Добавил:
Опубликованный материал нарушает ваши авторские права? Сообщите нам.
Вуз: Предмет: Файл:
учебный год 2023 / Cartwright_Hesselink_Precontractual_Liability_in_European_Private_Law.pdf
Скачиваний:
8
Добавлен:
21.12.2022
Размер:
2.63 Mб
Скачать

case 10: public b idding

281

value of the contract for the swimming pool appears very unlikely to be high enough to fall within the scope of the Regulations.20

Finland

There is a document of self-regulation of the Finnish building industry that is of importance in this case, entitled The Principles of Competitive Bidding on the Building Branch, published in the Building Information Foundation series (RT 16–10182).21 The purpose of the Principles is to define good building and construction practices in using competitive bidding, and they are meant to be binding both on the builder and on the contractor.22 The Principles are based on negotiations between central organisations of the industry, representing both builders and contractors.

The Principles are not public legislation. However, they are considered to be an expression of good practice in building and construction, and as such they can have some degree of bindingness. Court practice confirms that they bind parties if the builder has published a statement that they will be followed in the competitive bidding.23 In KKO 1998:48 the builder had committed itself to follow the Principles of Competitive Bidding RT 16–10182. After opening the bids it had, contrary to the Principles, negotiated with bidders and accepted a new lower bid made by another bidder. The original lowest bidder was entitled to compensation for the loss in losing the contract, measured by the so-called positive interest.

Of course, the Principles are not compulsory norms, and the parties may agree upon the application of different rules. In this case, A’s published statements of the rules of the bidding process, on the one

20The Regulations do not apply to contracts where the estimated value of the contract (net of VAT) is less than a defined threshold, currently (for public works contracts) E5,150,000: reg. 8.

21The Building Information Foundation (RTS) is Finland’s leading information service for the building and construction sector. Its mission is to foster and promote good planning and construction practices as well as sound property management procedures. It is a private foundation with representatives from 42 Finnish building organisations. It publishes the RT Building Information File (RT ¼ building information), which is updated regularly.

22See s.1.

23Court decisions, even those issued by the Supreme Court, are not considered to be legally binding in Finland. But in fact they often have great authority, and especially important precedents with thorough reasoning are followed in court practice. On the status of precedents as a legal source in Finland, see e.g. Aarnio, Laintulkinnan teoria

[The Theory of the Interpretation of Statutes], p. 230ff.

282 precontractual liability in european private law

hand, and submission by contractors of bids following the rules, on the other hand, can be considered as making an agreement between the parties on the application of those rules in the competitive bidding. Very little is said in the case about the content of the applicable rules, apart from A’s statement that the contract will be given to the lowest bidder. As no differences from the Finnish Principles are indicated in the case, the Principles may be worth citing as examples of how questions of good bidding practice are regulated in them.

According to the Principles, the equal treatment of bidders has to be ensured in dealing with the bids.24 The builder must not negotiate with a bidder to alter the bid price. The most profitable bid has to be accepted. All bids can be rejected only if the most profitable bid price is too high or the building project has to be suspended for good reasons or there are other special reasons for it.25 The profitability of bids should in general be assessed on the basis of contract price. According to section 7.4 the builder should choose among acceptable bids the most profitable taking into account economic, technical and functional criteria. A bid should be rejected26 if (1) the bid price is ambiguous or the bid is otherwise defective or incorrect; or if (2) after the call for bids, it has become evident that the bidder is considered to lack technical, economic or other qualifications to carry out the contract. A bid should also be rejected if (3) the bidder has acted dishonestly or its behaviour is contrary to good construction practice in the competitive bidding. In addition, a bid can be rejected if the bid price compared with the estimated building costs is so low that it is evident that the work cannot be carried out at the price indicated.

The rules agreed upon between the parties and, secondarily, general rules of good practice in competitive bidding are standards for judging the parties’ behaviour and their possible fault. Instead of culpa in contrahendo, we should perhaps speak about culpa in contractu as the applicable basis of liability. A breach of the agreed rules could be considered as a breach of contract between the parties. Accordingly, the standard of measuring the loss should be the positive interest rather than the negative interest. In the case from the Finnish Supreme Court, referred to above, it was the positive interest that was applied.

The positive interest aims to put the injured party into a position that is economically equal to the proper performance of the contract, meaning in this case the proper application of the agreed rules. The

24 Section 7.1. 25 Section 7.3ff. 26 Section 7.3.

cas e 10: pub lic b idding

283

prima facie positive interest of the lowest bidder is the economic value to it of the contract on the basis of its bid because according to the rules it is entitled to be awarded the contract unless any of the contrary reasons mentioned above exists. The only item of loss that is mentioned in the case, however, is the expenses incurred in preparing the bid. These are in principle not included in the positive interest. But if the value of the contract exceeds (or at least equals) the bidding costs, as is usually the case, the lowest bidder should of course have these costs compensated on the basis of the positive as well as the negative interest.

The positive interest of a bidder other than the one who is entitled to the contract is usually zero in spite of any fault on the other side. This is because it would not have been awarded the contract and thus would not have its expenses covered even if its bid had been treated properly. The application of the negative interest would not give a different result because there is no loss that would have resulted from an act by the liable party.

