Добавил:
Опубликованный материал нарушает ваши авторские права? Сообщите нам.
Вуз: Предмет: Файл:
книги / 593.pdf
Скачиваний:
1
Добавлен:
07.06.2023
Размер:
5.94 Mб
Скачать

4. NATURAL GAS

Price regulation for the gas network

The CRU conducts a review of gas network costs every 5 years to set a 5 year revenue allowance for GNI transmission and distribution. This 5 year allowance is determined by reviewing the expenditures incurred by the network companies and the new business proposals, followed by a public consultation. Once the amount is fixed, the allowance is split into annual allowances that can be recovered through network tariffs with flexibility of adjustments. On average, around one-third of a domestic customer’s gas bill relates to distribution tariffs and 10% to transmission tariffs (CRU, 2018b).

The price control for gas – price control 4 – covers from October 2017 to September 2022, during which the CRU will monitor network companies’ compliance through their licence conditions.

Additionally, the CRU has set up targets to ensure more-efficient cost control. The targets are normally set at a 1% increase in cost efficiency. However, there could be an annual 0.75% addition based on GNI review. The CRU introduced a fiscal incentive that warrants a bonus if the connection target is exceeded, and a penalty for failure, to encourage more ambitious gas network connections for price control 4.

Gas entry/exit tariff reform

With operation of the Corrib gas field, the interconnectors between Ireland and the United Kingdom are no longer the primary supply source of gas, at least in the medium term. The reduced Moffat throughput implied an increase in its entry tariff per unit, pushing up the wholesale gas price in Ireland. The CRU therefore implemented a reform of the existing gas entry/exit tariff methodology, and a new regime has been in place since October 2015. Key changes include:

An entry/exit tariff split implemented at a 33/67 ratio instead of a 50/50 ratio.

Commodity charges apply as a single rate for all entry points and a separate single rate for all exit points. Commodity charges were previously calculated separately for each entry/exit point. The newly applied single rate is based on the new entry/exit tariff split (33/67).

A capacity/commodity split maintained at a 90/10 ratio, with an exit tariff.2

Infrastructure

Gas networks

The GNI operates the transmission (2 427 km) and distribution networks (11 527 km) in Ireland. The transmission network transports gas from the entry points at Moffat, Inch and Bellanaboy to the distribution networks and connected loads (e.g. gas-fired power generators). The GNI transmission network also supplies gas to Northern Ireland and the Isle of Man, which are both part of the United Kingdom (Table 4.2).

2 The tariff consists of a capacity and commodity charge that applies for use of the Northern Ireland transmission network system.

61

ENERGY SECURITY

IEA. All rights reserved.

4. NATURAL GAS

The Moffat entry point connects the GNI network to the national grid gas network in the United Kingdom and allows for gas imports to Ireland via two subsea interconnectors (IC1 and IC2) (Figure 4.6) The existing interconnectors do not allow Ireland to export gas to the United Kingdom because they are unidirectional. The landfall installations for the interconnectors entering Ireland are located close to Loughshinny for IC1 and Gormanston for IC2, in the east of Ireland. The Inch entry point connects Kinsale and Seven Heads gas fields to the onshore GNI network, and the Bellanaboy entry point connects the Corrib gas field to the onshore GNI network. The Northern Ireland gas network connects to the GNI network at Twynholm in Scotland and delivers gas to Northern Ireland via the Scotland Northern Ireland Pipeline (SNIP). The South-North Pipeline (SNP) is an onshore gas transmission pipeline from Gormanston to Northern Ireland.

The distribution network delivers gas to over 680 000 customers across Ireland, and the network has been extended to Nenagh and Wexford towns. GNI completed extension of distribution to Listowel in the south-west of Ireland in late 2018. Additionally, GNI also completed the network extension to Center Parcs in the county of Longford in late 2018.

Table 4.2 Major gas network infrastructure in Ireland

 

Infrastructure

 

Function

Capacity (GWh/d)

 

 

 

 

 

 

 

 

Entry point to GNI system serving Ireland via the

342

 

Moffat entry point

 

onshore system in Scotland and subsea

 

 

 

interconnectors IC1 and IC2

 

 

(Scotland, United Kingdom)

 

 

 

 

 

Also serves Northern Ireland via Twynholm

 

 

 

 

installation and SNIP

 

 

 

 

Physically unidirectional

 

 

 

 

 

 

 

South-North CSEP

 

Exit point to Northern Ireland, supplied from IC2

66.3

 

(Ireland)

 

 

 

 

Corrib gas field

 

Domestic production facility, began commercial

103.5

 

(Ireland)

 

operation in December 2015

 

 

 

 

 

 

 

Southwest Kinsale storage

 

Underground storage facility (depleted gas field),

27.3

 

(Ireland)

 

due to decommission in 2021

 

 

 

 

 

 

Notes: CSEP = connected system exit point. GWh/d = gigawatt hours per day.

