- •Introduction
- •2. Calculating and graphic works №1. Determination of the annual electricity demand, building the load graphs and selection of equipment
- •2.1 Determination of the annual electricity demand
- •2.2 Building a summer and winter daily grid load graphs
- •4.3 Determination of the maximum amount of power of pSs and selection of electricity generators of the different types of stations for covering the load of region
- •Conclusion
- •List of References
- •17. Приказ №228-од от 29 августа 2007 года «Об утверждении Правил организации и функционирования централизованных торгов электрической энергии в Республике Казахстан».
- •18. Методические указания по проведению централизованных спот–торгов электрической энергией в течение операционных суток. Утверждены приказом № 13 от 29 февраля 2008 года ао «корэм».
MINISTRY OF EDUCATION AND SCIENCE OF THE REPUBLIC OF KAZAKHSTAN ALMATY UNIVERSITY OF POWER ENGINEERING AND TELECOMMUNICATION
Department of Economics, organizations and management of industry
Discipline “Economics and Organization of Production”
CALCULATION-GRAPHICAL WORK №1
The theme:“The main technical and economic calculations of the energy production”
Specialty: 5B071800- Electrical power engineering
Done by:Shaimuradov E. Group: EPEe-15-11 Student’s surname & initials academic group code
Checked by: docent Tuzelbayev B.I. Teacher’s academic degree, rank, surname & initials
__________ ___________________ «____» ________________2017 y. Score Teacher’s signature Date
Introduction
Summarize the energy sector economy and the problems of the power companies in the market. Characterize the technical and economic indicators of power companies.
Show the organizational chart of the functioning of the electricity market in Kazakhstan. Identify the key problems in the organization and functioning of the electricity market.
The variants for data students to carry out CGW select from Tables 1, 2, 3 of Annex A on the last two digits of Gradebook.
Released during the year, MW*h. |
Network losses, % |
Fuel |
|
Franco-consumer tenge / t.n.t |
Calorific value kcal /kg.n.t |
||
11872 |
10 |
3770 |
4550 |
Consumed by sectors of the National economy, % |
|||
Industry |
Municipal households |
Agriculture |
Transportation |
64 |
10 |
10 |
6 |
2. Calculating and graphic works №1. Determination of the annual electricity demand, building the load graphs and selection of equipment
2.1 Determination of the annual electricity demand
Total annual demand for electricity in the planning year in the established power system is based on:
- Actual electricity system subscribers for the year;
- The proportion of consumers in the annual consumption of electric power;
- Annual growth of electricity power system subscribers;
- Electricity losses in networks.
W = Wnet + Wlosses , МW·h/year, (1)
where Wnet, - the planned net supply of electric energy by-industries
Wlosses – electricity losses in networks.
Formula (1) can therefore be written as:
W = Wind+ Whous + Wagr + Wtran + Wlosses, (2)
where Wind – industries;
Whous – household consumers;
Wagr – agricultural production;
Wtran – electrified transport.
The necessary input data for determining the efficiency of the planned vacation in electricity production is given in Annex A.
Table 1.1 – The share of consumption sectors
The share of consumption and the number of industries use |
||
Branch |
The share of total consumption,% |
The number of hours of use, h |
Industry |
54 |
6500 |
Municipal house-holds |
15 |
3500 |
Agriculture |
10 |
3600 |
Transportation |
12 |
5500 |
Network losses |
9 |
8760 |
Table 1.2 – Power requirements for branches
Annual demand and daily maximum |
|||
Branch |
Annual
|
Daily winter maximum MWh |
Daily summer maximum MWh |
Industry |
7598 |
1101,16 |
825,87 |
Municipal house-holds |
1187,2 |
349,18 |
261,89 |
Agriculture |
1187,2 |
339,2 |
254,4 |
Transportation |
712,3 |
118,72 |
89,04 |
Network losses |
1187,2 |
135,53 |
101,65 |