A pivotal fact is that A has promised to give the contract to the lowest bidder. A breach of this promise is no doubt wrongful unless there are reasons to reject the lowest bid (for example, those mentioned in the Finnish Principles: see above). Choosing another bid could perhaps also be acceptable if it appears to be the most profitable taking into account, besides the price, all other economic, technical and functional criteria. However, the reasons mentioned in the case for not choosing B’s bid indicate no proper grounds for either rejecting it or accepting another bid.

In situation (i), B’s bid was the lowest one but either (a) it was not properly considered by A because of an administrative error or (b) A always intended to give the contract to C. The latter alternative (b) is a case of intentional breach of agreed rules. Also the former (a) falls within A’s control and thus indicates its fault. So both are cases of fault and constitute a basis of A’s liability. As the lowest bidder, B was in a position which, according to A’s promise, entitled it to get the contract. Only if A can show that the contract should not have been given to B, for example for the reasons set out above, can A avoid liability to B.

In situation (ii), B’s bid was not the lowest but it was not properly considered by A because of an administrative error. As discussed above, an administrative error is regarded as wrongful. However, this case is more complicated because B’s bid was not the lowest one and so it had no prima facie right to the contract. Only if B can show that according to the applicable rules the contract should have been granted to it and not

284 precontractual liability in european private law

to the lowest bidder can it be considered to have a right to the contract. According to the Finnish Principles, in considering this question all economic, technical and functional criteria can be taken into account.

So, in all of cases (i)(a) and (b) and (ii) there is the fault required for A’s liability. The liability is measured according to the positive interest. If B can be considered to have had the right to the contract, which is the case as a rule in situation (i) but not in situation (ii), its positive interest includes the value of the contract to it. If only the bidding expenses are claimed, in general they can be compensated on this basis (see above). If B did not have the right to the contract – this is the case probably in situation (ii) – then it would not be entitled to any compensation from A.

If A is a public authority the legislation on public procurement will be applied. The Finnish Act on Public Procurement (APP,1992) is applicable, amongst other things, to procurement by the state and the communes (local communities responsible for public administration). If the value of the procurement equals or exceeds the threshold value defined in a special decree,27 more detailed rules based on EU legislation will apply. The purpose of the APP is to promote competition and ensure the equal and non-discriminatory treatment of those who take part in the competitive bidding. The exceptions to the scope of the APP are not relevant in this case. According to the APP,28 a building project may not be carried out as own work without competitive bidding if state subsidy relating to a particular project is granted to the project and the cost estimate (including VAT) of the project equals or exceeds FIM5,000,000.29 Exception may be made only for special reasons, such as the small value of the procurement.

The APP contains detailed provisions30 on proper grounds for excluding a bidder from the procedure (such as lack of technical, economic or other qualifications or omission to pay taxes or social security fees). The bidders have to be treated equally and in a non-discriminatory manner in all phases of the procurement. According to section 7, the procurement has to be made as profitably as possible. The bid that is the most profitable in the light of all economic aspects, or the cheapest, should be accepted. There is also a special provision on damages liability.31 Liability

27Decree on Public Procurement and Building Contracts Exceeding the Threshold Value, 1998. The threshold value expressed in ECUs (without VAT) is that corresponding to 5m special drawing rights.

28Section 5. 29 Around E850,000 or £575,000. 30 Section 6. 31 APP, s. 8.

cas e 10: pub lic b idding

285

is imposed upon anyone who causes loss to a bidder or a supplier by an act that is contrary to the APP or statutes or provisions issued by virtue of it, or contrary to EU legislation or a WTO agreement on public procurement. If the claim for damages concerns the costs that have been incurred in the procedure, it is sufficient for the bidder to prove the wrongful act and that it would have had a real chance to get the contract if the correct procedure had been followed.

The main significance of the APP for civil law liability is in establishing the conditions of liability precisely but the provisions contain nothing that would be radically different from the rules applicable to competitive bidding in the private sector. The correct procedure is defined in law, and acting contrary to the provisions evidently constitutes fault that is required for compensation. It is clear that the facts indicated in the case as reasons for not choosing B’s bid constitute breaches of these legal provisions.

Moderating the plaintiff’s burden of proof as mentioned above can help the bidder to get compensation, especially in situation (i). For this, it is sufficient that it proves the incorrect act and that it would have had a real chance to get the contract in a correct procedure. The incorrectness of the procedure is proved, and in situation (i) it seems easy for B as the lowest bidder to prove its real chance of getting the contract. Of course, A can bring counter-evidence to rebut B’s right. But in situation (ii), the application of the APP does not seem to alter B’s situation from that in private sector bidding, because it would in any case have to bring evidence that it had a real chance to get the contract.

The APP contains also administrative means of satisfying the bidder for incorrect acts in competitive bidding.32 The Market Court (which deals with cases pertaining to competition or marketing law) may quash the decision of the procurement unit or issue an order to correct the procedure. If these measures would cause the other parties, third parties or the public interest harm that would exceed the benefits of the measure, the Market Court may order an indemnity to be paid to a party that would have had a real chance to win the competitive bidding if the procedure had been correct. The indemnity is not a civil law remedy but an administrative fee. It is not aimed at compensating the actual loss, nor do its preconditions correspond to those of compensation for loss. However, the quality of the fault in the procedure, the total value of the procurement and the

32 Section 9.