Source: Ireland country submission, 2018.

LNG terminal

Ireland does not yet have an LNG terminal. There is a commercial proposal to construct the country’s first LNG regasification terminal in the Shannon Estuary, on the south-west coast of Ireland. Shannon LNG Ltd received planning permission in 2008 for its proposed LNG terminal and for the associated transmission pipeline to deliver gas into Ireland’s transmission system. In 2017, the Shannon LNG terminal was included in the European Commission’s third list of the projects of common interest (PCIs).If Shannon LNG Ltd decides to take a final investment decision in 2018, the earliest possible start date for commercial operation of an onshore facility would be 2021. The initial phase will include construction of the LNG processing tanks and regasification facilities, with a maximum export capacity of up to 191.1 GWh/d (17.0 million standard cubic metres per day).

62

IEA. All rights reserved.

4. NATURAL GAS

Figure 4.6 Map of natural gas infrastructure

UNITED

KINGDOM

Derry

City- --y""'-

l.iravad

ENERGY SECURITY

United

Kingdom

North

Atlantic

Ocean

UNITED

KINGDOM

Seven Heads gas field

 

km

 

0

50

100

 

Existing gas pipeline

 

Proposed LNG terminal

Gas treatment terminal

Planned compressor station

Existing compressor station

Gas field

This map is without prejudice to the status of or sovereignty over any territory, to the delimitation of international trontiers and boundaries and to the name of any territory, city or area.

63

IEA. All rights reserved.

4. NATURAL GAS

In July 2017 NextDecade (an LNG export company in the United States) signed a memorandum of understanding with the Port of Cork company to study the possible development of a floating storage and regasification unit (FSRU) and the associated LNG import terminal infrastructure in Cork, in the south of Ireland.

The development of an LNG import terminal, either an onshore facility or an FSRU, would substantially improve the SoS in Ireland by providing direct access to the global LNG market and diversifying gas imports.

Storage facilities

The Southwest Kinsale storage facility was a gas production and seasonal storage facility located off the southern coast of Ireland with a working volume of 230 million standard cubic metres, about 5% of Ireland’s annual gas consumption in 2016/17. After it was depleted, the Southwest Kinsale field became Ireland’s first offshore gas storage facility and operated from 2001 to 2017. Gas injection has ceased since then, and production of cushion gas is also expected to cease in 2020; the field will be decommissioned in 2021. There was no other gas storage facility in operation in Ireland as of 2018.

The decision to stop gas storage operation in the Kinsale reservoirs was a commercial one. The GNI and EirGrid conducted a long-term resilience study in 2018 to assess Ireland’s resilience to a prolonged gas supply disruption. This was to feed into an evaluation of risks and options to deal with gas supply disruptions, including the possible role of gas storage (GNI, 2018b).

Infrastructure developments

The European Commission supports key energy infrastructure projects known as PCIs to improve gas supply security and create an integrated energy market. One Irish gas infrastructure project was on the first PCI list and was completed at the end of 2018. There are two projects on the current third PCI list (Table 4.3).

Table 4.3 Irish gas infrastructure development projects under the PCI, 2017

Project

Project

Aim

Status

 

promoter

 

 

Twinning of South

GNI (UK) Twin unparalleled section of

Funding provided by Connecting

West Scotland

Ltd

pipeline

Europe Facility (30%) and regulatory

Onshore System

 

Increase Moffat capacity to

capital allowance

(SWSOS)

 

375 GWh/d

 

(first PCI list)

 

 

 

Physical reverse

GNI (UK)

Make Moffat entry point

Feasibility study ongoing

flow at Moffat

Ltd

bi-directional

Funding provided by Connecting

(third PCI list)

 

 

Europe Facility (50%)

Shannon LNG

Shannon

Construct LNG process tanks and Planning permission received

(third PCI list)

LNG

regasification facilities with a

Earliest commissioning in 2022, if a

 

 

maximum export capacity of

final investment decision is taken by

 

 

191.1 GWh/d

in 2019

Source: Ireland country submission, 2018.

Another project under consideration is the physical reverse flow (bi-directional) of the SNP, led by GNI (UK) Ltd, but not as part of the PCI. The decision of the United Kingdom

64

IEA. All rights reserved.

Соседние файлы в папке книги