||
|
means of 300 |
mm 2 cable, the cable being routed |
|||
|
ith the II kV |
power cables. |
|
Earthing systems
In addition, a 150 mm 2 bond is to be provided between the motor and adjacent plant and structural (or other) steelwork to which personnel may make simultaneous contact.
• II kV/415 V gas turbine unit transformers The earth terminals of these transformers are connected to the station earth network by means of a 500 mm 2 earth cable.
•3.3 kV switchgear For switchgear connected to a transformer and not fuse-protected, the switchgear earth bar is connected to the main station earth network by two 300 mm 2 earth cables, one connected to each end of the bar.
For switchgear fed by fuse protected cables, the power cable armours will be utilised to provide the earth return path. A cable gland bond, of crosssection not less than half that of the power cable core, being provided between the gland and the switchgear earth bar with the exception of single-core power cables which utilise a 300 mm 2 bond.
•3.3 kV motors For 3.3 kV motors fed by three single-core power cables, an earth return cable of 300
mm 2 cross-section is provided from the motor earth terminal to the supply switchgear earth bar. The earth cable should be laid in proximity to the power cables..
When the motor is fed by a multicore cable, the cable armour is utilised to provide the earth return path, connection being trade to the cable armour from the motor earth terminal by a bond of crosssection not less than half that of the power cable core.
In addition, local bonding is provided between the motor earth terminal and adjacent plant, and structural or other . steelwork to which personnel may make simultaneous contact. The size of bond shall be half that of the power cable core cross-sectional area.
• |
3.3 kV diesel generators |
-- |
the 3.3 kV diesel gen- |
||
|
erator stator frame is connected to the station earth |
|
|
network by means of a 500 mm 2 earth cable. |
|
• |
3.3 kV diesel generator harmonic suppressors If |
|
|
harmonic suppressors are provided on the 3.3 kV |
diesel generators, their tanks are to be connected to the station earth network by means of a 500 mm earth cable.
•3.3 kV diesel generator neutral earthing resistors
The 3.3 kV diesel generator liquid earthing resistor tanks are to be bonded to the station earth network by means of a 500 mm2 earth cable.
•415 V switchgear For switchgear fed by single-core cables, the switchgear earth bar is connected to the main earth network by means of two 300 mm 2 cables, one connected to each end of the bar.
For switchgear fed by fuse-protected multicore cables, the power cable armouring is utilised to pro-
565
Cabling |
Chapter 6 |
|
|
|
|
vide the earth return path. A cable gland bond of cross-section not less than half that of the power cable core is provided between the gland and switchgear earth bar.
• Transformers having 415 V low voltage windings
Transformers of 1 MVA rating and larger have a 500 mm 2 cable connection between the transformer earth terminal and the 415 V switchgear earth bar.
Transformers of rating in the range 0.5 to 0.8 :VI VA have a similar connection of 300 mm 2 crosssection.
Transformers of rating less than 0.5 MVA have a si milar connection of cross-section not less than one half that of the power cable core.
•415 V plant other than switchgear and transformers
For plant within this range fed by a multicore cable the cable armour shall be utilised as the earth return. The gland bond size between the plant and the gland shall be of cross-section not less than half that of the power cable core, with a minimum cross-section
of 4 mm 2 .
When the plant is fed by single-core cables, an earth return cable of 300 mm 2 cross-section shall be provided from the equipment earth terminal to the supply switchgear earth bar. The earth cable shall be laid in close proximity to the single core power cables.
Any plant which is fed by a conduit or trunking system shall also have an earth cable included in the conduit of the same cross-section as that given by the above criteria.
For motor circuits of 1.5 kW and above, additional local bonding is provided between the motor and adjacent plant and structural or other steelwork to which personnel may make simultaneous contact. The bond size should not be less than half that of
the power cable core, with a minimum size of 4 mm 2 .
•Control and instrumentation marshalling boxes and cubicles The steelwork of all panels, marshalling
)oxes and the like should be bonded to the station earth network using 4 mm 2 earth cable. Where equipment is mounted directly onto earthed metalwork, no bond is necessary.
Where a power cable is taken into a panel, the cable armour is bonded to the panel and a separate bond to the station earth network is not required.
Plant bonding arrangements for insulated cable glands of the type described in Section 9.1 of this chapter are normally used for both power and control cables. This means that where a connection is required to the cable armour, a bond has to be connected from the gland integral earth tag to the equipment earth bar/stud or other glands as appropriate. In order to ,pass this information to site, a series of bond codes is used. The gland bond codes are recorded on the block cable dia-
grams and also on cable schedules and work cards used on site. A list of typical bonding codes is as follows:
•11 kV, 3.3 kV, 415 V power cables and multicore control cables
Earthed: A The armour is connected to the station earth or, where applicable, the equipment earth stud.
Floating: B The armour is insulated from earth. If the cable has a screen then this also is insulated. An insulating shroud is fitted over the gland body.
•Multipair cables
Earthed: H The armour is connected to the station earth system and the cable screen is connected to the instrument earth system.
FIn situations such as outbuilding control panels where a separate instrument earth system is not available, both armour and screen are connected to station earth.
Floating: B The armour is insulated from earth. If the cable has a screen then this also is insulated. An insulated shroud is fitted over the gland body.
PThe armour of 'digital control cables' is connected to the armours of other cables of the same discipline in the same box. The cable screen is connected to the screens of other cables of the same discipline in the same box.
RThe armour of 'analogue control cables' is connected to the armours of other cables of the same discipline in the same box. The cable screen is connected to the screens of other cables of the same discipline in the same box.
SSpecial requirement. To obtain the correct bonding information refer to the block cable diagram.
Actuator cables:
/ The armours of the actuator cables (composite power/control design) in the load centre are connected together and to the armour of the incoming multipair cable. The actuator cable outer screen and the incoming multipair cable screen are connected to the insulated screen bar in the load centre. The actuator cable inner screen is connected to station earth.
566